4.2 Schedule Management Flashcards

1
Q

Definition of a schedule

A

Timetable showing start and finish dates for project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Definition of scheduling

A

Identify activities and durations, accounting for requirements and resource availability to determine the overall project duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Definition of scope

A

Totality of outputs, outcomes, and benefits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Definition of outputs

A

Tangible or intangible products produced by the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Definition of outcomes

A

The change following transition and adoption of outputs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Definition of benefits

A

Positive measurable and quantifiable impact of the outcomes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Definition and features of a product breakdown structure

A
  • Structured method to identify output deliverables (using nouns)
  • Each entry has a unique identifier
  • Generated through workshop or individual sessions
  • Aligns specification with actual products
  • Forms part of the agreement and control of scope
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Definition and features of work breakdown structure

A
  • Structured method to identify work required to deliver all the products (using verbs)
  • Lowest levels define work packages
  • Defines baseline scope of work
  • Defines part of overall success criteria (along with schedule and budget)
  • Each lower level is a breakdown of the level above
  • WBS includes everything that is in scope
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Definition and features of work packages

A
  • Level of definition or unit of work for which budget is estimated
  • Discrete estimates associated with each package
  • Allocated to an accountable individual
  • Should be discrete, self-contained, without overlap
  • Should have unique numbering or ID
  • Should be short enough so activities can be measured
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Definition and features of cost breakdown structure

A
  • Hierarchically structured method to identify all project costs expected
  • Categories include labour, equipment, materials, expenses, consumables
  • Aligned with the WBS and OBS to assign budgets to work packages
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Definition and considerations of BAU Relationships

A
  • Acknowledge and manage interactions
  • Ensure project is not impacted by BAU activities
  • Stakeholders
  • Scope definition
  • Business change
  • Dependencies
  • Schedules
  • Costs
  • Quality
  • Risks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Definition and features of precedence diagram

A
  • Map of the logical dependencies between activities based on WBS
  • Lowest level work packages become nodes
  • Forward pass fills in the early start and finish of each task
  • Backward pass fills in the late start and finish of each task to establish float
  • Calculate total float
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Definition and features of critical path

A
  • Shortest sequence of activities from start to finish
  • Defines overall duration of the schedule
  • Identifies all activities that if delayed would affect the end date
  • Need to identify all dependencies, activity duration, and float
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Definition and features of Gantt chart

A
  • Visual representation of the precedence diagram
  • Communication tool for portraying progress
  • Relate the relative timings of the precedence diagram
  • Shows relationships and critical activities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Definition and features of critical chain

A
  • Resource based approach to scheduling
  • Protects critical path activities with addition of buffers
  • Real world factors influence work rate
  • Add a buffer at the end of a chain of activities to half the duration of each activity
  • Reduce the estimated duration of each activity in the chain by half
  • Buffer averages the impact of tasks finishing earlier or later than planned
  • Provides allowances for estimates being different to the probability of actual duration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Definition and features of estimating techniques

A
  • Impossible to know exactly how long an activity will take
  • Parametric estimating
  • Analogous estimating
  • Analytical estimating
  • Delphi technique
17
Q

How to improve estimations

A
  • Involve the project team
  • Validate assumptions as more is known
  • Manage risk and drawdown contingencies
  • Report variance
18
Q

Definition and features of re-estimations (and when it is required)

A
  • Revision to estimated durations as real data is available
  • Assumptions prove incorrect
  • Actual resource capacity is different to expected
  • Changing external factors
  • Unnecessary contingency included in estimations
  • Subjectivity of individuals or pessimistic bias
  • Lack of data or technical knowledge
19
Q

Stages of re-estimation

A
  1. Concept
  2. Definition
  3. Deployment
  4. Transition
  5. Adoption