2.
What is the most significant evident outcome you can expect when your team members are empowered?
SELECT THE CORRECT ANSWER
Humility
Leadership
High buy-in and trust
Conflict
Correct Option:C
EXPLANATION
An empowered team always has a better buy-in and displays high levels of trust.
6
As part of project planning, you refer to organizational practice and defined tolerance limits. Which of the following includes the key areas where tolerance limits are set?
SELECT THE CORRECT ANSWER
Quality, budget
Budget, time, quality, and non-functional requirements
Budget, time, and quality
Scope, schedule, and cost
Correct Option:B
EXPLANATION
Besides setting a tolerance limit for budget, quality, and time, you also need to define acceptable limits for deviations (non-compliances) for non-functional requirements. This will help you as a project manager to move forward swiftly with minimal escalations.
7
Tracking compliance information, including the proof of validation for each deliverable, is generally done as part of:
SELECT THE CORRECT ANSWER
Scope management
Stakeholder management
Risk management
Configuration management
Correct Option:D
EXPLANATION
One of the key attributes to be tracked is compliance of a deliverable with a defined requirement. Tracking the proof for validation of the compliance of the deliverable is done as part of configuration management (although it might sound like compliance management).
9
A risk breakdown structure is created as part of:
SELECT THE CORRECT ANSWER
Risk qualitative analysis
Risk identification and categorization
Risk response
Risk ownership
Correct Option:B
EXPLANATION
Once the risks are identified, they are categorized based on the source, like external, internal, technical, and project management. This gives the risk breakdown structure.
13A document that is normally prepared before the business case and expresses what needs to be produced or what is the goal of the project is called:
SELECT THE CORRECT ANSWER
Business needs document
Business case
Customer requirements document
Requirements documentation
Correct Option:A
EXPLANATION
The business needs document captures the goal of the project product or service what needs to be created.
15The data analysis technique used to identify different ways of collecting requirements to elaborate on project and product scope is called:
SELECT THE CORRECT ANSWER
Design of experiments
Iterative gathering
Alternative analysis
Brainstorming
Correct Option:C
EXPLANATION
Alternative analysis is the evaluation of various ways in which requirements can be collected from stakeholders, and this can have an impact on the scope management plan.
16SMART acronym is used while defining KPIs. While generally the ‘R’ in the acronym stands for ‘Realistic’, in the context of project management it denotes:
SELECT THE CORRECT ANSWER
Real time
Recurring
Relevant
Reasonable
Correct Option:C
EXPLANATION
The target needs to be relevant in the context of the larger objectives and critical success factors.
18You are in the process of assessing the performance of your team productivity. You want to use the data to predict the output for future iterations as well. The tool that is generally used for this is:
SELECT THE CORRECT ANSWER
Velocity
RACI matrix
Throughput
Kanban
Correct Option:A
EXPLANATION
It is the sum of the story point sizes for the features actually completed in an iteration. This allows the team to plan its next capacity more accurately by looking at its historical performance.
19Mind Mapping and Affinity Diagram are examples of:
SELECT THE CORRECT ANSWER
Techniques for data consolidation
Techniques for data gathering
Techniques for data elicitation
Techniques for data representation
Correct Option:D
EXPLANATION
Mind mapping and affinity diagram are examples of techniques for data representation.
21Which of the following is effective in measuring project compliance with quality? (Choose two)
SELECT THE CORRECT ANSWER(S)
Using QA outputs to confirm deliverable compliance
Risk analysis
Issue resolution
Sign-off and approval from stakeholders
Correct Option:A, D
EXPLANATION
Both QA outputs to confirm deliverable compliance and Sign-off and approval from stakeholders are effective in measuring project compliance with quality.
24Henry is the project manager who is in the process of understanding the requirements. He is going through the available Business and Marketing plan, service agreements, and process diagrams. What technique is he using?
SELECT THE CORRECT ANSWER
Requirements mapping
Document analysis
Traceability matrix
Brainstorming
Correct Option:B
EXPLANATION
A technique where the existing available documents are gone through to generate more understanding about the project’s requirements.
26
In Agile projects, teams use a ceremony to communicate and address impediments slowing down the progress of work. This ceremony is called:
SELECT THE CORRECT ANSWER
Retrospective
Scrum facilitation
Daily stand-ups
Sprint review
Correct Option:C
EXPLANATION
A daily stand-up meeting with the scrum team is a daily routine which serves as a communication platform for the team to address blocks and impediments.
