PMP TEST 1 Flashcards
1The Project Manager shifts to an agile approach for a project with an aggressive go-to-market timeline. The Project Manager needs to revise the stakeholder plan so that it follows agile principles. What should the Project Manager do to meet this need?
SELECT THE CORRECT ANSWER
Design a digital communication system that allows for virtual submission, logging, reviewing, and escalation of issues
Remove unnecessary layers of management to promote direct communication between the project team and stakeholders
Modify templates to include product backlog progression and the burndown rate and encourage use of standups
Increase the number of formal training workshops to cover all relevant issues for all stakeholders, including the project sponsor and client
Correct Option:C
EXPLANATION
Servant leadership requires shared responsibility. Changing documentation and processes across the team toward agile methodologies ensures that all team members are kept up to date on expectations, roles, and responsibilities.
Project team members are concerned that a new resource does not seem suitable for an assigned task. How should the project manager respond to this concern?
SELECT THE CORRECT ANSWER
Contact senior management to discuss the possibility of reassigning the new resource to a different project.
Schedule time to chat with the new resource to assess their skills and understand their strength level.
Ask the team members to document task-related deficiencies displayed by the resource.
Contact the project sponsor to highlight these concerns and decide on an appropriate response.
Correct Option:B
EXPLANATION
A project manager should not take action by just listening to other members feedback. He should talk to the new member to find out about his strength and make some evaluation later. PMBOK Guide Sixth Edition (2018) PMI, 9. Project Resource Management / 9.4 Develop team, p338 | The Agile Practice Guide, 2.2 The Agile Manifesto and Mindset , p8
3A Project Manager develops a project management plan and schedule based on an agreed-upon project life cycle of 16 months. Later, due to changing business requirements, the Project Manager receives a request for completion within 9 months. How should the Project Manager respond to this proposed change in timeline?
SELECT THE CORRECT ANSWER
Work with key stakeholders to identify project requirements that could be reduced
Immediately ask project team members to increase the pace of each task within the project
Modify the original project schedule so that revised deadlines can be met
Meet individually with project team members to discuss how aspects of the project can be completed more quickly than planned
Correct Option:A
EXPLANATION
To execute the project quickly, the project team should discuss on the whole scope together and find out the way to complete tasks at individual level within short time. By the discussion, many tasks could be by-passed from the base tasks and new tasks can be identified, which might help the project to reduce the total time frame of the project. This is the agile mindset of the Project Manager by which more value can be delivered in a shorter period of time.
4During an agile iteration, Task 1 cannot be completed on time due to unexpected challenges. Another team within the project is depending on timely completion of Task 1 in order to fulfill their part of the project. How should the Project Manager resolve this issue?
SELECT THE CORRECT ANSWER
Meet with both teams separately and ask them to figure out a way to meet the required deadlines and complete the project on time
Meet with the product owner to reprioritize the iteration backlog so that it does not impact other teams or obligations
Increase the number of team members for the project team and increase the iteration length ensuring that the work will be completed according to schedule
Let team members know you want them to do their best under difficult circumstances, and make sure to note the iteration’s challenges in lessons learned
Correct Option:B
EXPLANATION
The hybrid approach might also involve evaluating iteration backlog items’ priorities to resolve time constraints.
5The project manager schedules an iteration review and learns that a few key stakeholders do not approve of how a feature has been developed. What should the project manager do first in order to address this issue?
SELECT THE CORRECT ANSWER
Invite project team members to a brainstorming session to identify an appropriate response.
Address the issue only after evaluating why these stakeholders are concerned.
Determine the impact of the conflict by listing the pros and cons of the situation.
Ask the project sponsor to act as a neutral party in negotiation with those stakeholders who are dissatisfied.
