Test 6.1 Flashcards
2 NEXT
You are managing a waterfall project. In the middle of the project the customer asks you to revise the scope defined at the beginning of the project. As an experienced project manager what should you do?
SELECT THE CORRECT ANSWER
Deny the request as the scope of work was frozen during planning
Accept the request and update the project charter
Generate a change request and follow the change control process
Consult with your sponsor on the customer request
Correct Option:D
EXPLANATION
The customer wants to change the scope defined at the beginning of the project. That scope was a part of the project charter, which is the responsibility of the sponsor. Hence, the project manager needs to talk to the sponsor.
3 QUALITY
During the quality testing of the new software integration project, the results show performance variance from the quality management plan. Thus, the project manager asked the quality team to investigate the root cause of the variance and resolve it to get back on track. What type of action did the project manager request?
SELECT THE CORRECT ANSWER
Corrective Action
Preventive Action
Defect Repair
Project Tracking
Correct Option:A
EXPLANATION
Finding the root cause and taking action to bring the project back on track come under Corrective Action.
5 NEXT CLOSING
Your company decided to terminate your 24 months’ project in the 7th month of execution because of insufficient budget. What you should do as a project manager?
SELECT THE CORRECT ANSWER
You must meet the top management and convince them to reconsider their decision.
If the management decide to terminate the project, the project manager cannot do anything.
You must submit a report mentioning that you completed the project successfully as you have been delivering the deliverables on time for seven months.
You should transfer the finished and unfinished deliverables to the relevant stakeholders.
Correct Option:D
EXPLANATION
If the project is terminated as a result of insufficient budget, it is most likely a project exit criteria. The project manager should look at the project closing process, which includes handing over the deliverables to the relevant stakeholders.
6 AGILE
You joined in as the project manager of an ongoing hybrid project after 6 months of project start date. You heard the team members saying that despite a robust change control system, there are too many changes in the project and the requirements keeps changing. What should you do?
SELECT THE CORRECT ANSWER
Halt all the changes until you know the reason for the previously done changes
Consider changing the development approach
Update the change management plan
Tell the team that changes are normal in hybrid projects
Correct Option:B
EXPLANATION
If the requirements are changing too rapidly, the project manager should consider changing the development approach from hybrid to agile.
9 NEXT AGILE
You are the project manager of an ongoing agile software development project and you completed your second release. What should you do to prepare for the next release?
SELECT THE CORRECT ANSWER
Manage changes to the scope baseline of the previous release
Review the backlog items
Confirm the validity of the project scope statement
Review the resource utilization
Correct Option:B
EXPLANATION
In agile projects, the project manager and product owner need to reprioritize the backlog items based on the work done during a sprint and the release, so after finishing the release, the project manager and product owner should review the backlog.
10
During the project management plan review meeting, one of the senior directors raised a concern that one major deliverable was missing in the scope of work. What should you do as a project manager?
SELECT THE CORRECT ANSWER
Initiate change management process
Tell the director the change can not be added as the scope is already defined
Review the requirement documentation and requirement traceability matrix (RTM)
Change the plan to include missing deliverable
Correct Option:C
EXPLANATION
As a project manager, you should look into the requirement documentation to see if the requirement was captured.
13 NEXT CLOSING
You were managing a project to set up a car assembly line. The assembly line is almost ready and you have closed all the procurements, submitted the final report, and also took feedback from all the relevant stakeholders. What should you do next?
SELECT THE CORRECT ANSWER
Hand over the assembly line to the operations team
Prepare a report to show how the project achieved all the business objectives
Give final payment to all the vendors and contractors
Send out formal notice to close the project
Correct Option:A
EXPLANATION
Once the project finishes, the project manager and the project team need to hand over the project to relevant stakeholders
14 NEXT PLANNING
You are about to start the planning of a large and complex project in a very regulated environment. Due to the size and regulatory considerations, the planning becomes really critical. What is the first thing you should do to start the planning process?
SELECT THE CORRECT ANSWER
Start stakeholder identification so that you can engage the required stakeholders in the planning process
Get the statement of work from the customer and share it with all the stakeholders so that everybody knows what the priorities are
Review the project charter to understand high-level requirements of the project
Conduct a project kick-off meeting with the stakeholders to inform and engage them and to take their commitment
Correct Option:C
EXPLANATION
Project charter gives all the high-level information, and the information becomes the base for detailed planning.
