1A key characteristic of a High-Performing team is that team members:
SELECT THE CORRECT ANSWER
Are familiar with each other
Have a shared understanding of the project
Live in the same location
Have the same cultural background
Correct Option:B
EXPLANATION
High-performing teams have a shared understanding of and commitment to the project.
2A project team is performing the work of the project to achieve its objectives. Which of the following is not potentially a project team?
SELECT THE CORRECT ANSWER
Project management staff who perform budgeting and reporting.
Project staff who create project deliverables.
Customer representatives who provide requirements
Stakeholder group
Correct Option:D
EXPLANATION
Stakeholder group is the larger group of people and organisations and not all are part of the project team
3A project manager is performing project resource management. Which of the following is NOT a critical part of this activity?
SELECT THE CORRECT ANSWER
Obtain people
Facilitate interactions
Develop project scope
Manage team personnel changes
Correct Option:C
EXPLANATION
Project scope is part of Plan and Manage Scope while Project Resource management is concerned with the team.
4Your project manager is working on preparing a stakeholder register. Who among the following would be his least priority?
SELECT THE CORRECT ANSWER
Sponsor of your project
Functional managers for team members
Director of procurement in your organisation
Project team member of a competing organization
Correct Option:D
EXPLANATION
Sponsor, functional managers for team members and Director of procurement in the organisation are relevant stakeholders to consider as they can have direct impact on the project. A project team member of a competing organization might be the least of his priority while identifying and developing an appropriate stakeholder engagement strategy for a project.
5A project manager has been working with the team on task assignment and following were the final assignments for developing project management plan: John and Steve were assigned as Responsible for the task William and James were assigned as Accountable for the task. Jacob was identified as the SME and was marked under Consult Program Manager Jack was marked under Informed of the RACI chart. Which of the following statements are true about RACI chart
SELECT THE CORRECT ANSWER
Chart cannot have more than one person assigned for Responsible
Chart cannot have more than one person assigned as Accountable
Chart cannot have more than one person assigned as Informed
Chart cannot have more than one person assigned for Consulted
Correct Option:B
EXPLANATION
We have only one person assigned for Accountable in RACI chart
6Project ABC is geographically distributed and has members from different backgrounds. Project manager Sam is working on building a productive climate for the team. Which of the following is not an attribute of diversity and inclusion?
SELECT THE CORRECT ANSWER
Team members using a local language in project communication
Team members being conscious of group contrasts
Objecting to discrimination and bigotry
Establishing conditions where different types of groups can thrive
Correct Option:A
EXPLANATION
Communication is one of the key challenges in virtual teams. The team should agree on a common language to be used which is conducive to members of all regions. The team members using the local language in project communication can be detrimental to the team as not all of them might understand the local language if the team is geographically distributed.
7A project team along with their project manager are working on identifying activity resources. Which of the following do you need to consider while producing a resource calendar?
SELECT THE CORRECT ANSWER
Working days and holidays
Availability of physical resources
Attributes like skills and geographies
All of the above
Correct Option:D
EXPLANATION
Resource calendar includes all of the above, along with identifying details of when and how long the resources are available for the project.
8Virtual teams could be ideal for geographically distributed projects, but they have their certain challenges. Which of the following is a challenge for virtual teams?
SELECT THE CORRECT ANSWER
Recruiting experts from all around the globe
Bonding with geographically dispersed team members
Higher cost of operations
Lack of information radiators to help share information
Correct Option:B
EXPLANATION
Virtual teams are groups of people with shared goals with little or no time spent on face-to-face interactions. These teams are distributed across geographies with occasional physical meetings, while some never get a face-to-face meeting. Bonding and team identification can be difficult because finding ways to provide a sense of team spirit and cooperation is difficult compared to a co-located team.
9Key members of a project are in the process of defining and assigning individual and team responsibilities. Which of the following is most critical for this team while the project management method is still not finalized?
