PMP TEST 2.1 Flashcards

1
Q

1
Which organization structure is a combination of all structures?
SELECT THE CORRECT ANSWER

Tight Matrix

Strong Matrix

Composite

Functional

A

Correct Option:C

EXPLANATION

Composite structure is a combination of all organizational structures.

1) Tight Matrix- collocated
2) Strong Matrix - the project manager with equal or more power than the functional manager. The project manager has primary control over resources
3) Composite - combination of all structures
4) Functional - organization is grouped into departments where people with similar skills are kept together in forms of groups

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

3
You are in charge of managing a software development project that is related to simulations for driving racing cars. In one of your team meetings, it is revealed that a lot of issues have been reported in the air tunnel modelling module. On deeper analysis, it is found that many of the issues could have been prevented had a simple code review checklist been used. You prepare a code review checklist and ensure the code is reviewed per the checklist. This is a good example of:
SELECT THE CORRECT ANSWER

Corrective Action

Preventive Action

Defect Repair

Quality Control

A

Correct Option:A
Nonconformity - issues reported during Quality Assurance

1) Corrective action - is always preceded by nonconformity
2) Preventive action - is never preceded by nonconformity

3) Defect repair - issues found in the current delivery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

5
You are managing a software development project for a banking product. In one of the team meetings, a debate arises if defects found during Quality control need to undergo change control. Some team members are convinced that all defects should undergo change control, while others are convinced that defects need not undergo change control. Which of the following statements is untrue?
SELECT THE CORRECT ANSWER

Defects to deliverables need to undergo change control

Defects to deliverables need not undergo change control

Corrective actions need to undergo change control

Preventive actions need to undergo change control

A

Correct Option:B

EXPLANATION

Defects to deliverables, corrective actions, and preventive actions need to undergo change control. So, all the above statements, except option B, are true.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

7
You are in charge of a project that deals with laying out a lavish 18-hole golf course. You have a number of contractors working on the project and you know that communication is key to success of the project. You have identified 10 stakeholders with whom you need to communicate. Due to some internal and external organizational changes at the client’s end, three new stakeholders have been added with whom you need to communicate. You also had to reduce one of the contractors with whom you were communicating. How many communication channels do you have now?
SELECT THE CORRECT ANSWER

45

78

91

66

A

Correct Option:D

EXPLANATION

Originally, you had 10 stakeholders to communicate with, so the number of communication channels was 10 * (10-1) /2 = 45. However, 3 new stakeholders were added, while 1 stakeholder was removed. So, the total number of stakeholders = 10 + 3 -1 = 12. The total number of communication channels is (12 * (12-1)) /2 = 66.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

8
You are in charge of a project, and to ensure things go well, you have had monthly meetings with the stakeholders. The project is running on schedule and budget. You are in your fourth month of execution, but the stakeholder indicates dissatisfaction with the deliverables. Making changes in the deliverables would mean a delay in the schedule. Which process could have prevented this situation?
SELECT THE CORRECT ANSWER

Scope Planning

Scope Control

Schedule Control

Risk Monitoring and Control

A

Correct Option:A

EXPLANATION

The process that could have prevented this situation is Scope Planning. Project deliverables are defined during scope planning, so proper implementation of this process could have prevented this situation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

10RISK
Your company has bagged a number of government contracts dealing with setting up infrastructure. This includes setting up roads and bridges. This is a very big and prestigious project, so your company wants to ensure everything is planned well in advance. You are the project manager of this project. Considering its importance, you and your team come up with a list of risks. One of the subject matter experts indicates that during the months of July and August, the construction work of the bridge across the river would need to stop on account of past history of flooding of the river. You agree with the expert and plan the schedule accordingly. What strategy did you just apply?
SELECT THE CORRECT ANSWER

Accept

Exploit

Mitigate

Transfer

A

Correct Option:A

EXPLANATION

This is an example of Risk acceptance strategy as there is nothing you can do about situations not in your control. Risk exploitation is meant for positive situations, while risk mitigation is where you have a strategy to either reduce the risk impact or probability. Transfer is also not correct as the question does not state that someone else will be responsible for handling the risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

