PMP TEST 4.2 Flashcards
19You were given a budget of $3000, and you spent $2000. However, you only completed $1200 worth of work. What do you currently expect the TOTAL project to cost, considering your situation?
SELECT THE CORRECT ANSWER
Not possible to estimate
5000
6000
6200
Correct Option:B
EXPLANATION
Estimate at completion (EAC) =BAC/CPI. Here, we have BAC=$3,000, AC=$2,000, and EV=$1,200. CPI=EV/AC=1200/2000=.6. So, EAC=3000/.6 =5,000.
26Team norms have to be established during the beginning of the project so that the team is equipped to handle challenges as the project progresses. Which of the following is NOT included in the team norms?
SELECT THE CORRECT ANSWER
Meetings
Communication Approaches
Monitoring the performance
Shared Values
Correct Option:C
EXPLANATION
Meetings, Communication Approaches, Managing conflicts, Shared Values, and Decision making are all included in team norms.
29You are managing a project to develop an online PMP exam simulator to help students practice exam questions in a real-life environment. The team has completed design work, received approval from the technical review team, and initiated coding work. Your management asks you what you currently expect the TOTAL project to cost, and you assure them that the rest of the job will be done as per budget. Which of the following formulas will you use to get the most accurate estimate at completion (EAC)?
SELECT THE CORRECT ANSWER
EAC = AC+(BAC-EV)
EAC = AC+BOTTOM-UP ETC
EAC = (BAC/EV)/CPI*SPI
EAC = BAC/CPI
Correct Option:A
EXPLANATION
You are assuming that the rest of the job will be done as per budget; all you need to do is take the remaining work (BAC-EV) and add funds spent, AC.
30The project manager, project team members, and procurement managers are actively involved in negotiating contracts. Which of the following may the Project team NOT suggest?
SELECT THE CORRECT ANSWER
Deliverables and Milestones
Data consideration
Risk and issues
Resource requirements
Correct Option:B
EXPLANATION
Deliverables & Milestones, Risk and issues, and resource requirements can all be suggested by the project team.
37Multiphase projects are planned by developing phases that are performed sequentially to ensure proper control of the project and attain the desired product, service, or result. In some cases, it is necessary to accelerate the project life cycle by overlapping project phases. Which of the following is NOT true about this kind of overlapping relationship?
SELECT THE CORRECT ANSWER
This technique can be applied as a schedule compression technique called fast-tracking.
This kind of relationship may increase project risk and the potential for conflicts. A subsequent phase can progress before accurate information is available from the previous phase.
In this kind of relationship, a phase is planned at a given time; planning for a subsequent phase is carried out as work progresses on the current phase or deliverables.
This kind of relationship can reduce the ability to develop long-term planning, but it is suitable in an undefined, uncertain, and rapidly changing environment.
Correct Option:C
EXPLANATION
In iterative relationships, a phase is planned at a given time. Planning for a subsequent phase is carried out as work progresses on the current phase or deliverables. In overlapping relationships, the successor phase can start prior to the completion of the predecessor phase. This approach can be applied as a schedule compression technique called fast-tracking. An overlapping relationship may increase project risk and the potential for conflicts as a subsequent phase progresses before accurate information is available form the previous phase. This kind of relationship can reduce the ability to develop long-term planning, but it is very suitable in an undefined, uncertain, and rapidly changing environment.
39As a project manager, you and your team are mainly focused on finding a less costly way to do the same work and on achieving more out of the project in every possible way to increase the bottom line, decrease costs, improve quality, and optimize the schedule without reducing or impacting the scope. Which of the following techniques are you most likely using?
SELECT THE CORRECT ANSWER
Benchmarking
Value analysis
Life cycle costing
Reserve analysis
Correct Option:B
EXPLANATION
Value analysis is also referred to as value engineering or value methodology. It is the technique of finding a less costly way to do the same work and of achieving more out of the project in every possible way to increase the bottom line, decrease costs, improve quality, and optimize the schedule without reducing or impacting the scope.
42Which of the following assessments explores alternatives to overcome or avoid the risk?
SELECT THE CORRECT ANSWER
Backlog Assessment
Skill Gap Assessment
Risk Assessment
Team Assessment
Correct Option:A
EXPLANATION
Backlog Assessment or refinement explores alternatives to overcome or avoid the risk
43A project manager working on implementing WIMAX connectivity in a rural area has to deploy several network devices and set up POPs to house those devices. She performed a cost-benefit analysis and was concerned about the high cost of nonconformance as a result of not following the proper quality procedures in the project. What should the project manager do?