15 VZORCE
You are working on a cement plan maintenance project. The total estimated budget for project is $100000. At 40% completion of the actual work, the actual cost spent is $60000. At the same pace, how much more money will it take to complete the project?
SELECT THE CORRECT ANSWER
$123,512
$97,889
$122,678
$89,254
Correct Option:D
EXPLANATION
The question says “how much more” money you would need to complete the project. So the question requires us to calculate the ETC. First we will calculate EV by using the formula %completeBAC(40%100000), which would be $40000, then we will derive the CPI by the formula EV/AC (40000/60000), which would be 0.67. We need to use the CPI to calculate EAC by the formula BAC/CPI (100000/0.67), which would be 149254, and finally we need to calculate ETC by the formula EAC-AC (149254-60000) = 89254.
16 MONITORING AND CONTROL
Your are managing a large construction project. Currently, you and your team are following the monitor and control project work process. Which of the following activities you and team might carry out during this process?
SELECT THE CORRECT ANSWER
Accepting or rejecting the change requests
Performing quality control activities on the deliverables
Getting formal acceptance on the deliverables from the customer (customer validation)
Comparing the actual progress against the baseline and the project management plan to keep the project under control
Correct Option:D
EXPLANATION
The question asks about the process of monitor and control project work and not about monitoring and controlling process groups. The process group includes all the options, but the process of monitor and control project work includes comparing the actual progress against the project management plan and making sure the project runs on track.
18 QUALITY ASSURANCE
You are managing a defect rate reduction project for a manufacturing process. To analyze and improve the process, you and the team are now involved in the quality assurance process. Which of the following could help in improving the process?
SELECT THE CORRECT ANSWER
Add a zero inventory process to the project
Consult with the quality control department
Make a process improvement plan with a Kanban expert
Consult with a Six Sigma Black Belt consultant
Correct Option:D
EXPLANATION
Six sigma is a lean project management concept, which is centralized around process improvement. The six sigma consultant can help in reducing the error rate.
20During the project review meeting with the team, you identified a significant variance. It is because of an issue in configuration. If the issue is not fixed before the next client inspection, your project might be canceled, However, after further review with the team, you came to know that bringing the project back on track is only a minor correction to the configuration element. What should you do first?
SELECT THE CORRECT ANSWER
Contact your sponsor
Talk to the customer and inform them about the findings
Raise a change request
Change the configuration element to bring the project back on track
Correct Option:C
EXPLANATION
Because the change is in configuration, the first thing the project manager should do is to raise a change request.
21
You are an experienced project manager working on a large software development project. Using a hybrid approach in this project, you are trying to break the work package into activities for scheduling purposes. During the decomposition of the testing work package, you need more information about the project which will come only once the development work is at least 60% complete. Since the development work will take about four months to complete, how you would proceed with the decomposition?
SELECT THE CORRECT ANSWER
Review the project scope statement to check if there is a possibility to reduce some work from development work package
Review the project management plan to determine how to proceed with the decomposition
Contact the solution architects to see if they could help in decomposition
Breakdown the development work package for now and decompose the testing work package later after getting the required information
Correct Option:D
EXPLANATION
One of the decomposition techniques is Rolling Wave Planning. The project manager decompose the work packages as they move into execution and more information is available. The best option here is to decompose the development work package for now and wait for the required information to decompose the testing work package later.
22 DEFINITION
You and the team are trying to estimate the time periods required by each activity. In this process, you are using a document which contains information on categories of labour, material, and equipment resources. To complete the project work, you also want to know the skill set, grade of supplies, and required certifications. Which of the following documents would you primarily refer for this purpose?
SELECT THE CORRECT ANSWER
Resource management plan
Work breakdown structure
Resource breakdown structure
Project management plan
Correct Option:C
EXPLANATION
The team is in the estimate activity duration process. One of the inputs to that process is the resource breakdown structure, which has information related to labour, material, and equipment resources.
23
You are using a rented facility from where the team of developers and testers are working. The weekly renewal of the facility is bound to happen on Monday, next week. The development work is delayed and will take another week. You had a discussion with the landlord to renew the contract for one more week but the landlord informs you that the facility is already booked. What should you do next?
SELECT THE CORRECT ANSWER
Update this risk in your risk register
Update this issue in the issue log
Update the resource management plan
Update procurement documentation
Correct Option:C
EXPLANATION
Since the issue has already occurred, there is no need to change the facility. The facility is a part of physical resources, the resource management plan needs to be updated with this change.