12
You are managing a project that has teams located in different parts of the world. While the advantage of colocation is beneficial, the team structure or locations cannot be changed. Being an experienced manager, you realize that lack of a proper communication channel can quickly lead to chaos. What would your choice of communication be?
SELECT THE CORRECT ANSWER

Formal and Verbal

Formal and Written

Informal and Written

Informal and Verbal

A

Correct Option:B

EXPLANATION

Considering cross-located teams and difference in cultures, the best choice of communication in this case would be formal and written.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

14
You head the engineering department in your company. Lately, you have observed that certain deliveries of a specific team member are missing the schedule. You decide to discuss it with the team member. Initially, the team member is reluctant to discuss but finally opens up and indicates that the cause of the delays is often different instructions coming in from you as well as the project manager. She indicates that at such times she is confused about whose instructions to follow, thereby causing delays. What kind of an organizational structure is this most likely to be?
SELECT THE CORRECT ANSWER

Functional

Projectized

Weak Matrix

Balanced Matrix

A

Correct Option:D

EXPLANATION

1) Funcional - organization is grouped into departments where people with similar skills are kept togethe
2) Projectize - works by arranging activities into portfolios or programs and executing them through projects.
3) Week matrix - functional manager controls the project budget
4) Balnced matrix - authority is balanced between the project manager and the functional manager

Here the team member is being expected to follow instructions from both the Project Manager and the Functional Manager. This is never the case in a Functional or Projectized organization where the lines of authority are clearly defined. A weak matrix organization is more like a Functional Organization where the project manager has almost no authority. The scenario explained above is typical of a balanced matrix organization where power resides equally distributed between the functional and project manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

15The release criteria include:
SELECT THE CORRECT ANSWER

The timing of the release of team members

The method in which you will release them

Both of the above are true

None of the above

A

Correct Option:C

EXPLANATION

The release criteria include both the timing of the release of team members and the method in which you will release them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

16As a project manager, you have successfully delivered all project deliverables within stipulated timelines. Your senior management wants you to calculate the Cost of Quality. As a project Manager, what costs would you NOT consider while making this calculation?
SELECT THE CORRECT ANSWER

Cost of Hiring

Prevention costs

Appraisal costs

External and Internal Failure costs

A

Correct Option:A

EXPLANATION

Option A is incorrect as hiring costs have nothing to do with Cost of Quality. Prevention and Appraisal Costs refer to expenditure during the project to avoid failures, while Internal and External Failure Costs are those incurred during and after the project because of failures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

17Which of the following is part of the Manage Quality process?
SELECT THE CORRECT ANSWER

Benchmarking

Cost of Quality

Design of experiments

Quality audits

A

Correct Option:D

EXPLANATION

Quality audits are part of the Manage Quality process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

18You are the project manager for a project. You are updating the WBS during Define Activities. This process is often called ________.
SELECT THE CORRECT ANSWER

Refinement

Update

Analysis

Supporting detail

A

Correct Option:A

EXPLANATION

Updating the WBS during Define Activities is often called Refinement. It occurs with riskier projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

19
The Project Quality Management process must __________.
SELECT THE CORRECT ANSWER

Address the quality of the product

Improve project management

Ensure that the project satisfies customer requirements

All of the above

A

Correct Option:D

EXPLANATION

Project Quality Management addresses both the management of the project and the product. It improves project management as well as the quality of the product. It ensures that the project will satisfy customer requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

21
You are managing a project and you have decided to outsource a part of the project to a vendor. You have offered a bonus to the vendor if the work is completed in two months. This is an example of:
SELECT THE CORRECT ANSWER

Project incentive

Project goal

Fixed price contract

None of the above

A

Correct Option:A

EXPLANATION

This is an example of project incentive.