29Common tools to track the performance of a team in AGILE include: (Choose two)
SELECT THE CORRECT ANSWER(S)
Scrum or Kanban board
Throughput
Project board
Blackboard
Correct Option:A, B
EXPLANATION
Common tools to track the performance of team in AGILE includes: Scrum or Kanban board and throughput.
32One of your team members, who is not very experienced in Agile methodologies, is informing you that the product owner has made some changes to the product backlog and has explained the changes to the team. The other team members have accepted and made changes to the backlog. This new team member is not sure if this is the normal practice in Agile. You explain to him that the product backlog changes throughout the project. The term that refers to this practice of changing the product backlog based on changes to business requirements is called:
SELECT THE CORRECT ANSWER
Product backlog item
Backlog grooming and refinement
Daily stand-up
Retrospective
Correct Option:B
EXPLANATION
In backlog grooming and refinement, the product owner is tasked with the responsibility of looking at the impact of any change and looking at ways to reprioritize the backlog items.
33Agile projects tend to avoid using absolute time estimates as the level of uncertainty in the work is often high. Instead, a relative measure of estimation is used. Which of the following is an example of the relative estimation method?
SELECT THE CORRECT ANSWER
Factoring
Three point estimating
Story point estimating
Planning poker
Correct Option:C
EXPLANATION
Requirements are explained as stories and story points rate the relative work, risk, and complexity of a requirement or story. Agile teams use story points to estimate effort.
34Changes to external and internal environmental factors can affect the project and its outcomes. A framework used to analyze the external factors impacting the project is:
SELECT THE CORRECT ANSWER
Business complexity
Competitive strategies
PESTLE
SMART
Correct Option:C
EXPLANATION
PESTLE (stands for Political, Economic, Social, Technological, and Environmental) is used to analyze the external factors which impact the project.
35
A team’s checklist for a user-centric requirement that has all the information the team needs to be able to begin working on is called:
SELECT THE CORRECT ANSWER
Definition of done
WBS
Definition of ready
Scope delineation
Correct Option:C
EXPLANATION
Definition of ready is a team’s checklist for a user-centric requirement that has all the information about the team’s needs.
37The famous Quality Trilogy is attributed to:
SELECT THE CORRECT ANSWER
Peter Drucker
Joseph Juran
Philip Crosby
Edward Deming
Correct Option:B
EXPLANATION
The Juran trilogy gives the concept of quality management with its underlying three universal processes of quality planning, quality control, and quality improvement.
40Your team is very experienced in the predictive approach. The new project that is being taken up now requires an Agile approach. You need to support and mentor the team members for the required transformation. Which of the following will be most useful in this situation? (select two)
SELECT THE CORRECT ANSWER(S)
Reading Agile magazines
Training team members in Agile ceremonies
Lessons learned from previous Agile projects
Outsource a specialist Agile team
Correct Option:B, C
EXPLANATION
Historical lessons from previous projects will also be helpful.
42Business risks impact the project. Choose three business risks from the following:
SELECT THE CORRECT ANSWER(S)
Competitive
Scope related
Legislative
Operational
Correct Option:A, C, D
EXPLANATION
Competitive, legislative, and operational risks are the business risks that impact the pr
45A classification model that groups stakeholders on the basis of their level of authority, their immediate needs, and how appropriate their involvement is in terms of the project is known as:
SELECT THE CORRECT ANSWER
Impact grid
Salience model
KANO model
None of the above
Correct Option:B
EXPLANATION
This classification model uses power versus legitimacy, or urgency of stakeholders.
48You have successfully completed a project for setting up a e-commerce website. You have conducted a successful demonstration of the portal and the customer is happy. The product is transitioned and the site is thrown open to public. After a month, when the traffic increased, it is noticed that the response of the website became very slow. You get a call from customer asking you to fix the issue immediately. You find that this is primarily due to the sizing of the hardware. What requirement should have been taken care of to avoid this scenario?
SELECT THE CORRECT ANSWER
Operational requirements
Training
Non-functional requirements
None of the above
Correct Option:C
EXPLANATION
Non-functional requirements, or NFR, include capacity, availability, scalability, and security, which need to be carefully analyzed and understood before making the design.
50A high-level visual summary of the product or products of the project that includes goals, milestones, and potential deliverables is called:
SELECT THE CORRECT ANSWER
Product roal
Product strategy
Product roadmap
Product lifecycle
Correct Option:C
EXPLANATION
Product roadmap contains milestones and deliverables over a period of time.
