PMP TEST 1.1 Flashcards
1The Project Manager shifts to an agile approach for a project with an aggressive go-to-market timeline. The Project Manager needs to revise the stakeholder plan so that it follows agile principles. What should the Project Manager do to meet this need?
SELECT THE CORRECT ANSWER
Design a digital communication system that allows for virtual submission, logging, reviewing, and escalation of issues
Remove unnecessary layers of management to promote direct communication between the project team and stakeholders
Modify templates to include product backlog progression and the burndown rate and encourage use of standups
Increase the number of formal training workshops to cover all relevant issues for all stakeholders, including the project sponsor and client
Correct Option:C
EXPLANATION
Servant leadership requires shared responsibility. Changing documentation and processes across the team toward agile methodologies ensures that all team members are kept up to date on expectations, roles, and responsibilities.
3A Project Manager develops a project management plan and schedule based on an agreed-upon project life cycle of 16 months. Later, due to changing business requirements, the Project Manager receives a request for completion within 9 months. How should the Project Manager respond to this proposed change in timeline?
SELECT THE CORRECT ANSWER
Work with key stakeholders to identify project requirements that could be reduced
Immediately ask project team members to increase the pace of each task within the project
Modify the original project schedule so that revised deadlines can be met
Meet individually with project team members to discuss how aspects of the project can be completed more quickly than planned
Correct Option:A
EXPLANATION
To execute the project quickly, the project team should discuss on the whole scope together and find out the way to complete tasks at individual level within short time. By the discussion, many tasks could be by-passed from the base tasks and new tasks can be identified, which might help the project to reduce the total time frame of the project. This is the agile mindset of the Project Manager by which more value can be delivered in a shorter period of time.
5The project manager schedules an iteration review and learns that a few key stakeholders do not approve of how a feature has been developed. What should the project manager do first in order to address this issue?
SELECT THE CORRECT ANSWER
Invite project team members to a brainstorming session to identify an appropriate response.
Address the issue only after evaluating why these stakeholders are concerned.
Determine the impact of the conflict by listing the pros and cons of the situation.
Ask the project sponsor to act as a neutral party in negotiation with those stakeholders who are dissatisfied.
Correct Option:B
EXPLANATION
One of the required abilities of Project Managers is to identify when the conflict escalates. If it happens, the Project Manager should help to facilitate a satisfactory solution, addressing conflict early, in private and using a direct and collaborative approach. PMBOK Guide Sixth Edition (2018), 9. Project Resource Management / 9.5.2 Manage Team: Tools and Techniques, p348
13A Project Manager’s team has been efficiently delivering expected results in an environment where budget and scope are fixed. Now, there is an increased demand for new skills due to changes in the market. What can the Project Manager do to meet this new demand?
SELECT THE CORRECT ANSWER
Meet the new demand by adding new resources with the required skills
Hire a third-party vendor who can provide resources with the needed skills
Change the distribution of partially-dedicated resources with the needed skills
Meet the new demand by upgrading the existing team members’ skills
Correct Option:A
EXPLANATION
Developing the team is very important. However, in a situation where time is limited, the most efficient option is expanding the team to included skilled resources.
14A project team is small and the team members have known each other for a long time. The team’s project is in the execution phase. Recently, a team member told the new project manager that another team member has been complaining about how the project is being managed. How should this new project manager respond?
SELECT THE CORRECT ANSWER
Preview the current stakeholder engagement plan for the way to resolve the difficulty.
Schedule a mandatory team meeting which will lead to the creation of a new social contract.
Notify team members that they should submit anonymous recommendations for a new social contract.
Send a survey to team members, requesting suggestions for dealing with the dissatisfaction.
Correct Option:B
EXPLANATION
A) No - While this may help in addressing the situation, it will not help to rectify any existing damage done to the team as a result of the situation. B) Yes - This is the best solution. It encourages every team member to particulate and results in a clear set of guidelines for the team. C) No - This is not the best answer. While this will create a set of guidelines, they may not be the best ones for the team. D) No - This is not the best solution as it does not encourage team cohesion and self leadership. PMBOK Guide Sixth Edition (2018), 9. Project Resource Management / 9.1.3.2 Team Charter, 319 | The Agile Practice Guide (2017), 5. Implementing Agile: Delivering In AN Agile Environment / 5.1 Charter The Project And The Team p50
16A project manager has multiple projects. One project has new team members and is in its early stages. Unfortunately, the project manager will be very busy executing other projects over the next few weeks. How can the project manager develop the new project team over the next few weeks?
SELECT THE CORRECT ANSWER
Help the team create a social contract that will encourage team cohesion.
Suggest that the team engage in multiple team-building events to normalize the team.
Keep the team informed by sending short daily project status updates.
Engage in face-to-face personal conversations with each team member to build relationships.