Bonus as additional motivation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

22
You and your team have just created a schedule network diagram. You have come up with the estimates, defined the durations, and identified the Critical Path. You now decide to do a Backward Pass through the Schedule Network Diagram. What would you be calculating?
SELECT THE CORRECT ANSWER

The Early Start and Early Finish for each activity

The Late Start and Late Finish for each activity

The duration of paths other than the critical path

The duration of the critical path

A

Correct Option:B

EXPLANATION

Options C and D are incorrect as Backward Pass is not used to calculate the duration. In fact, the critical path is calculated based on duration. Option A talks about Early Start and Early Finish, which are calculated using Forward Pass. Backward Pass is used to calculate the Late Start and Late Finish of all the activities in the network diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

23
Of the following types of contracts, which has the highest risk for the seller?
SELECT THE CORRECT ANSWER

Cost plus fixed fee - CPFF

Time and Material - T and M

Firm Fixed Price Contract - FFP

Cost plus Incentive fee CPIF

A

Correct Option:C

EXPLANATION

The riskiest for the seller among the options stated is Firm Fixed Price Contract, FFP. It’s a Fixed price contract in which total costs are fixed. The scope of work is clearly defined and stated. Cost-reimbursable contracts are the least risky for the seller since the costs are not fixed and paid at actuals. Time and material have medium risk from the perspective of the buyer and seller and are typically used for smaller dollar amounts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

25
You are in charge of a software project that is almost 40% complete. The project stakeholders want a performance report to date. You had planned to use Earned Value Management methodology. You come up with the following numbers: EV = 100, AC = 300, PV = 150, and BAC = 600. Your team has faced numerous issues till now. However, you choose to ignore the current work performance and decide to go with what was originally planned. Based on this information, what would be the EAC for the project?
SELECT THE CORRECT ANSWER

800

200

600

1800

A
EV - Earn value
AC - Actual cost
PV - Planned value
BAC - Budget at complete
EAC - Estmate at complete

Correct Option:A

EXPLANATION

It is stated that the issues experienced in the project were ignored, so the past performance is not considered and the planned values are considered. So, EAC = AC + (BAC - EV) = 300 + (600 - 100) EAC = 800.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

26
Your team has delivered phase one of a project to the client. Based on client feedback and issues found by the client, you decide to do some introspection to identify root causes so that the subsequent deliverables do not face the same issues. What techniques would you choose to apply?
SELECT THE CORRECT ANSWER

Perform Quality Audits

Review Activity Network Diagrams

Look up Process decision program charts

Perform Process Analysis

A

Correct Option:D

Quality Audits - project activities conform to the policies and procedures

Activity Network Diagrams - used for scheduling,

Process decision program charts - used to anticipate intermediate steps

Process Analysis - used to identify a problem and its cause and develop preventive actions

EXPLANATION

Quality Audits are meant to ascertain if the project activities conform to the policies and procedures, so it is not the correct answer. Activity Network diagrams are used for scheduling, while Process decision program charts are used to anticipate intermediate steps. The correct answer is Process Analysis, which is used to identify a problem and its cause and develop preventive actions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

29
As a project manager, you are expected to calculate the cost of Poor Quality. The project work is in progress. What costs would you consider?
SELECT THE CORRECT ANSWER

Cost of Hiring

Prevention costs

Appraisal costs

External and Internal Failure costs

A

Correct Option:D

EXPLANATION

Cost of Hiring has nothing to do with cost of Poor Quality, so it is not the correct answer. Cost of Poor Quality is just another term for Failure Cost. Failure Costs are generally categorized into External and Internal Failure costs, so option D is correct. Prevention and Appraisal costs are costs of conformance, which are the costs incurred to avoid failures. Hence, these are not considered cost of Poor Quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

33
Earned Value Analysis is used to measure performance based on a few parameters. Identify them.
SELECT THE CORRECT ANSWER

Scope and Cost

Scope and Schedule

Scope, Cost, and Schedule

Cost and Schedule

A

Correct Option:C

EXPLANATION

Earned Value Analysis is used to measure performance based on Scope, Schedule, and Cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

36
Which of the following best describes Vroom’s Expectancy theory?
SELECT THE CORRECT ANSWER

Employees will put in efforts dependent on expectancy, valence, and instrumentality.

Employee motivation is not achievable

Hygiene factors will ensure that job dissatisfaction does not occur; however, it does not ensure job satisfaction.