24 RISK
The project management plan explains that the predictive life cycle has been selected to produce the project deliverables. During which of the following areas will the overall project risk be the lowest?
SELECT THE CORRECT ANSWER
Initiation
Planning
Monitor and control
Closing
Correct Option:D
EXPLANATION
The overall project risk is highest at the beginning of the project and is lowest during the closing.
27
A few deliverables in your project demand procurement of goods and services from outside the organization. You have instructed your team to document all individual project risks related to the procurement activities. How should the team proceed with this activity?
SELECT THE CORRECT ANSWER
Review and update the risk management plan
Update the risk register
Review procurement documentation
Interview the vendors and contractors to identify the risks
Correct Option:C
EXPLANATION
Although the team is performing the identification of the risk process from the risk management knowledge area, the risks are related to procurement. The procurement documents such as bid documents and statement of work can be useful in the identification of the risks. Procurement documentation is also an input to the risk identification process.
28 WHICH DOCUMENT
The project you are currently managing has five phases. At the phase gate meeting, the management wants to determine if the phase has met the success criteria so they can proceed to the next phase. Along with the project management plan, what is the other document that should be referred?
SELECT THE CORRECT ANSWER
Business case and Project charter
Issue log
Risk register
Lessons learned register
Correct Option:A
EXPLANATION
To explain the success criteria, the project manager should refer to the business case and the project charter, along with the project management plan, as these documents contain the business objectives and other high level information about the project.
29 CHANGE MAN.
As per the organization policy, the Change Control Board (CCB) should review all the changes. They should also follow all the activities which are defined in the PMBOK for the change control. Since the project manager and the team are not the part of the CCB, which of the following activities may the CCB perform?
SELECT THE CORRECT ANSWER
Submit change request
Implement approved changes
Update project management plan
Terminate project
Correct Option:A
EXPLANATION
As the CCB is required to follow the change control activities, and the project manager is not part of the CCB, it is responsible for submitting the change request.
30 WHICH DOCUMENT
You are an experienced project manager working on an automobile project. Before working on one of the work packages to design clutch plates for the new vehicle, you wanted to review the acceptance criteria for the work package. Which document should you refer to?
SELECT THE CORRECT ANSWER
Project management plan
Requirements traceability matrix
Project scope statement
WBS Dictionary
Correct Option:D
EXPLANATION
The WBS Dictionary contains work package information such as owners, scheduled activities, and acceptance criteria.
33 THEORY
According to Tuckman’s ladder, in which area would a team experience maximum coordination and synergy?
SELECT THE CORRECT ANSWER
Performing
Norming
Forming
Adjourning
Correct Option:A
EXPLANATION
According to Dr. Bruce Tuckman’s ladder of team dynamics, a team has maximum coordination and synergy during the performing phase.
35 VZORCE
Your project sponsor wants you to calculate the Expected Monitory Value of two different alternatives available to complete the project per the decision tree. Which of the following formulas will you use to calculate the EMV?
SELECT THE CORRECT ANSWER
Probability * Impact
Positive outcome - Negative outcome
Negative outcome - Positive outcome
Average of the above options
Correct Option:B
EXPLANATION
The formula for calculating the EMV is Positive outcome - Negative outcome.
36 RISK
You are in the process of prioritizing the risks in the project with your team. Which of the following will have the least effect on the prioritization of the risk process?
SELECT THE CORRECT ANSWER
Reviewing risk register
Reviewing stakeholder register
Reviewing assumptions log
Reviewing the risk report
Correct Option:D
EXPLANATION
Reviewing the risk report will have the least impact on the prioritization process as the reports are made after the risks are identified and prioritized and the mitigation plans are prepared.
38 RISK
While managing a large and complex project, you followed all the best practices of project management. However, you still identified a lot of critical risks during the project, and so, it was not able to achieve the objectives. What went wrong?
SELECT THE CORRECT ANSWER
The risks were not identified properly.
The qualitative risk analysis was not done.
The quantitative risk analysis was not done.
The risk mitigation plans were poorly implemented.
Correct Option:D
EXPLANATION
Since you followed all the good practices, you must have done the identification and qualitative and quantitative risk analysis,.The only possible reason for the failure of the project could be that the risk response plan was not properly implemented.
39 COMMUNICATION
You are managing a construction project. In the process of defining the communication management plan, you want to understand the communication needs of all the stakeholders, especially related to the type and format of the communication. Which of the following options is the best way to get this information?