Correct Option:A
EXPLANATION
A) Yes - This will allow the team to normalize themselves and be self-servicing when you are unavailable. B) No - This may be productive, but it is a one-time activity and does not encourage self-servicing when you are unavailable. C) No - This does not encourage the team to get to know each other and become self-servicing. D) No - While this may result in deeper relationships, there is not enough time for this and it does not encourage the team to get to know each other. PMBOK Guide Sixth Edition (2018), Part 2 The Standard for Project Management / 1.5 The Project Lifecycle, pp 547-548
17A Project Manager needs to ensure that the team delivers business value within the required timelines. The manager recently learned that key stakeholders are worried that the current release plan will not meet urgent business needs. What can the Project Manager do to effectively respond to the stakeholder concerns?
SELECT THE CORRECT ANSWER
Renegotiate scope with the project sponsor after examining the work breakdown structure (WBS)
In consultation with the stakeholders and team members, identify the minimum viable product needed for launch
Determine the schedule performance index (SPI) and escalate the schedule risk to the project sponsor
Monitor progress using a burndown chart after modifying the schedule baseline to meet stakeholder requirements
Correct Option:A
EXPLANATION
Assuming that the work can be completed may create new issues. It is best to work with the project sponsor and see if there is any scope that can be reduced to meet a more realistic timeline.
18A key stakeholder voices a concern during the planning stage about whether the available resources are sufficient to meet the objectives of the project. The Project Manager believes that the stakeholder is right. How should the Project Manager handle this stakeholder’s concern?
SELECT THE CORRECT ANSWER
Review the bounds of the negotiations for agreement
Determine the project’s ultimate objectives after carefully evaluating project priorities
Engage in agreement negotiations for better resources
Ensure that the impact of the unavailability of required resources is fully documented
Correct Option:D
EXPLANATION
Fully documenting the impact of situation ensures that all stakeholders are aware of any risks, issues, quality concerns, etc.
22A customer requests a change in the technical approach for a product currently in development. The project manager learns about this request during a reoccurring project review. What should the project manager do in response to the customer’s request?
SELECT THE CORRECT ANSWER
Work with team members to immediately implement the new approach.
Have the team decide on the appropriate approach, giving them authority to implement their decision and validating their decision in talks with stakeholders.
Discuss the pros and cons of the proposed approach with stakeholders, then select the approach that is best for the team and notify team members.
In order to obtain sponsor buy-in, have the team to benchmark the approach.
Correct Option:B
EXPLANATION
As a technical issue the project management should address the team to assess and select the best options to solve, empower then and improving engagement. The Agile Practice Guide (2017), 2 An Introduction To Agile / Figure 2-2 The Twelve Principles Behind the Agile Manifesto, p9 | The Agile Practice Guide (2017), 4 Implementing Agile: Creating An Agile Environment / 4.2 Servant Leadership Empowers The Team, p33
23A Project Manager realizes during the third iteration of product development that the template used for the project management plan is not showing updates. Which action should the project manager take?
SELECT THE CORRECT ANSWER
Assign one team member to update the project management plan template and document any risk
Rank the need to update the template according to the business value for the upcoming iterations
Avoid adding to team distraction by fixing the issue independently
Document the issue as a new project risk and propose a solution
Correct Option:D
EXPLANATION
This issue may or may not also be a risk to future iterations. Documenting it as a new project risk also ensures that there is a proper risk analysis performed to analyze what could happen in different scenarios.
25During work on a government project, stakeholders pressure the project manager to submit to their preferred actions. While the project manager must coordinate and plan with multiple stakeholders, the project manager must also deal with complex relations and frequently changing scenarios. What should the project manager consider doing? (Choose two.)
SELECT THE CORRECT ANSWER(S)
Use the Prioritization method of categorization.
Use the Salience model of categorization.
Use the Transformation model of categorization.
Use the Transaction model of categorization.
Correct Option:A, B
EXPLANATION
Both salience model and prioritization needs to be used to categorize for government contracts especially when the scenario is for frequently changing, complex relationships with multiple representatives involved. PMBOK Guide Sixth Edition (2018), 13. Project Stakeholder Management / 13.1.2.4 Data Representation, p513
27A Project Manager needs to ensure that all data security requirements are covered during a data warehouse development projects execution phase. Each of the databases created during different project phases will have a specific data security policy to comply with governmental data security laws. How should the Project Manager plan to meet these requirements?
SELECT THE CORRECT ANSWER
Plan a database development specification and regularly check this to ensure the developer aligns with the specification
Arrange for review of the data security status on a quarterly basis and recommend remedial steps if noncompliance is found
Tell the database developer to submit documentation of data security items and the steps they take to correct items that do not meet specifications
Add a quality assurance specialist resource to the project team who will be responsible for monitoring the data security quality of the project
Correct Option:C
EXPLANATION
Clearly documenting how key requirements have been met is a great way to ensure quality and identify any gaps that need to be addressed
29A company is struggling to define the scope of a new project that has multiple phases with a high level of dependency between the phases. How should the project manager approach this challenge?