People have needs starting with Physiological Needs and ending with self-actualization.

A

Correct Option:A

EXPLANATION

Vroom’s Expectancy theory is based on the idea that people believe there are relationships between the effort they put in at work, the performance reviews/ratings they are credited for the effort, and the rewards they receive from their effort and performance review ratings. So, people will be motivated if they believe that hard work and effort will lead to good performance reviews and good performance reviews will lead to desired rewards. This theory consists of three key elements: Expectancy (perception of an employee of how much and what amount of effort will lead to a desirable performance rating), Instrumentality (perception or expectation that a good performance rating would translate into a hefty salary hike), and Valence (preference of an employee for a certain reward). Option B is clearly unrelated to this theory, so it is not the correct answer. Option C is related to Herzberg’s Hygiene theory, so it too is not the correct answer. Option D is about Maslow’s Theory of Hierarchical needs, so it’s not the correct answer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

37
Who among the following gave the framework for Continuous improvement?
SELECT THE CORRECT ANSWER

Peter Drucker

Joseph Juran

Philip Crosby

Edward Deming

A

Correct Option:D

EXPLANATION

Deming’s cycle is known as PDCA-Plan-Do-Check-Act

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

39
The Scope Baseline consists of _____.
SELECT THE CORRECT ANSWER

Approved Project Scope Statement, WBS, WBS Dictionary

Preliminary Project Scope Statement, Approved Project Scope Statement, WBS, WBS Dictionary

Scope Management Plan, WBS, WBS Dictionary

Scope Management Plan, Approved Project Scope Statement, WBS Dictionary

A

Correct Option:A

EXPLANATION

Scope Baseline
Baseline: an initial estimate (scope, cost, schedule)
used for further planning and control.
Includes
* Scope Statement - describes, in detail, the project’s deliverables and
the work required to create those
* Work Breakdown Structure (WBS)
* WBS Dictionary - extra scope details organized
to assist in further planning and control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

41RISK
As a manager on a project, you have to ensure that the project delivers within the scheduled timelines with minimal rework and customer delight. For some time now, the project work is proceeding smoothly with a CPI and SPI a perfect 1. One of your team members approaches you and indicates the possible need for a long vacation on personal grounds two months from now. You look up the schedule and find that this team member is scheduled to execute activities that are on the critical path, and the team member’s absence in two months’ time would cause a delay in schedule. You decide to take some action and reschedule task allocation to ensure that this team member is not planned to work on any of the critical path activities. What did you just do?
SELECT THE CORRECT ANSWER

Mitigate the risk

Avoid the risk

Transfer the risk

Exploit the risk

A

Correct Option:B

EXPLANATION

You have avoided the risk. By interchanging the tasks, you have ensured that the resource who wants to go on a long vacation does not work on critical path activities. There is no question of exploiting the risk as this is not a positive risk. This is not a case of risk mitigation since you have neither created a backup plan nor come up with an alternate strategy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

43
Which of the following activities is not performed as a part of Project Closure?
SELECT THE CORRECT ANSWER

Ensuring all the deliverables meet contract requirements

Creating lessons learned and updating Organizational Process Assets

Final acceptance

Verifying scope

A

Correct Option:D

EXPLANATION

All the options except verifying scope are performed during project closure. Ensuring deliverables meet contract requirements and formal acceptance are key activities of project closure. Capturing lessons learned is also a very important activity performed during project closure. However, verifying scope is not performed during project closure. It belongs to the Monitoring and Controlling process group.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

44
You have recently taken over a project that is using Agile methodology. Your team is in the process of understanding the user requirements and trying to prioritize them. Which technique will be most useful?
SELECT THE CORRECT ANSWER

Interviews

Kano Model

Delphi Technique

None of the above

A

Correct Option:B

EXPLANATION

MoSCoW model, 100 points method, and Kano model are techniques generally used in Agile projects.