SELECT THE CORRECT ANSWER
Review the stakeholder register
Review the requirement documentation
Conduct communication requirement analysis
Review the stakeholder engagement plan
Correct Option:C
EXPLANATION
You should perform a communication requirement analysis with all the stakeholders.This exercise will help you to identify the type and format of the communication needed by the stakeholders.
40 RISK
In order to respond to a risk, the project team has two different option. The first option has four criteria to meet and costs $10,000. the second option has only two criteria to meet but costs $3,000. Which of the following actions is the team least likely to opt for?
SELECT THE CORRECT ANSWER
Running a Monte Carlo analysis
Performing alternative analysis
Using multicriteria decision analysis
Performing cost benefit analysis
Correct Option:A
EXPLANATION
The Monte Carlo analysis is a technique for identification of the risk.
41 PROCUREMENT
You are managing a pipeline expansion project in Canada and want to outsource some work to local contractor. In a process of preparing bid package for the contractor, which of the following documents is not required?
SELECT THE CORRECT ANSWER
Procurement statement of work
Request for proposal
Independent cost estimates
Bid documents
Correct Option:C
EXPLANATION
Independent cost estimates are internal documents that the buying organization uses for benchmarking the procurement processes. They are not shared with the vendors or contractors.
43 RESOUCES
One of the projects you are managing requires hazardous chemicals to be transferred from one location to the other location. This task requires very specific skills and experience, and there is a debate among the team members on the quantity and type of resources required for this task. As a project manager, what should you do first?
SELECT THE CORRECT ANSWER
Take any available resource to complete the work
Select the resources after the voting process based on majority
Research the specific skill set and experience required and search for resources which fulfill the requirements
Use resource management plan
Correct Option:C
EXPLANATION
The first thing you should do is research the required skill set and experience.
45 AGILE
Your organization is moving from a traditional project management approach to an adaptive one, and you are given the responsibility to lead that transition, During the project, you realize that you need to update a lot of templates to be used in adaptive projects, and one such template is for the schedule management plan. Which of the following things are you most likely to update in the template?
SELECT THE CORRECT ANSWER
The schedule model, iteration and release lengths, and reporting formats
Schedule maintenance and level of accuracy
Units of measurements and Ops charts
Summary milestones and key deliverables
Correct Option:A
EXPLANATION
As the questions reflect that the organization is moving from predictive to agile project management, the schedule management plan needs to be updated with the iteration and release planning.
46 COMMUNICATION
A few stakeholders are complaining about a team member who is not performing well in the project. As a project manager, how should you handle this situation with the team member?
SELECT THE CORRECT ANSWER
Meet the functional manager and ask for replacement
Use formal written communication with the team member
Use formal verbal communication with the team member
Discuss the issue with the team member
Correct Option:D
EXPLANATION
The best choice should be to go and talk to the team member about the issue.
48
A lot of key stakeholders’ responsibilities are disrupted because of the organizational restructuring, and it is becoming difficult for you to keep the stakeholders engaged in the project in a positive manner. What should you not do to manage the engagement?
SELECT THE CORRECT ANSWER
Use your interpersonal and team skills to manage the engagement
Develop the approaches to engage the stakeholders based on their needs, expectations, interests, and potential impact
Use communication management plan to engage stakeholders
Engage stakeholders at appropriate project stages to obtain, confirm, and maintain their commitment toward the success of the project
Correct Option:B
EXPLANATION
All the other options are for stakeholder engagement, and since this option is for the identification of the stakeholders, it is not an action to be taken.
49 CHANGE - MONITOR AND CONTROL
During an inspection, you detect a defect which was already identified in one of the previous inspections and a change request was also raised to correct it. You are wondering how the defect resurfaced. After a discussion with the team, you come to know that the team never implemented the change. What could have prevented this situation?
SELECT THE CORRECT ANSWER
Using an requirement traceability matrix
Updating the defect into issue log and risk register
Holding an approved change request review
Performing root cause analysis
Correct Option:C
EXPLANATION
Approved change request review is a part of the monitor and control process. This includes reviewing all the change requests that are approved by the CCB to see the status of their implementation.
50
You are managing a big multiphase project. The phases are planned in a sequential manner. After the second phase of the project, which process group of the third phase should start?