SELECT THE CORRECT ANSWER
Understanding the location and time zone of team members
Knowing the attitudes of team members
Having open communication and effective collaboration
Skill and experience of team members
Correct Option:C
EXPLANATION
Project responsibilities within a team Open communications and effective collaboration are critical regardless of the specific project management method chosen
10A project team is trying to agree on actions that are acceptable and unacceptable in the project management context. This is done to set expectations for performance and decrease risk of confusion. Which of the following stakeholders are an important part of this?
SELECT THE CORRECT ANSWER
Project sponsors
Customer representatives
Project management staff
Project team members
Correct Option:D
EXPLANATION
Team charter and ground rules should be produced by the team or at least with the teams active participation
11Negotiations ensure mutual understanding prior to entering a contract. Which of the following might not be included in the agreement documents?
SELECT THE CORRECT ANSWER
Statement of Work
Benefits management
Subcontractor approvals
Termination clauses
Correct Option:B
EXPLANATION
Statement of work, subcontractor approvals, and termination clauses should be included in the agreement document.
12An important feature in Agile is to maintain a prioritized list of backlog. Which of the following is NOT a prioritization technique?
SELECT THE CORRECT ANSWER
Monte Carlo simulation
Kano model
MoSCoW analysis
100 Points Method
Correct Option:A
EXPLANATION
Monte Carlo simulation is a technique used to understand the impact of risk and uncertainty in prediction and forecasting models.
13It is critical to understand the required competencies when forming and developing high-performing teams. Which of the following is used to determine team weaknesses?
SELECT THE CORRECT ANSWER
KANO model
PERT
SWOT
100 Points Method
Correct Option:C
EXPLANATION
SWOT is a technique used to analyze Strengths, Weaknesses, Opportunities, and Threats. Project manager can leverage SWOT analysis to improve overall team performance as well as challenges, that the team will need to overcome for better performance
14Estimations are fundamental in every project. Which of the following is used as an estimate in Agile projects?
SELECT THE CORRECT ANSWER
Absolute time estimate
Relative measures
Three point estimate
Hours of effort
Correct Option:B
EXPLANATION
Story Point estimating uses relative measures, which can be helpful as an integrated assessment to provide time estimates.
15Teams in Agile approach take accountability to ensure that all the work required for an iteration is delivered. Which of the following statements is not true?
SELECT THE CORRECT ANSWER
Agile teams are self-organized.
Task accountability need not be tracked.
Team members pull work for an iteration.
User stories are decomposed into required tasks.
Correct Option:B
EXPLANATION
Accountability of tasks should be tracked in an Agile approach.
16Tuckman’s ladder model describes 5 stages of team development . Which of the following is not true about this model?
SELECT THE CORRECT ANSWER
Teams are in the Forming stage at the beginning.
Team disperse as part of the Adjourning stage.
Conflicts are high during Storming stage
Teams do not find themselves returning to a stage once they have passed it.
Correct Option:D
EXPLANATION
Teams find themselves returning to one or more stages at different times in a project. Strong innovative people will disagree from time to time.
17The Project Manager of a team observes that the project team is spending too much time during standups though this is meant to be a 15-minute ceremony every day. What could be the possible cause of this?
SELECT THE CORRECT ANSWER
Team members might not be sticking to the agenda
The team might be trying to find solutions to problems that were brought up.
Team might not be making effective use of parking lot to discuss issues post the standup meeting
All of the above
Correct Option:D
EXPLANATION
Standup meetings should be focusing on the following 3 questions for every team member and are typically timeboxed for 15 minutes: What did you do yesterday? What will you do today? Are there any impediments?
18It is important to have a clear vision for every project. Sam states that Vision is about bridging the gap between where we are and where we want to be. John mentions that Vision is about satisfying customer needs based on the requirements provided. Vinod says that Vision is only meant for the organization as a whole and not required for a project. Joe states that Vision is a desired end state. Who among them is correct about Vision?
SELECT THE CORRECT ANSWER
Sam and John
Vinod and Joe
Joe
Vinod
Correct Option:C
EXPLANATION
Vision is a desired end-state and it is critical to have a clear vision of the desired end objectives for a new project.