Kano model
Breaks down quality definitions of a project into 5
categories:
* Must-be - customers expect these and take them for
granted.
* 1-dimensional - result in satisfaction when fulfilled,
result in dissatisfaction when unfulfilled.
* Attractive - result in satisfaction when fulfilled,
do NOT result in dissatisfaction when unfulfilled.
* Indifferent - neither good, or bad, don’t result in
satisfaction or dissatisfaction
* Reverse - by satisfying some, dissatisfy others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

49
Which factors can either support or limit the project management options, act as inputs for planning processes, and have a negative or positive influence on a project outcome?
SELECT THE CORRECT ANSWER

Enterprise Environmental Factors

Organizational Standards

Norms

PMIS

A

Correct Option:A

EXPLANATION

These factors are conditions not under the immediate control of the team, but can influence, constrain, or direct the project, program, or portfolio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

51
You are in your third month of project execution, which is expected to continue for 14 months. Your sponsor has asked for a performance report. You decide to create an S curve. Based on the S curve, you report your Actual Cost, which is more than the Earned Value. Also, the Planned Value is greater than the Earned Value. What would be the interpretation of this data?
SELECT THE CORRECT ANSWER

The project is over budget and behind schedule

The project is on schedule and on budget

The project is over budget but on schedule

The project is on budget but behind schedule

A

Correct Option:A

EXPLANATION

This is because both SPI and CPI are less than 1.

Schedule Performance Index = EV/PV
Cost Performance Index = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

52
You have been asked to provide cost estimates for a project involving complete electrical installation in warehouses. As a project manager, you have had past experience in similar projects in your previous organization. The organization you have joined also has recently done a similar project. The executive management wants you to quickly come up with an estimate. What estimation technique would you adopt?
SELECT THE CORRECT ANSWER

Ask your previous organization for the estimates

Use Parametric Estimating technique

Use Bottom-up Estimating

Use Analogous Estimating

A

Correct Option:D

EXPLANATION

Analogous estimating relies on previous similar projects as the basis of estimation. So, it relies on historical information. This technique is used when there is limited amount of detailed information, like during the early phases of the project. It is less costly and less time-consuming. As time is a constraint, this is the best choice.

Top-down I perform an analysis at the whole-project level.
Fast, not too accurate.

           (2) variations that are top-down.

     * Analogous  (estimating by analogy, or history)
		  "uses history"
		 'Since similar projects have cost about $65,000,
		  this project should also cost about $65,000.'

     * Parametric (estimating by history and a little math/parameters)
		  "uses history and a bit of math
		 'Other projects have taught us it takes about 10 days to build
		  1 km of road. This project requires 10 km, therefore should take
		  about 100 days.'
		  Parameter -> 1 km road = 10 days duration...

Bottom-up I perform an analysis on each activity, and roll
the totals up to a single project total.
Accurate, not too fast.

		No variations. Merely Bottom-up.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

56
You have been assigned to a project that deals with developing a software product for the BFSI domain. You and your team are building the schedule network diagram. While sequencing activities, one of the Architects in your team suggests that rather than interacting with the database on every activity, you should introduce an activity that would cache the data. The team member argues that this will improve performance and suggests that the activity be introduced in the sequence prior to other activities that deal with database interaction. What kind of a dependency is this?
SELECT THE CORRECT ANSWER

This is an example of Mandatory Dependency.

This is an example of External Dependency.

This is an example of Discretionary Dependency or Soft Logic.

This is an example of Hard Logic.

A

Correct Option:C

EXPLANATION

Discretionary Dependency is also known as Soft Logic or Preferred Logic or Preferential Logic. Note that this is not a mandatory dependency as it is not a Must Have but more a Should have. Discretionary dependency decisions are usually based on best practices and business knowledge. In this case, a Software architect can be assumed to be an expert in his field.