Correct Option:B
EXPLANATION
One of the required abilities of Project Managers is to identify when the conflict escalates. If it happens, the Project Manager should help to facilitate a satisfactory solution, addressing conflict early, in private and using a direct and collaborative approach. PMBOK Guide Sixth Edition (2018), 9. Project Resource Management / 9.5.2 Manage Team: Tools and Techniques, p348
6While reviewing the issues log, the Project Manager notices that tasks assigned to two team members are quite a bit behind schedule. What should be done?
SELECT THE CORRECT ANSWER
Notify the responsible team members of the need to complete the overdue tasks quickly in order to avoid introducing extra project risks.
Tell the team members who are behind schedule that they should explain why tasks were delayed and how they will get back on schedule.
Document the issue, escalate to the project sponsor, and ask for how they would like it resolved.
Work with the relevant team members to review the delayed tasks and decide on strategies for resolution.
Correct Option:D
EXPLANATION
The Project Manager needs to be proactive and review the activities with the team and to identify resolution strategies.
7A Project Manager realizes that sponsor expectations are not being met, specifically regarding project deliverables. To address this issue, what action should the Project Manager take?
SELECT THE CORRECT ANSWER
Update the risk register
Develop a stakeholder engagement plan
Develop a communications management plan
Create a work breakdown structure (WBS)
Correct Option:A
EXPLANATION
The risk register may have existing entries about the potential for the sponsors’ expectations not being met that need updating. If there were no existing entries, then there will be new risks associated with any plan of action.
8During a meeting, a Project Manager learns that a business result needs to be delivered in four weeks, although the original plan was sixteen weeks. The Project Manager also hears that there is no available technical resource who might be able to join the team. The Project Manager knows the technical resource manager because they worked together on a previous project. What is the first thing the Project Manager should do?
SELECT THE CORRECT ANSWER
Since time is short, hire an outside party to meet the need for a technical resource
Check with the technical resource manager to see if there is an available technical resource
Immediately escalate the issue to decision-makers in the organization
Notify the project sponsor about the lack of a technical resource
Correct Option:B
EXPLANATION
As per the Agile manifesto one should value individuals and interactions over processes and tools. Thus, it is best to meet with the technical resource manager to understand the real situation rather than informing sponsor first which might be a false alarm.
9A team decides that an agile approach fits the needs of the next phase in their project. Unfortunately, there are team members who have not had the appropriate agile training. How should the project manager respond to the lack of agile training?
SELECT THE CORRECT ANSWER
Identify and implement the most cost-effective agile training for the team members.
Create virtual training sessions for key team members, covering the main agile topics.
Ensure the project’s contingency reserve can cover agile training for all team members.
Include agile training for these team members in a change request.
Correct Option:A
EXPLANATION
If project team members training results in added skills that could be useful for future phases or future projects, schedule training lessons and related costs could be evaluated to be included in resource management plan and cost management plan. PMBOK® Guide Sixth Edition (2018) 9. Project resource Management / 9.4.2.6 Training, p342 | The Agile Practice Guide (2017), 4. Implementing Agile: Creating An Agile Environment / 4.2.1 Servant Leader Responsibilities, 37
10A Project Manager believes that a delay in developing a prototype was due to a lack of knowledge in a specific skill that was needed by the cross-functional team. How could the Project Manager prevent this situation in future projects?
SELECT THE CORRECT ANSWER
Offer more specialized training throughout the project to the team
Identify required strengths and organize the team based on those strengths
Meet with the project sponsor and team members to assign training for specific skills
Empower team members to problem solve in situations where skills may be lacking
Correct Option:B
EXPLANATION
Developing the team is an important part of servant leadership.
11A new Project Manager joins the projects daily standups only to find that the project team spends too much time discussing ways to deal with obstructions in the project. Because of these discussions, standups often last well over two hours. What process should be used to deal with this issue?
SELECT THE CORRECT ANSWER
Ask team members to invite their managers to standup sessions in order to find solutions more quickly
Explain to team members that long discussions take time away from actual work on the project
Insert a new team member who will manage obstacles and schedule additional meetings to discuss possible solutions
Tell the team members that they are required to shorten the standup meetings and improve on finding solutions
Correct Option:B
EXPLANATION
Shared responsibility is an important part of agile teams. The team charter should provide an outline of what meetings are for what purposes.