19Project Charter is a document issued by the:
SELECT THE CORRECT ANSWER
Project Team
Sponsor
Project Manager
None of the above
Correct Option:B
EXPLANATION
Project Charter is a document issued by the Sponsor or project initiator
20Agile has certain ceremonies like daily standup, sprint review, and sprint retrospective. Which of the following is not true about the ceremonies?
SELECT THE CORRECT ANSWER
Daily standups are status meetings.
Sprint planning is a collaborative event for planning the project release.
Both A and B are wrong
Both A and B are correct
Correct Option:C
EXPLANATION
Sprint planning plans the work for the current sprint, not an entire project. Daily standups are not status meetings. The are required for a team to reaffirm commitment to its objectives, coordinate work among team members, and surface potential blockers.
21Kanban board is a tool that: (Mark all correct choices)
SELECT THE CORRECT ANSWER(S)
Enables teams to create WBS
Helps identify bottlenecks
Helps in project selection
Works as an information radiator
Correct Option:B, D
EXPLANATION
Kanban board is a visualization tool that enables improvements to the flow of work by making bottlenecks and work quantities visible
22Fist of five technique is used for building consensus. A fist is a statement of:
SELECT THE CORRECT ANSWER
Agreement with a team’s conclusion
Strong disagreement
General agreement with minor questions
Minor disagreement
Correct Option:B
EXPLANATION
A fist (or 0 fingers) is a strong statement of disagreement and will require adjudication.
23A project team is discussing story points to be used for estimates. Which of the following is correct when it comes to story points?
SELECT THE CORRECT ANSWER
Story points must strictly follow the Fibonacci sequence.
A story point of 5 indicates a day’s work.
The team decides on the benchmark for story points.
8 story points indicate 8 hours of effort.
Correct Option:C
EXPLANATION
Story points are unit-less and attempt to capture the overall impact of work. The team agrees on a benchmark based on known level of work which can be used for relative comparison.
24XP Metaphor describes a common vision on how a program works. Metaphors are not intended to be:
SELECT THE CORRECT ANSWER
Simple
Technical
Helpful in understanding the overarching approach
Easily understood by a broad array of stakeholders
Correct Option:B
EXPLANATION
Metaphors should be simple and non-technical to enable a large array of stakeholders to understand the overall program.
25Which is of the following techniques puts customers/stakeholders in the position of a marketer of the product?
SELECT THE CORRECT ANSWER
XP Metaphor
Product box exercise
Planning poker
None of the above
Correct Option:B
EXPLANATION
Product Box Exercise gets stakeholders to describe aspects of a solution in the same way a marketer might describe product features and benefits. It helps team understand the most critical value aspects of the solution.
26Customer ABC has a project requirement where they are not certain about the end product but would like to progress based on feedback and review of the development. Customer XYZ is clear about the requirements and has provided a detailed document of expectations along with the requirements. Which of the following methodologies would you follow for these customers?
SELECT THE CORRECT ANSWER
Predictive for customer ABC and Plan-Driven for customer XYZ
Predictive for both customers
Waterfall for customer ABC and Agile for customer XYZ
Predictive for customer XYZ and Agile for customer ABC
Correct Option:D
EXPLANATION
Agile methodology relies on customer feedback and collaboration to make progress and is best suited when the requirements for the entire project are not very clear.
27A senior member from the portfolio team of your organization has requested you to prepare a document to validate the benefits of a component since they do not have enough information. Which document would you prepare in this case?
SELECT THE CORRECT ANSWER
Project implementation plan
Business needs document
Charter
Business Case
Correct Option:D
EXPLANATION
Business case is a documented economic feasibility study used to establish the validity of the benefits of a selected component when there is a lack of sufficient information.
28Agile Practice Guide categorizes project life cycle into 2 major types:
SELECT THE CORRECT ANSWER
Agile and Predictive
Predictive and Adaptive
Predictive and Incremental
Incremental and Iterative
Correct Option:B
EXPLANATION
Two major types of project life cycle as per Agile Practice Guide are predictive and adaptive.
29Which of the following characterizes Adaptive life cycle as per Agile Practice Guide? Choose the best answer.