Dependency:

  • Mandatory “hard logic”
    ‘Part of the way you have to do the work’ (“nature” of the work)
    “We need to wait 2 weeks for concrete to dry and cure before
    we start building.”
  • Discretionary “soft logic”
    ‘The team can use their preference or “discretion”’.
    ‘We can build the servers at our desk and then take them to the lab, or just build them in the lab…’
  • External (outside the work/project)
    “We can’t start construction until City Hall has approved Blue-prints.”
  • Internal (inside the work/project)
    ‘… within the team’s control…’
    “As soon as we’ve brought the concrete mix on-site, we can start building the concrete pad.”
31
Q

57
You and your team are in the process of creating WBS and WBS Dictionary. What would be the best choice of attributes in a WBS Dictionary?
SELECT THE CORRECT ANSWER

Work Package ID and Work Package Description

Work Package ID, Control Account ID, and Work Package Description

Work Package Description

Work Package ID, Control Account ID, Work Package Description, Acceptance Criteria, Responsible Organization, Cost, Assumptions

A

Correct Option:D

EXPLANATION

Options A, B, and C describe what a WBS Dictionary should contain. So, they all seem like the right choices. However, the question asks about the BEST choice of attributes in a WBS Dictionary, which is provided in Option D. Note that the WBS and WBS Dictionary are correlated by WBS Name and Work Package ID

32
Q

58
Project manager’s role is part time in _________ organization structure?
SELECT THE CORRECT ANSWER

Matrix

Composite

Functional

Projectized

A

Correct Option:C

EXPLANATION

PM’s role is part time in functional type of organization structure. The functional manager has authority.

33
Q

59S Curve depicts a relationship between:
SELECT THE CORRECT ANSWER

Resource Availability and time

Remaining budget and time

Actual Cost, Planned Value, and Earned Value

Cost and Quality

A

Correct Option:C

EXPLANATION

S curve shows a relationship between Actual Cost, Planned Value, and Earned Value.

34
Q

60Which of the following statements is false regarding Risk Management?
SELECT THE CORRECT ANSWER

All identified risks are maintained in the Risk Register.

Risk prioritization occurs in Qualitative Risk Analysis.

Risk prioritization occurs in Quantitative Risk Analysis.

Low-priority risks are maintained in a Watch List.

A

Correct Option:C

EXPLANATION

All of the statements are true except the statement regarding Quantitative Risk Analysis. Quantitative Risk analysis does not deal with prioritizing risks. The prioritization occurs in the Qualitative Risk Analysis process. Quantitative Risk Analysis deals with assigning numeric values to risks.

35
Q

62
You are in charge of a project for the electrical layout of a five-star hotel. You see this as a very simple project as you and your team have a lot of experience executing similar projects. As a result, your organization has a wealth of Organizational Process assets. You have worked out the exact details of the work involved and have a very detailed WBS with granular-level activities defined. You decide to employ the services of a contractor for laying out of the cable trays. What kind of a contract would be the best choice?
SELECT THE CORRECT ANSWER

Cost-reimbursable contract

Fixed-price contract

Time and Material contract

None of the above

A

Correct Option:B

EXPLANATION

When as a buyer you are clear of the scope and statement of work, the contract choice should be Fixed-price. In this type of contract, the scope is clearly defined, and almost all the risk lies with the seller. Here, the buyer has experience executing similar projects in the past and has also broken down WBS into detailed activities. So, the scope is clear, and the correct answer is option B.

36
Q

66You have asked your team members to provide estimates of tasks. You see that a specific team member has provided estimates on the higher side. You discuss this with the team member. The team member admits that they did not have an idea of how long the task would take, so they came up with an estimate and then doubled it to be safe. What is this known as?
SELECT THE CORRECT ANSWER

Lead

Lag

Free Float

Pad

A

Correct Option:D

EXPLANATION

Pad is adding time as a buffer to project estimate. As the team member was uncertain of the time it would take, they doubled the estimate to be safe. Padding is a sign of poor Project Management.

PAD - is adding time as a buffer to project estimate.
LAG - delay between tasks that have a dependency

37
Q

69
You are starting a new project. You break up the work into discrete work packages. To ensure that each work package has all the necessary details, you and your team decide to write down detailed information for each work package, such as Statement of work, details of the work package, and who will be responsible for the work package. Where would you store this information?
SELECT THE CORRECT ANSWER

Project Management Plan

WBS

WBS Dictionary

Approved Project Scope Statement

A

Correct Option:C

EXPLANATION

This is where this information is stored.