SELECT THE CORRECT ANSWER
Contract with a third-party company that specializes in helping businesses define scope of work on large projects.
Work with project stakeholders to recommend an iterative approach that will then help to define the project’s scope.
Construct a project management plan that provides extra time within the schedule, then seek to revise the scope of work.
Suspend final delivery dates for the project in order to have time to revise the schedule once there is clarity on the scope of work.
Correct Option:B
EXPLANATION
Although most of the distractors are not bad ideas for the project manager, the key is the first correct action the they must perform. Introducing adaptive steps in a heavily predictive environment is never easy and also, the stakeholders will be the ones heavily involved in the 3 weeks interaction phase. PMBOK Guide Sixth Edition (2018), 13. Project Stakeholder Management / 13.3 Manage Stakeholder Engagement, p524 | The Agile Practice Guide (2017), 5. Implementing Agile: Delivering In An Agile Environment / 5.2.6 Planning for Iteration-Base Agile, p55
31All team members on a new project want to gain the customer’s trust by delivering value as quickly as possible. The project manager learns that one resource has worked with the sponsor on other projects. The resource seems to be using personal influence, working with a project sponsor to increase the project’s benefits realization. At which stage in the project should the project manager address this concern to optimize cost effectiveness?
SELECT THE CORRECT ANSWER
At the start of the team’s performing stage
Immediately after the first benefit realization
During the next retrospective ceremony
During the next resource performance review
Correct Option:C
EXPLANATION
The retrospective would be the event to address this concern. PMBOK Guide Sixth Edition (2018), 8. Project Quality Management / 8.3.2. Control Quality: Tools and Techniques / 8.3.2.6 Meetings, p305 | PMBOK Guide Sixth Edition (2018), 13. Project Stakeholder Management / 13.4.2.6 Meetings, p535
32A project team learns that there is a new compliance requirement from an international entity that may impact the baseline business case for the project. They learn this right after project charter is completed and the project sponsor has signed. How should the project manager proceed?
SELECT THE CORRECT ANSWER
Research the requirement and possible consequences, then give the sponsor a recommendation.
Address the requirement through the creation of a quality management plan.
Decline to address the issue, as the new requirement is not part of the project’s documented scope.
Ensure that the requirement is documented in the risk register, then ask for further guidance from all stakeholders.
Correct Option:A
EXPLANATION
The context of this scenario demands the Project Manager to influence the organization (sponsor) and recommend next steps after reviewing and understanding compliance requirements and consequences. PMBOK Guide Sixth Edition (2018),4. Project Integration Management / 4.1.1.3 Enterprise Environmental Factors p78
35During one daily standup meeting, team members indicate that they are having to engage in rework because there seems to be too much up-front work. How should the Project Manager respond to this concern?
SELECT THE CORRECT ANSWER
Try using a Kanban board for reviews
Request that team members explicitly implement time boxing
Request that the project owner maximizes the product value
Engage in a process to manage a reduction in the product backlog
Correct Option:B
EXPLANATION
Rework can often caused by trying to do too much in too little time. Timeboxing is a great technique to choose an appropriate window of time dedicated to a single focus.
36A Project Manager from a traditional project management organization is assigned to an ongoing project. Recently, the organization has started to use agile methodologies in its projects. The Project Manager hears that some team members feel like key subject matter expertise is missing and there is insufficient collaboration within the team. How should the Project Manager respond to these team members’ concerns?
SELECT THE CORRECT ANSWER
Employ third-party specialists to fill the knowledge gap
Add additional resources via a request to the sponsor
Add cross-functional internal resources
Where possible, modify Gantt charts to Kanban boards
Correct Option:C
EXPLANATION
Agile methodologies require T” shaped team members. That is
38A key team member is unhappy with the overall approach documented in a project management plan. The member surprises the Project Manager with negative comments about the approach during a weekly status meeting during the execution phase of the project. How should the Project Manager address the team members concerns?
SELECT THE CORRECT ANSWER
Continue with the meeting, and ensure that the concerns are added to the risk register after the meeting is finished.
Continue with the scheduled agenda items after reminding the team member of expected meeting etiquette. Then, solicit feedback about the etiquette expectations.
Remember that a project should not go forward when key team members are in disagreement, and use the meeting to discuss the members concerns.
Make a short comment to acknowledge the team members concerns, continue with the meeting, and meet with the member in private to discuss their concerns.
Correct Option:D
EXPLANATION
Conflict should be addressed in private, first, to better understand the concern being raised. Exploring the concern after the meeting gives the PM an opportunity to verify the concern and determine needed next steps without disrupting the meeting with all meeting attendees.