SELECT THE CORRECT ANSWER
Iterative
Incremental
Agile
All of the above
Correct Option:D
EXPLANATION
Adaptive life cycle is Iterative, Incremental. and Agile
30You are nominated as a project manager and presented an overview of the project in which the outcome is well understood and cost is determined in the early phase. Which lifecycle represents this the best?
SELECT THE CORRECT ANSWER
Agile
Iterative
Predictive
Incremental
Correct Option:C
EXPLANATION
A predictive life cycle is one in which project scope, time and cost are determined in the early phases of the life cycle. This cycle is preferred when the project outcomes are well understood and known.
31Which technique allows a large number of ideas to be classified into groups for analysis?
SELECT THE CORRECT ANSWER
Mind mapping
Affinity diagram
Plurality
Benchmarking
Correct Option:B
EXPLANATION
Affinity diagram is a technique that allows large numbers of ideas to be classified into groups for review and analysis.
32A project manager requests his subject matter experts to build visuals to represent the project outcome with an intent to illustrate the functioning of a product. Which of the following is the project manager expecting from the SMEs?
SELECT THE CORRECT ANSWER
Work breakdown structure
Storyboarding
Join application design
Quality function deployment
Correct Option:B
EXPLANATION
Storyboarding is a prototyping method that can use visuals or images to illustrate a process or represent a project outcome.
33Planning packages in WBS are:
SELECT THE CORRECT ANSWER
Activities meant for creating a plan
Components of known content without detailed schedule activities
Components in WBS with detailed steps to achieve a deliverable
All of the above
Correct Option:B
EXPLANATION
Planning package is a WBS component below the control account with known work content but without detailed schedule activities
34Code of Accounts in WBS is used:
SELECT THE CORRECT ANSWER
As a management control point
As a tracking system by finance to verify costs
As a work package with dependencies
To identify components
Correct Option:D
EXPLANATION
A code of accounts is a numbering system used to uniquely identify each component of the WBS.
35Which of the following can a Scope Baseline include?
SELECT THE CORRECT ANSWER
Cost baseline
Benefits plan
Planning package
Business case
Correct Option:C
EXPLANATION
A scope baseline may include any of the following components: Project scope statement, WBS, Work package, Planning package, WBS dictionary
36Work and activities from the WBS can be placed in backlogs. Which of the following is correct about backlogs?
SELECT THE CORRECT ANSWER
A product backlog is a list of all expected work.
A product backlog changes throughout the project.
Backlog items are added as necessary.
All of the above
Correct Option:D
EXPLANATION
The product backlog is essentially a list of all expected work to deliver the product. A project’s product backlog changes throughout the project based on prioritization.
37User stories are written by:
SELECT THE CORRECT ANSWER
Product owner
Anyone in the project team
Customer representatives
Project lead who assigns the work
Correct Option:B
EXPLANATION
User stories can be written by anyone in the team
38A typical user story contains:
SELECT THE CORRECT ANSWER
Risks
Constraints
Assumptions
Value
Correct Option:D
EXPLANATION
User stories describe the value/objective.
39Which of the following is NOT a tool/technique for verifying scope?
SELECT THE CORRECT ANSWER
Definition of Done
Definition of Ready
Acceptance Criteria
Team review comments
Correct Option:D
EXPLANATION
DOD, DOR, and Acceptance criteria are tools and techniques for verifying the scope.
40A project manager is reviewing a checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use. What is the checklist called?
SELECT THE CORRECT ANSWER
Definition of Ready
Validation of Scope
Definition of Done
Acceptance Criteria
Correct Option:C
EXPLANATION
Definition of Done is a team’s checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use.
41A few team members are determining the cause and degree of difference between a baseline and actual performance. The team is involved in:
SELECT THE CORRECT ANSWER
Trend analysis
Variance analysis
Acceptance analysis
Assumption analysis
Correct Option:B
EXPLANATION
Variance Analysis is a technique for determining the cause and degree of difference between the baseline and actual performance.
42A project team has identified all the WBS elements and has completed its estimates. The project manager is now working toward creating a cost baseline. Which of the following should not be considered for this?