38
Q

71You know that the success of your project will be determined by how well you manage risks. You know that identifying risks upfront can help you be better prepared with risk response strategies. So, you decide to identify risks by taking help of experts. You have identified some experts, and rather than calling them to your office, you send them questionnaires. You promise them complete anonymity so that they give unhindered responses. What information gathering technique are you adopting?
SELECT THE CORRECT ANSWER

Brainstorming

Root Cause Identification

SWOT analysis

Delphi Technique

A

Correct Option:D

EXPLANATION

All the four options listed above are information gathering techniques, but the correct answer is Delphi Technique. This is a form of information gathering technique where inputs from experts is solicited anonymously without gathering them together.

39
Q

72Which of the following options best describes Achievement Theory of Motivation?
SELECT THE CORRECT ANSWER

Employees given a reward are most likely to be motivated.

People cannot be trusted and must be governed and monitored regularly to ensure tasks get done.

People are motivated by achievement, power, and affiliation.

Employees will put in an effort in direct proportion to the perceived review and reward.

A

Correct Option:C

EXPLANATION

Option A and Option D are related to Expectancy theory; Option B is related to Theory X style of management. So, these options are not the correct answers. Option C is the correct answer. The Achievement Theory of Motivation states there are three types of motivational needs: need for achievement, need for authority and power, and need for affiliation. As per this theory, a strong affiliation motivation undermines a manager’s objectivity because of the need to be liked, and this affects a manager’s decision-making capability. A strong authority motivation will produce a determined work ethic and commitment to the organization. Such people are attracted to the leadership role, though they may not possess the required flexibility and people-centered skills. People with strong achievement motivation make the best leaders, although there can be a tendency to demand too much of their staff in the belief that they are all highly achievement-focused and results-driven, which most people are not.

40
Q

73
The key benefits of __________ process is that it will maintain or increase the efficiency and effectiveness of stakeholder engagement activities as the project evolves and the environment changes.
SELECT THE CORRECT ANSWER

Plan Stakeholder Engagement

Identify Stakeholders

Manage Stakeholder Engagement

Monitor Stakeholder Engagement

A

Correct Option:D

EXPLANATION

The key benefits of Monitor Stakeholder Engagement process is that it will maintain or increase the efficiency and effectiveness of stakeholder engagement activities as the project evolves and the environment changes.

42
Q

82Identify the basic quality tools to facilitate, measure, and control quality.
SELECT THE CORRECT ANSWER

Cause and effect diagrams, Flowcharts, Check sheets, Pareto diagrams, Histograms, Control Charts, Sequence Diagrams

Cause and effect diagrams, Flowcharts, Check sheets, Histograms, Control Charts, Scatter Diagrams

Activity diagrams, Flowcharts, Check sheets, Pareto diagrams, Histograms, Control Charts, Sequence Diagrams

Cause and effect diagrams, Monte Carlo analysis, Check sheets, Pareto diagrams, Histograms, Control Charts, Scatter Diagrams

A

Correct Option:B

EXPLANATION

As per PMBOK Guide - Sixth Edition, Pareto chart is not included as a tool under control quality process.

43
Q

87The goal of value analysis is to improve the overall:
SELECT THE CORRECT ANSWER

Share Value

Product Value

Business Value

Stakeholder value

A

Correct Option:C

EXPLANATION

Value analysis is the process of examining each of the components of business value with an aim of increasing business value.

44
Q

89Legal or Regulatory requirements are part of:
SELECT THE CORRECT ANSWER

Compliance requirements

Non-functional requirements

Technical Requirements

Support Requirements

A

EXPLANATION

It is mandatory to comply with legal and regulatory requirements. Non-conformance is a potential threat to the project.

45
Q

92Which of the following is a classification model that groups stakeholders on the basis of their level of authority, their immediate needs, and how appropriate their involvement is in terms of the project?
SELECT THE CORRECT ANSWER

Power-interest Model

Power-Influence Model

Salience Model

Legal-Influence Model

A

Correct Option:C

EXPLANATION

Salience Model classifies stakeholders based on their authority, urgency (immediate involvement), and legitimacy.