SELECT THE CORRECT ANSWER
Look for benchmarks
Allocate additional budget to deal with the situation
Utilize the existing reserve money to deal with her situation
Perform a quality audit
Correct Option:D
EXPLANATION
A quality audit is a scheduled or random structured review performed by internal or third-party auditors to determine whether quality management activities comply with organizational and project processes, policies, and procedures. It ascertains inefficient and ineffective activities and processes used in the project as well as lessons learned, such as gaps and best practices, that can improve the performance of the current project or future ones. A quality audit to correct any deficiencies in the quality processes should result in a reduced cost of quality and an increase in stakeholders’ acceptance of the product.
44A project manager has observed that the project team members’ performance is deteriorating and motivation has also reduced. What is the best course of action the project manager can initiate?
SELECT THE CORRECT ANSWER
Reward & Recognition
Reward & Regulation
Penalty for degraded performance
Allow team to improve themselves
Correct Option:A
EXPLANATION
Reward and Recognition is an effective way of motivating teams to perform and contribute to the success of the project.
45Which of the following tools is not used to measure team performance?
SELECT THE CORRECT ANSWER
Sprint
Kanban Board
Earned Value
Velocity
Correct Option:A
EXPLANATION
Kanban Boards, Throughput metrics, Cycle Time, Quality Metrics, Earned Value, Bar Charts, and Velocity are the various tools used to measure a team’s performance.
50Which of the following is essential for delivering the high-level organization strategy?
SELECT THE CORRECT ANSWER
Quality Management
Change Management
Knowledge Management
Transition Management
Correct Option:B
EXPLANATION
Change Management is essential for delivering the high-level organization strategy.
55Henry, a project manager, utilizes different conflict resolution techniques to resolve conflicts in his project. He created an open environment so that his team members feel free to discuss their concerns and issues. He is also focused on resolving issues rather than fixing the personalities of his team members, and he pays more attention to the present than the past. Which of the following conflict resolution techniques will lead to the least sustaining positive result?
SELECT THE CORRECT ANSWER
Withdrawing or avoiding
Forcing
Confronting or problem-solving
Compromising
Correct Option:A
EXPLANATION
Withdrawing or avoiding is the technique of retreating from conflict and avoiding or postponing resolution. This technique leads to the least sustaining positive results.
56Facilitating meetings and sessions is an effective technique for:
SELECT THE CORRECT ANSWER
Meetings
One-on-one mentoring
Collaboration
Team management
Correct Option:B
EXPLANATION
Facilitating meetings and sessions is an effective technique for one-on-one mentoring, because this provides the mentor an opportunity to engage with the stakeholders effectively and guide them to right directions. Secondly, the stakeholder will have safe environment to express themselves in the absence of others.
57Which of the following is NOT an element of self-regulation?
SELECT THE CORRECT ANSWER
Self Control
Trustworthiness
Adaptability
Agility
Correct Option:D
EXPLANATION
Self Control, Trustworthiness, Conscientiousness, and Adaptability are self-regulation elements.
58You are responsible for making arrangements for your company’s annual picnic. You have taken all the necessary actions and have reserved an outdoor park on a particular day. You have bought umbrellas and rented tents just in case you need them. Which of the following risk strategies are you using in this case?
SELECT THE CORRECT ANSWER
Passive acceptance
Contingency planning
Avoidance
Transference
Correct Option:B
EXPLANATION
The contingency plan includes specific action that will be taken if opportunities or threats occur.
60In the communication process, a basic model of communication that exhibits how information is sent from the sender and how it is received by the receiver has all the following components EXCEPT:
SELECT THE CORRECT ANSWER
Sender
Message and feedback message
Urgency
Noise
Correct Option:C
EXPLANATION
Urgency is not included in the basic communication model but should be considered when determining the method of communication to be used.
61While overseeing a software engineering project, you find that one of the subcontractors failed to deliver on the last three projects. Upon further investigation, you learn that there are several complaints filed against this subcontractor and that they have a very bad reputation in the market. Realizing that is it too big a risk, you terminate the contract with the subcontractor and instead hire a couple of individuals to work on the components. Which risk response strategy did you use in this situation?
SELECT THE CORRECT ANSWER
Accept
Transfer
Mitigate
Avoid
Correct Option:D
EXPLANATION
Avoid is the elimination of the threat by eliminating the cause or changing the project management plan. Here, you utilized the avoid strategy by terminating the contract with the subcontractor to eliminate the threat to your project.
71Your team members have created a requirement document, a scope statement document, and a work breakdown structure. They have identified twenty work packages and completed the WBS dictionary. Some of these team members were also involved in creating the business case and conducting the feasibility study at the early stage of the project. Which of the following items will the team members work on now?
SELECT THE CORRECT ANSWER
Help the project manager to develop the schedule
Create the detailed activity list
Create the network diagram
Identify the sequence of the activities
Correct Option:B
EXPLANATION
Once the WBS is created with all the work packages, the team members should work on decomposing the work packages to create the detailed activity list. Network diagram and activity sequencing can be performed only after the activity list is created.