12A customer is not satisfied with the delivered product, saying that it was not what they expected. The project manager is surprised, because the agile development team delivered the product several iterations early. What is one way that the project manager could have avoided this result?
SELECT THE CORRECT ANSWER
Required team sign off for each of the constant changes to the requirements
Set aside more resources for product testing after changes are made
Made sure that the customer was aware of the value of demos
Ensured that the team fully participated in developing the project scope
Correct Option:C
EXPLANATION
The customer was not engaged enough in the project. The iteration review is the best mechanism for the team to demonstrate working software and for the customer to give feedback to ensure that their expectations are met. PMBOK Guide Sixth Edition (2018), 13. Project Stakeholder Management / 13.3 Manage Stakeholder Engagement,524 | The Agile Practice Guide (No Date), 5 Implementing Agile: Delivering in and Agile Environment / 5.2.5 Demonstrations/Reviews, 55
13A Project Manager’s team has been efficiently delivering expected results in an environment where budget and scope are fixed. Now, there is an increased demand for new skills due to changes in the market. What can the Project Manager do to meet this new demand?
SELECT THE CORRECT ANSWER
Meet the new demand by adding new resources with the required skills
Hire a third-party vendor who can provide resources with the needed skills
Change the distribution of partially-dedicated resources with the needed skills
Meet the new demand by upgrading the existing team members’ skills
Correct Option:A
EXPLANATION
Developing the team is very important. However, in a situation where time is limited, the most efficient option is expanding the team to included skilled resources.
14A project team is small and the team members have known each other for a long time. The team’s project is in the execution phase. Recently, a team member told the new project manager that another team member has been complaining about how the project is being managed. How should this new project manager respond?
SELECT THE CORRECT ANSWER
Preview the current stakeholder engagement plan for the way to resolve the difficulty.
Schedule a mandatory team meeting which will lead to the creation of a new social contract.
Notify team members that they should submit anonymous recommendations for a new social contract.
Send a survey to team members, requesting suggestions for dealing with the dissatisfaction.
Correct Option:B
EXPLANATION
A) No - While this may help in addressing the situation, it will not help to rectify any existing damage done to the team as a result of the situation. B) Yes - This is the best solution. It encourages every team member to particulate and results in a clear set of guidelines for the team. C) No - This is not the best answer. While this will create a set of guidelines, they may not be the best ones for the team. D) No - This is not the best solution as it does not encourage team cohesion and self leadership. PMBOK Guide Sixth Edition (2018), 9. Project Resource Management / 9.1.3.2 Team Charter, 319 | The Agile Practice Guide (2017), 5. Implementing Agile: Delivering In AN Agile Environment / 5.1 Charter The Project And The Team p50
15During a highly-regulated project, the project sponsor and a high-level executive have asked for changes that appear to disregard legal requirements. What should be the first step in the project manager’s response?
SELECT THE CORRECT ANSWER
Immediately schedule a meeting with the stakeholders to review the situation.
Send the change control board (CCB) a change request.
Check with the organization’s relevant legal practitioner for guidance.
Review the organization’s lessons learned database for precedents and direction.
Correct Option:C
EXPLANATION
A) No - This is not the best response as you may not fully understand the situation. B) No - This is necessary but is not the first step. C) Yes - This is the best FIRST step before going to the CCB because this is a highly regulated industry. D) No - While this may provide guidance, this is not ultimately your decision to decide. PMBOK Guide Sixth Edition (2018), Part 2 The Standard for Project Management / 1.3 Linking Organizational Governance and Project Governance PMI, p545 | Project Managers Portable Handbook, 3rd Ed (2010) Section 6. Project Initiation and Execution / 6.3 Legal Considerations and Execution
16A project manager has multiple projects. One project has new team members and is in its early stages. Unfortunately, the project manager will be very busy executing other projects over the next few weeks. How can the project manager develop the new project team over the next few weeks?