SELECT THE CORRECT ANSWER
Planning
Executing
Initiating
Closing
Correct Option:C
EXPLANATION
In a sequential life cycle, when the closing process group ends, it starts the initiation process group of the next phase.
51
While performing the slab casting activity of a construction project for a private client, the client asks if you could also do the false ceiling. You analyze the change against the schedule and conclude that this will have no impact on the schedule.What is the first thing you should do to proceed with the change?
SELECT THE CORRECT ANSWER
Project schedule management
Project quality management
Project tracking
Project change control management
Correct Option:A
EXPLANATION
All the terms mentioned in the question point out that the project is an agile project. All of these activities are the part of managing the schedule in an agile environment.
56
The project that you are managing is going well, and there is a high-performing team whose contribution you want to recognize. Which of the following options can be used as a guide to the process?
SELECT THE CORRECT ANSWER
Organizational Process Assets
Quality Matrix
Team Performance Assessment
Enterprise Environmental Factors
Correct Option:A
EXPLANATION
The process you are managing is ‘Manage Team’ from resource management. One of the inputs to that process is the Organizational Process Assets.
57 AGILE
Which of the following is the difference between iterative and adaptive development life cycle?
SELECT THE CORRECT ANSWER
In iterative life cycle, the iterations are repeated until we get the desired results.
In adaptive life cycle, the iterations are repeated until we get desired results.
In iterative life cycle, the scope of the project is defined in the first iteration.
In adaptive life cycle, the project management plan is defined during project planning.
Correct Option:A
EXPLANATION
According to PMPBOK- 6, the definition of iterative life cycle is that the iteration runs until it is deemed true.
58 AGILE
In the course of managing an agile project, the team conducts a sprint review with the customer representative(s) at the end of the second sprint. After the customer suggests many changes, the team documents the changes, what should the team do next?
SELECT THE CORRECT ANSWER
Conduct retrospective meeting and reprioritize the backlog
Put the customer-suggested changes to the next iteration
Start the next iteration as per the previous plan
Consult product owner to see if the changes are viable
Correct Option:A
EXPLANATION
Since the team just concluded the sprint review, the next step should be to conduct a retrospective, mark the areas of improvement by putting all the customer requirements and improvements back into the backlog, and reprioritize the backlog to plan the next iteration.
60 BUDGET
You are managing a large scale construction project. You have 230 resources working on the project in which a lot of material is also used. During the execution, the rate of cement has risen significantly due to economic growth of the country. How would you manage the risk involved?
SELECT THE CORRECT ANSWER
Use contingency reserve
Use management reserve
Ask the finance department for more funds
Contact your sponsor
Correct Option:A
EXPLANATION
As the price escalation of the cement is due to economic growth, ideally it is already identified as a risk. So the project manager should use the contingency reserve planned for the particular risk.
61 CONFLICT
During a sprint in a hybrid project, two of the senior team members have a conflict. One team member is complaining that the other team member is keeping the testing tool busy for almost the entire time and thus, the former is not able to perform the test cases. The project manager convinced both of them to adjust their work timings so that both can use the testing tool. Which conflict resolution technique did the project manager use?
SELECT THE CORRECT ANSWER
Smoothening
Problem solving
Compromising
Avoiding
Correct Option:C
EXPLANATION
The project manager used a compromising technique as both of the team members adjusted their timings. It is partial satisfaction to both the parties involved.
62 PROJECT CHARTER
You are in the process of defining the project charter for an industrial infrastructure project and keen to determine how business objectives are related to the project. What should you do?
SELECT THE CORRECT ANSWER
Refer to the business case to check the business objectives, update it, and submit to the sponsor
Identify how the project is related to the business objectives from the business case
Go through the agreements related to the project
Review business cases of similar past projects
Correct Option:B
EXPLANATION
The business case documents the business needs and objectives related to the project.
63 NEXT
When planning for management of project resources, you have used your expert judgment, prepared hierarchy charting of the project organization, and held related meetings while acknowledging organizational theories. These have resulted in the creation of a good quality resource management plan. However, another item has not been created yet. What is it?
SELECT THE CORRECT ANSWER
Project team assignments
Resource requirements
A team charter with operating guidelines for the team, their values, and agreements.
Resource calendars
Correct Option:C
EXPLANATION
The team charter and the resource management plan are the two key outcomes of the planning resource management process.
66
During a water dam construction project, a lot of villagers came up and started opposing the construction, they demand very high compensation that would adversely impact the budget and the schedule of the project, which of the following process would have helped in preventing this problem from occurring?