SELECT THE CORRECT ANSWER
Cost estimates of WBS elements
Contingency reserve
Management reserve
Cost estimate of software licenses
Correct Option:C
EXPLANATION
A cost baseline is the approved version of the time-phased project budget, excluding any management reserves.
43A charter for a simple project without much dependency is approved, and the team is working on Iterative scheduling. Which of the following is NOT true about Iterative scheduling?
SELECT THE CORRECT ANSWER
The method uses progressive elaboration
Iterative scheduling works best for complex projects with dependency
Stories that provide the highest value are prioritized
Stories are prioritized based on how long they take
Correct Option:B
EXPLANATION
Iterative scheduling with a backlog does not work well with activities that have complex dependency relationships.
44Which of the following is not true about Agile release planning?
SELECT THE CORRECT ANSWER
Agile does not have release planning since its focus is on sprints.
Release planning determines the number of iterations needed.
Release planning determines features that each iteration will contain.
Release planning determines target date for each release.
Correct Option:A
EXPLANATION
Agile release planning is a process in which you determine the number of iterations that are needed to complete each release, features that each iteration will contain, and target dates of each release.
45When do we use Agile methodologies in a project?
SELECT THE CORRECT ANSWER
During Initiation and Conclusion
During Execution
During Monitoring and Control
All of the above
Correct Option:D
EXPLANATION
Agile is a framework used across the lifecycle of the project.
46Project Manager Rachel is preparing for a phase gate review, and some of her peers are concerned because the project does not have any product deliverables. Which of the following is correct about phase gates?
SELECT THE CORRECT ANSWER
Every phase gate must have a product ready for customer inspection.
Phase gates are overhead and do not serve any purpose.
Phase gates are required only at the end of a project, before delivering the product to a customer.
A phase gate is a review at the end of a phase.
Correct Option:D
EXPLANATION
Phase gate, also known as governance gate, is a review at the end of a phase in which a decision is made to continue to the next phase.
47An Agile team is preparing for its retrospective. Which of the following is NOT correct about retrospectives?
SELECT THE CORRECT ANSWER
A retrospective is a review of what went well
A retrospective is a review of what could have been done better
A retrospective assesses team collaboration.
The product owner is not included as this is for the agile team
Correct Option:D
EXPLANATION
A retrospective meeting consists of the agile team, product owner, and key stakeholders
48Which of the following is correct about Minimum Viable product?
SELECT THE CORRECT ANSWER
It is used to determine a usable product for the customer
Low hanging activities in a logical order
Activities required to build basic infrastructure for the team such as office, seating, and administrative details.
Meant only for agile teams to logically align their activities
Correct Option:A
EXPLANATION
Minimum Viable product is used to determine a usable product for the customer in each increment and understand the core value sought by the project.
49Minimum business increment best works for:
SELECT THE CORRECT ANSWER
A new product ideation
Creating MVP for a new product release
Products that are live and in-use
None of the above
Correct Option:C
EXPLANATION
Minimum Business Increment works best when the product and functions are understood or for improving products that are live and in-use.
50Which of the following is NOT true about timeboxes?
SELECT THE CORRECT ANSWER
Keep the team focused
Help project teams set up time blocks
Allow for better telemetry over time
Help project manager set working hours for teams
Correct Option:D
EXPLANATION
Timeboxes are typically in the form of week or days. They help keeping the team focused and help provide better telemetry over time.
51Diversity is an important element to implement effective leadership. One should be aware that the working style of individuals varies based on:
SELECT THE CORRECT ANSWER
Experience
Job role
Age
All of the above
Correct Option:D
EXPLANATION
Motivations and working styles of individuals and groups vary greatly based on their experiences, age, culture, job roles, and many more influencers.
52Which of the following is not a trait of servant leadership?
SELECT THE CORRECT ANSWER
Providing coaching
Removing impediments
Facilitating and guiding
Having the team work for you
Correct Option:D
EXPLANATION
Servant leadership is where you work for the team; the team does not work for you.