SELECT THE CORRECT ANSWER
Help the team create a social contract that will encourage team cohesion.
Suggest that the team engage in multiple team-building events to normalize the team.
Keep the team informed by sending short daily project status updates.
Engage in face-to-face personal conversations with each team member to build relationships.
Correct Option:A
EXPLANATION
A) Yes - This will allow the team to normalize themselves and be self-servicing when you are unavailable. B) No - This may be productive, but it is a one-time activity and does not encourage self-servicing when you are unavailable. C) No - This does not encourage the team to get to know each other and become self-servicing. D) No - While this may result in deeper relationships, there is not enough time for this and it does not encourage the team to get to know each other. PMBOK Guide Sixth Edition (2018), Part 2 The Standard for Project Management / 1.5 The Project Lifecycle, pp 547-548
17A Project Manager needs to ensure that the team delivers business value within the required timelines. The manager recently learned that key stakeholders are worried that the current release plan will not meet urgent business needs. What can the Project Manager do to effectively respond to the stakeholder concerns?
SELECT THE CORRECT ANSWER
Renegotiate scope with the project sponsor after examining the work breakdown structure (WBS)
In consultation with the stakeholders and team members, identify the minimum viable product needed for launch
Determine the schedule performance index (SPI) and escalate the schedule risk to the project sponsor
Monitor progress using a burndown chart after modifying the schedule baseline to meet stakeholder requirements
Correct Option:A
EXPLANATION
Assuming that the work can be completed may create new issues. It is best to work with the project sponsor and see if there is any scope that can be reduced to meet a more realistic timeline.
18A key stakeholder voices a concern during the planning stage about whether the available resources are sufficient to meet the objectives of the project. The Project Manager believes that the stakeholder is right. How should the Project Manager handle this stakeholder’s concern?
SELECT THE CORRECT ANSWER
Review the bounds of the negotiations for agreement
Determine the project’s ultimate objectives after carefully evaluating project priorities
Engage in agreement negotiations for better resources
Ensure that the impact of the unavailability of required resources is fully documented
Correct Option:D
EXPLANATION
Fully documenting the impact of situation ensures that all stakeholders are aware of any risks, issues, quality concerns, etc.
19A project manager notices that one team member seems increasingly unhappy during team meetings. The team member is not making progress on a key work package, and this lack of progress is now impacting the critical path. The team member feels that they are not in the correct role within the project team. What should the project manager do?
SELECT THE CORRECT ANSWER
Reassure the team member about their abilities by reminding them that they were chosen for a reason.
Meet with the team member to discuss where they can contribute, based on their strengths.
Enroll the team member in targeted training to acquire the needed skills for their assigned role.
Schedule weekly touchpoints with the team member to discuss barriers that may impact their work.
Correct Option:B
EXPLANATION
A) No - This is positive reinforcement, but it may be unwarranted. B) Yes - This is the best response. The individual may truly be right. As a Servant Leader, you can help them find the correct role. C) No - This is helpful, but it doesn’t address the core of their concern. D) No - This creates a false sense of momentum that doesn’t address the core of their concern. PMBOK Guide Sixth Edition (2018), Part 2 The Standard for Project Management 1. Introduction 1.7 Role of the Project Manager, p552 | The Agile Practice Guide (2017), 4. Implementing Agile: Creating An Agile Environment / 4.2.1 Servant Leader Responsibilities 34
20A project owner repeatedly complains, saying that a function developed by the development team does not seem to align with the original design. What will help to solve this issue?
SELECT THE CORRECT ANSWER
Ask the product owner to sit in on the next iteration review meeting to learn more about the development status for the product.
Ask the quality assurance team to identify any mismatches in functionality compared to the initial design.