SELECT THE CORRECT ANSWER
Developing the Schedule
Determining the Budget
Identify Stakeholders
Identify Risk
Correct Option:C
EXPLANATION
The identification of the stakeholder process is a part of initiation which helps in identifying both positive and negative stakeholders and to plan the strategy to handle the stakeholders.
67
When mapping the characteristics of the stakeholders, the project manager is in the process of selecting the representation tool to be used. He is deciding on using either the stakeholder cure or the bubble chart. What is common between these two representation tools?
SELECT THE CORRECT ANSWER
Bubble chart is used for risk analysis.
Stakeholder cube is used to depict multidimensional characteristics of stakeholders.
Both can deal with more than two dimensions.
Both are stakeholder identification techniques.
Correct Option:C
EXPLANATION
Usually, three dimensions are depicted in these charts. In case of the stakeholder cube, it is about the stakeholders, and in case of bubble chart, it is about the risks.
68
You are managing an agile project of which four sprints of two weeks each are remaining. This is the last release and your product owner informs you that a multimillion dollar project is about to start in the next three months. What is the first thing you should do?
SELECT THE CORRECT ANSWER
Review your project resource requirements
Try to wrap-up the current project as quickly as possible so that the resources are available to work on the big project.
Ask the management how the new project impacts your current project
Look into the skill set document and see how you can leverage the skills of your resources to work on the big project
Correct Option:C
EXPLANATION
The first thing the project manager should do is analyze how the new project impacts the current project.
69
During an hybrid project, you realize that for producing a few deliverables, you would need external resources, and so, you start preparing a contract SOW (statement of work). Which of the following will not help you in this process?
SELECT THE CORRECT ANSWER
The project scope statement
The WBS Dictionary
The WBS of the project
The cost of the work required
Correct Option:D
EXPLANATION
The contract statement of work only requires information about the scope of work to be completed and not the cost of the work.
70 CONTRACTS
During a large scale oil and gas project, you wanted to outsource a part of the project work which contains high amount of risk. Due to the risk involved in the work, not many contractors are interested to take up the work. What type of contract you would suggest to attract the vendors and contractors?
SELECT THE CORRECT ANSWER
Cost plus fixed fee
Cost plus award fee
Fixed price incentive fee
Firm fixed price contract
Correct Option:B
EXPLANATION
Due to the nature of the work, if the contractors are not interested to take up the job, the project manager can suggest to go for a cost plus award fee contract as it gives extra award to the contractor who is willing to take up the job.
71
You and the team are working on selecting the project management approach for the project. The team is in a discussion about the various priorities of different project management approaches. As an experienced project manager, what would you suggest is the highest priority of an agile project management approach?
SELECT THE CORRECT ANSWER
Working software over comprehensive documentation
Individuals and interactions over processes and tools
Customer satisfaction through delivery of valuable products
Responding to change and progressive elaboration of plans
Correct Option:C
EXPLANATION
Although all the options are from the agile manifesto, this option most closely resembles the highest priority according to the Agile Manifesto, which states, “Our highest priority is to satisfy the customer through early and continuous delivery of valuable software.”
72 QUALITY AGILE
You are delivering a software product to the customer using an agile methodology. During the sprint review, the customer reverted with a few defects.The team was unable to identify and resolve these defects in any of the quality processes. According to agile, what are these defects called?
SELECT THE CORRECT ANSWER
Undetected defects
Escaped defects
Primary defects
Secondary defects
Correct Option:B
EXPLANATION
Escaped defects are those defects that have escaped all software quality processe. These are usually pointed out by the customer during the iteration review meeting.
74 AGILE CEREMONY
You are organizing a meeting with all the agile team members to synchronize their activities and ensure they are all working toward a common iteration goal. What this meeting is called?
SELECT THE CORRECT ANSWER
Sprint review
Sprint planning
Daily stand-up
Sprint retrospective
Correct Option:C
EXPLANATION
Daily stand-up meetings are scheduled to help synchronize the team’s activities and ensure alignment.
75 AGILE
During an agile project, you have just completed the development of a potentially shippable product increment. What is the time taken by the team to create this increment called?
SELECT THE CORRECT ANSWER
Cycle time
Throughput time
Velocity
Actual time
Correct Option:A
EXPLANATION
Cycle time refers to the time it takes (from beginning to end) to complete the creation of a potentially shippable product increment.