53Value stream mapping is used to:
SELECT THE CORRECT ANSWER
Develop earned value management
Develop expected monetary value
Analyze flow of information
Compute overall value of the project
Correct Option:C
EXPLANATION
Value stream mapping is used to document, analyze, and improve the flow of information or materials required to provide a product or service for a customer.
54A project team is discussing daily standup meeting since some of them are new to this. Which of the following is not true about daily standups?
SELECT THE CORRECT ANSWER
They are best conducted at the start of working hours.
Only team members facing impediments are required to attend
They are typically short, 15-minute meetings.
All team members focus on 3 basic questions.
Correct Option:B
EXPLANATION
Daily Standup meetings should be conducted at the start of working hours, and the presence of all team members involved in the Sprint is mandatory.
55Impediments and blockers can be identified at various stages by the team. Which of the following is NOT true about impediments?
SELECT THE CORRECT ANSWER
Can be uncovered during daily standups.
Can be represented using sticky notes on a whiteboard
Can be tracked using sophisticated software
Cannot be a result of project risks
Correct Option:D
EXPLANATION
Impediments may be due to or as a result of project risks or issues.
56A team charter is a document that supports a productive project environment. Which of the following is NOT true about team charter?
SELECT THE CORRECT ANSWER
Is a document
Records agreements of team members
Authorizes a project
Records team values
Correct Option:C
EXPLANATION
A team charter is defined s a document that records the team values, agreements and operating guidelines as well as establishing clear expectations regarding acceptable behaviour by project team members.
57Personality profile assessment can help assess and present the personality profile of each individual, which suggests ways to work with them. Which of the following is not a personality style assessment for individuals?
SELECT THE CORRECT ANSWER
DiSC model
Theory of Psychological types
Tuckman’s model
True colors methodology
Correct Option:C
EXPLANATION
Tuckman’s model articulates team formation cycle and is not about individual styles
58Maintaining compliance requirements is a necessity as part of managing a project. Compliance requirements must be maintained:
SELECT THE CORRECT ANSWER
Only if a project needs interactions with government authorities
Only during project closure
At the beginning to get the required approvals from sponsor
Throughout the project
Correct Option:D
EXPLANATION
It is necessary to maintain visibility into compliance requirements throughout the project.
59Most projects have aspects that are subject to legal or regulatory constraints, and the requirements for compliance must be managed through the project. Identify aspects that are NOT included in the compliance requirements.
SELECT THE CORRECT ANSWER
Privacy laws
Handling sensitive information
Data retention
None of the above
Correct Option:D
EXPLANATION
Requirements for specific practices, privacy laws, handling of sensitive information, and many other areas are subject to regulatory constraints
60Project risks are captured, tracked, and managed using a risk register. Which of the following is true in relation to compliance with legal and regulatory requirements?
SELECT THE CORRECT ANSWER
Risks related to compliance should include risk owner and impact.
Compliance validation must be assured as the project deliverables are created.
Risks are meant for the project team and are not related to compliance.
Both A and B
Correct Option:D
EXPLANATION
Identified risk, owner, impact and risk responses should be tracked to establish compliance with legal and regulatory requirements. It is also necessary to assure compliance validation as the deliverables are created.
61Customers can consider buying insurance from a third party that will assume the financial risk as a risk response. Which of the following is NOT true about managing risks?
SELECT THE CORRECT ANSWER
Some of the financial risk may be shared among stakeholders.
Project teams can take action to potentially improve the likelihood of realizing the positive risk.
Residual risks are not required to be tracked.
Project manager, along with other stakeholders, need to determine appropriate response.
Correct Option:C
EXPLANATION
Ongoing actions should be taken to continue to manage residual risks and identify additional responses as needed.
62Some of the senior team members in a project are classifying compliance. The team comes up with a list of categories, which includes environmental risk, Workplace safety, corrupt practices, social responsibility, quality, and process risks. The architect does not agree that social responsibility and process risks are categories for compliance. The test lead believes that process risks is a correct category but social responsibility does not have any meaning and cannot be considered a compliance category. The development manager states both social responsibility and process risks can be part of the compliance category classification. Who is correct about compliance categories classification?