Ask the development team to rewrite the function so that it matches with the project scope.
Schedule time during the next retrospective session to discuss all corrective actions and ask the project owner to participate in the session.
Correct Option:D
EXPLANATION
Retrospective can discuss the product release status, whether the team reaches any other milestone. It can be used by project manage to survey all necessary parties to reach consensus and build understanding. PMBOK Guide Sixth Edition (2018), 8 Project Quality Management / 8.3.2.6 Meetings, p305 | The Agile Practice Guide (2017), 5. Implementing Agile: Delivering In An Agile Environment / 5.2.1 Retrospectives, pp 50-51
21A customer indicates that they would like to add functionality. Although this request is made during the execution phase of the project, the project manager finds that the cost for the addition would be small. The additional functionality, if successful, would increase the opportunity for profit. What should the project manager do next?
SELECT THE CORRECT ANSWER
Agree that the functionality would offer a great opportunity, but the proposed addition is out of scope.
Schedule a meeting with the company’s management team, and present the customer’s request for additional functionality as a good opportunity.
Move forward, using the project’s management reserve to add the requested functionality.
Identify an already-developed feature that could be combined with the new functionality and use the combination to meet the customer’s request.
Correct Option:B
EXPLANATION
By building a small increment and then testing and reviewing it, the team can add value in terms of new functionalities or additional awarded projects. Important factor for a successful implementation and value capture is the response time of the team. PMBOK Guide Sixth Edition (2018), 1. Introduction / 1.2.4.1 Project and Development Life Cycles, p19
22A customer requests a change in the technical approach for a product currently in development. The project manager learns about this request during a reoccurring project review. What should the project manager do in response to the customer’s request?
SELECT THE CORRECT ANSWER
Work with team members to immediately implement the new approach.
Have the team decide on the appropriate approach, giving them authority to implement their decision and validating their decision in talks with stakeholders.
Discuss the pros and cons of the proposed approach with stakeholders, then select the approach that is best for the team and notify team members.
In order to obtain sponsor buy-in, have the team to benchmark the approach.
Correct Option:B
EXPLANATION
As a technical issue the project management should address the team to assess and select the best options to solve, empower then and improving engagement. The Agile Practice Guide (2017), 2 An Introduction To Agile / Figure 2-2 The Twelve Principles Behind the Agile Manifesto, p9 | The Agile Practice Guide (2017), 4 Implementing Agile: Creating An Agile Environment / 4.2 Servant Leadership Empowers The Team, p33
23A Project Manager realizes during the third iteration of product development that the template used for the project management plan is not showing updates. Which action should the project manager take?
SELECT THE CORRECT ANSWER
Assign one team member to update the project management plan template and document any risk
Rank the need to update the template according to the business value for the upcoming iterations
Avoid adding to team distraction by fixing the issue independently
Document the issue as a new project risk and propose a solution
Correct Option:D
EXPLANATION
This issue may or may not also be a risk to future iterations. Documenting it as a new project risk also ensures that there is a proper risk analysis performed to analyze what could happen in different scenarios.
24During a challenging shareholder meeting, the customer indicates that they will reject an iteration’s deliverable. What should the project manager do?
SELECT THE CORRECT ANSWER
Send a request to the project sponsor, asking them to update the project charter then reassign the responsibilities and authorities.
Meet with the project team to add new and improved features to replace the features that were rejected.
Work with stakeholders to create a shared approach that will address the issues of concern.
File a change request with the change control board (CCB) in order to add budget to the baseline.
Correct Option:C
EXPLANATION
Before initiate any action the project manager should work with the team to identify the root cause of the problem and build an approach to conduct the project for the next iterations. As a hybrid approach a retrospective ceremonial can be a good option to solve this situation. PMBOK Guide Sixth Edition (2018), Part 2 The Standard for Project Management / 5. Monitoring and Controlling Process Group / 5.1 Monitoring and Controlling Project Work, p 615