40During an iteration, a project team encounters problems that may cause a delay in task completion. Another team within the same project needs the task to be completed on time in order to meet their schedule. What can the project manager do to resolve this problem?
SELECT THE CORRECT ANSWER
Insist that the project team work a bit harder to complete on time, in order to avoid delaying the work of other teams.
Work with the product owner to reprioritize the iteration backlog, so that it does not delay work by other teams.
Increase the iteration length, and add additional resources to the project team, so that they can meet the appropriate deadlines.
Ask team members to perform to the best of their abilities during the iteration, and engage in a retrospective after completion of the iteration.
Correct Option:B
EXPLANATION
May cause a delay does not mean the task completion will be delayed, To improve probability of success, reprioritizing the backlog may improve the probability for success more than the other options. PMBOK Guide Sixth Edition (2018), 6. Project Schedule Management / 6.6 Control Schedule, pp 222-224 | The Agile Practice Guide (2017), 5 Implementing Agile: Delivering In An Agile Environment / 5.2.3 Backlog Refinement, p52
41Certain key stakeholders are dissatisfied with how a key feature of a project has been developed. They express their dissatisfaction during an iteration review meeting. What should the project manager do first to resolve this issue?
SELECT THE CORRECT ANSWER
Gather the project team for a brainstorming session and identify a solution.
Identify the reasons why there are issues with the feature, then address the issue.
Create a list of the pros and cons of the situation to define the impact of the conflict.
Add a neutral party, such as the project sponsor, to function as a negotiator with stakeholders.
Correct Option:B
EXPLANATION
Identifying the source of conflict is a key initial step in conflict management. PMBOK Guide Sixth Edition (2018), 9. Project Resource management / 9.5.2 Manage Team Tools and Techniques, p348
42During a technical project, a well-liked project member is reassigned to a different project. The team has expressed disapproval regarding the reassignment. What action can help mitigate the team’s disapproval?
SELECT THE CORRECT ANSWER
Notify the project sponsor regarding the teams disapproval and brainstorm a response
Employ coaching tools and techniques to increase team motivation
Add a resource with the same skills to replace the key team member
Notify the change control board (CCB) and discuss possible ways to resolve the issue
Correct Option:B
EXPLANATION
PM should know how to handle key personnel changes and keep the team motivated and productive.
43At a weekly project status meeting, a key team member expresses concerns about the overall approach documented within the project management plan. The Project Manager is surprised because the team is in the process of executing an important component of the project and the concern has not been raised before. What steps should the Project Manager take?
SELECT THE CORRECT ANSWER
Update the risk register to document the concerns, then continue with the meetings scheduled agenda items.
Recognize that the concern must be fully discussed and resolved prior to continuing with the meetings agenda items.
Address the team with a generic reminder about meeting etiquette, then ask if the team wants to use the time to fully discuss the concerns raised during the meeting.
Immediately acknowledge the team members concern, continue with the scheduled agenda, then privately meet with the team member to fully understand the concerns expressed.
Correct Option:D
EXPLANATION
Conflict should be addressed in private, first, to better understand the concern being raised. Exploring the concern after the meeting gives the PM an opportunity to verify the concern and determine needed next steps without disrupting the meeting with all meeting attendees.
45A project manager has been asked to conduct a risk analysis that is based on a high-level scope. As part of the analysis, the project manager must use expert judgment to prepare a document. Which document-based action is being performed?
SELECT THE CORRECT ANSWER
Creating the project charter
Preparing the scope statement document
Creating a project management plan
Documenting the risk management plan
Correct Option:A
EXPLANATION
Expert judgment is one of the tools and techniques for developing the project charter. PMBOK Guide Sixth Edition (2018), 4. Project Integration Management 4.2.1 Develop Project Charter, p79
47A project manager receives complaints from a project sponsor because of a delay in developing a prototype. The project manager responds that the delay was due to a lack of knowledge in a specific skill that was needed by the cross-functional project team. How could the project manager avoid this type of situation in the future?
SELECT THE CORRECT ANSWER
Create training sessions at the start of the project, so all necessary skills are learned.
List required skills for the project, and organize the project team based on those skills.
Consult with the project sponsor to add training once the lack of a specific skill becomes apparent.
Empower team members to problem solve where skills may be lacking, using the skills they do have.
Correct Option:B
EXPLANATION
Develop the human resource management plan by defining the roles and responsibilities of the project team members in order to create a project organizational structure and provide guidance regarding how resources will be assigned and managed. PMBOK Guide Sixth Edition (2018), 9. Project Resource Management / 9.3.3 Develop Team: Outputs, p343 | The Agile Practice Guide (2017), 4 Implementing Agile: Creating An Agile Environment / 4.3.3 Generalizing Specialists, p42