SELECT THE CORRECT ANSWER
Architect
Development Manager
Test Lead
None of the above
Correct Option:B
EXPLANATION
There are many different types of compliance categories that may be necessary for a particular industry and solution scope. This may include social responsibility and process risks.
63Project managers need to ensure that compliance requirements for the project are continually identified and managed. Which of the following is least important for potential threats to compliance?
SELECT THE CORRECT ANSWER
Bugs in deliverables
Changes in regulatory requirements
Changes in legal requirements
Architect resigning
Correct Option:D
EXPLANATION
Potential threats to compliance include errors or bugs in deliverables, changes in legal or regulatory requirements and more.
64Which of the following is NOT a non-functional requirement?
SELECT THE CORRECT ANSWER
Security of confidential information during transaction
Capacity of enough supply to meet demand
Product feature to enable online purchase
Both A and B
Correct Option:C
EXPLANATION
Non-functional requirements focus on usability and level of service warranty of the deliverables.
65Identify where tolerance levels and thresholds can be set.
SELECT THE CORRECT ANSWER
Budget
Time
Nonfunctional requirements
All of the above
Correct Option:D
EXPLANATION
Areas of tolerance might include budget, time, quality, and nonfunctional requirements.
66Which of the following is done by QA?
SELECT THE CORRECT ANSWER
Review the deliverable so that it meets functional and nonfunctional requirements
Suggest potential improvements
Make recommendations to address any noncompliance
All of the above
Correct Option:D
EXPLANATION
As the project team produces deliverables, quality assurance (QA) will review the deliverable, verify that it meets functional and nonfunctional requirements, and often identify and suggest potential improvements. QA will validate whether the deliverables align with compliance requirements and provide feedback on any variances.
67What is an immediate next step when a noncompliance issue is identified?
SELECT THE CORRECT ANSWER
Escalate to the sponsor as this is a compliance issue and needs immediate action
Determine if it is within the tolerance level of the project manager
Escalate to adjudication
Option A followed by option C
Correct Option:B
EXPLANATION
When a noncompliance issue is identified, the next step is to determine whether it is within the tolerance level of the project manage
68Quality audits are used to verify compliance and are generally conducted by an external team. Audits are generally used to: (Choose all options that are correct)
SELECT THE CORRECT ANSWER(S)
Share good practices from other projects in the organisation or industry
Highlight contributions to lessons learned
Identify critical path
None of the above
Correct Option:A, B
EXPLANATION
Quality audits are used to verify compliance with organizational policies, processes, and procedures. They are generally used to identify good practices being used, share good practices from other projects, proactively offer improvements to improve productivity, and highlight contributions to lessons learned.
69Which of the following are components of Business value?
SELECT THE CORRECT ANSWER
Employee knowledge
Customer value
Channel partner value
All of the above
Correct Option:D
EXPLANATION
Shareholder value, customer value, channel partner value, and employee knowledge are all part of business value.
70A project management plan can contain many subsidiary plans. Which of the following is not correct about Benefits Management Plan?
SELECT THE CORRECT ANSWER
It describes how the benefits of a project will be derived.
It describes how the benefits are measured.
It is a subsidiary component of the project management plan.
It describes when the benefits will be realized, usually by project phase.
Correct Option:C
EXPLANATION
Benefits Management plan is a business document and is not a subsidiary component of the project management plan.
71Your company has organized a user conference. In a discussion with one of your company’s customers, you ask them a question related to their satisfaction with your company’s product. The customer replies that they would be willing to work with another provider since they were not satisfied with your company’s product. How would you categorize this customer on the NPS scale?
SELECT THE CORRECT ANSWER
Passive
Promoter
Detractor
None of the above
Correct Option:C
EXPLANATION
Detractors would be willing to work with another provider since they were not satisfied with your solution.
72Which of the following is NOT true about internal business environment changes?
SELECT THE CORRECT ANSWER
They may change organizational roles.
They may reprioritize existing deliverables.
They will not impact the business case of an existing project already underway.
They may change the workflows.
Correct Option:C
EXPLANATION