51You and your team are engaged in the process of finding out redundancies, bottlenecks, and non-value efforts in a process end-to-end that can potentially cause unnecessary delays. What process are you involved in?
SELECT THE CORRECT ANSWER
Value stream mapping
Process mapping
Root cause identification
None of the above
Correct Option:A
EXPLANATION
The focus of the value stream mapping exercise is to not only remove wasteful efforts to make processes lean, but also to ensure maximum value flow to customers.
52You are in the process of defining the scope of the product that will be delivered as the final output of the project. You are analyzing the product in terms of characteristics and using all relevant aspects of the product to better understand it. What kind of tool are you using?
SELECT THE CORRECT ANSWER
Scope verification
Value analysis
Requirement analysis
Product analysis
Correct Option:D
EXPLANATION
Product analysis is thorough analysis of the features for better understanding.
54You and your team are finalizing the project’s scope statement. The scope statement contains: (Choose two)
SELECT THE CORRECT ANSWER(S)
Work, deliverables
Assumptions and constraints
Resources
WBS
Correct Option:A, B
EXPLANATION
Scope statement includes description of work, deliverables, assumptions and constraints.
56Which of the following are part of the resource calendar? (Choose two)
SELECT THE CORRECT ANSWER(S)
Training dates
Availability of resources
Interdependencies between resources
Working days
Correct Option:B, D
EXPLANATION
Availability of resources and working days are part of the resource calendar which gives the period of engagement of resources.
57The goals of retrospectives in Agile are different from sprint reviews. A retrospective is not: (Choose two)
SELECT THE CORRECT ANSWER(S)
Demonstration of the product
Generate insights
Identify areas for improvement
Getting feedback on the product
Correct Option:A, D
EXPLANATION
Retrospective is done to generate insights and identify areas for improvement.
58A team member is working on identifying areas for improvement in the project. He wants to know how to go about it. Which of the following would be a good source to start with?
SELECT THE CORRECT ANSWER(S)
Historical lesson learned
Sprint review
Demonstration
Meetings
Correct Option:A, D
EXPLANATION
Lessons learned from previous projects are a good starting point to identify areas for improvement. Then you look at lessons from retrospectives in this project.
60Change requests approved by the change control board normally consist of: (choose three)
SELECT THE CORRECT ANSWER(S)
Preventive actions
Scope control
Defect repair
Corrective actions
Correct Option:A, C, D
EXPLANATION
Change requests can comprise preventive actions, corrective actions, and defect repair.
63The presence of a set of factors which may not motivate but the absence of which would definitely demotivate the team members is known as:
SELECT THE CORRECT ANSWER
Reward factors
Hygiene factors
Motivational factors
X factors
Correct Option:C
EXPLANATION
According to Herzberg’s theory, real motivational factors are responsibility and recognition.
65Your team is in the process of finalizing the type of contract for procurement. It is observed that the procurement statement of work is not precise and there are some constraints which do not permit further clarity in defining the statement of work. It is agreed amongst stakeholders that the team can go for a slightly open-ended and flexible arrangement with the seller. Which of the following contract types would be best suited?
SELECT THE CORRECT ANSWER
Fixed price incentive fee contracts
Cost plus fixed fee
Time and materials or T and M
Fixed price-EPA
Correct Option:C
EXPLANATION
Time and materials or T and M contract works best for flexible arrangements.
67You are starting a new space related project. A project charter has been created and handed over to you. What is the next step?
SELECT THE CORRECT ANSWER
Sign the charter for acceptance
Start planning
Identify stakeholders
Identify risks
Correct Option:C
EXPLANATION
The next step is to identify stakeholders in the project.
69One of your key stakeholders wants to review the product’s completion by comparing it against the requirements. Which document would you present to him?
SELECT THE CORRECT ANSWER
Project scope statement
Product requirements
WBS dictionary
Requirement traceability matrix
Correct Option:B
EXPLANATION
Completion of product scope is compared against product requirements.
72An organizational construct that focuses on the flow of value to customers through delivery of specific products and services is called:
SELECT THE CORRECT ANSWER
Product strategy
Value stream
Service delivery
Product catalogue
Correct Option:B
EXPLANATION
Value stream is the value delivered to customers through a product or service.
76Risk management plan contains:
SELECT THE CORRECT ANSWER
What are the techniques to identify risk
How risks would be identified, analyzed, managed, and monitored
How the risk audit will be done
What are the responses planned
Correct Option:B
EXPLANATION
It is a subsidiary plan which describes the approach and methodology of how risks will be managed in the project.