46
Q

95A data point in a control chart that requires investigation is called:
SELECT THE CORRECT ANSWER

A special cause

A quality fault

A rule of seven

A rule of five

A

EXPLANATION

A data point in a control chart that requires investigation is called a special cause.

47
Q

96You have just begun a project. Some members have been given training on some skilled tasks, but you are apprehensive that the knowledge and skills may not be sufficient. You decide to put a few customer stakeholders together to enable them to interact with the team and learn from one another. This is called:
SELECT THE CORRECT ANSWER

Hands-on Training

Pairing and Mentoring

Shadow Training

None of the above

A

Correct Option:B

EXPLANATION

This is one of the ways by which a project manager can ensure knowledge transfer on the job.

48
Q

98You are managing a project, and to ensure things run smoothly, you have decided to provide project information periodically to all the stakeholders. You have decided that you would report against the baselines for scope, cost, and schedule. Which of the following would be the best choice?
SELECT THE CORRECT ANSWER

Performance reporting

Status reports

Forecasts

Risk Register

A

Correct Option:A

EXPLANATION

The best choice is Performance reporting with respect to the triple constraints - Scope, Schedule, and Cost. Forecasts are future projections, and risk register deals with risks. These are not the right options. While status reports could be an option, the best answer is Performance reporting.

49
Q

107Which of the following is NOT a form of communication?
SELECT THE CORRECT ANSWER

Formal and Informal

Written and Verbal

Precise and Vague

Vertical and Horizontal

A

Correct Option:C

EXPLANATION

Precise and vague are not forms of communication, while all others are.

50
Q

114You are in the process of making a cost estimate for a large prestigious project. You decide to use the Three Point Estimation technique with Triangular Distribution. Based on your analysis, you are confident that the project will be completed with a total cost of $108,000. You also estimate that a best-case estimate would be $90000, while a worst-case scenario would result in the costs shooting up to $138000. What would the Three point Cost estimate be?
SELECT THE CORRECT ANSWER

112000

110000

28000

None of the above

A

EXPLANATION

The question states the use of Three point estimate using triangular distribution. The formula for this estimation technique is a + b + c /3, where a = Most Likely estimate, b = Estimate based on analysis of the Best-case scenario, and c = Estimate based on analysis of the Worst-case scenario. So, the Three point estimate using Triangular distribution is 108000 + 90000 + 138000 / 3 = 336000/3 = $ 112000.

51
Q

115The project you’re managing is around 50% complete. You are creating Earned Value Methodology to report performance. Based on your calculations, you realize that the initial plan is no longer valid. However, you still need to provide an EAC. What is the best course of action?
SELECT THE CORRECT ANSWER

Calculate EAC as EAC = BAC / CPI

Calculate EAC as EAC = AC + BAC - EV

Calculate EAC as EAC = AC + (BAC - EV/(CPI * SPI )

Calculate EAC as EAC = AC + Bottom-up Estimate

A

Correct Option:D

EXPLANATION

Option A is to be used if past CPI is expected to continue. Option B is to be used if future work is going to be performed at the planned rate. Option C is to be used if both CPI and SPI influence remaining work. Option D is to be used when the initial plan is no longer valid, which is the case here.

52
Q

117Minimum Business Increment (MBI) works best when:
SELECT THE CORRECT ANSWER

Customer agrees to the scope

Sprints have long duration

Business team supports the sprint

Incremental increase in value can be seen

A

Correct Option:D

EXPLANATION

In Agile, earliest delivery of value is of paramount importance. The team decides the incremental value to be delivered in the next iteration.

53
Q

118In order to determine the details of the work to be performed in work packages, which of the following can be used?
SELECT THE CORRECT ANSWER

WBS

WBS Dictionary

Control Account

Work Packages

A

Correct Option:B

EXPLANATION

WBS Dictionary provides details such as description of work to be done for each work package, any schedule milestones, and statement of work. It is also used to prevent scope creep.

54
Q

119You need to provide estimates for activities on the project. You and your team discuss and conclude that as detailed information is not yet available, the best option would be to use Parametric Estimates. Which of the following is used to create Parametric Estimates?
SELECT THE CORRECT ANSWER

Critical Path Method

One-Time Estimate

Regression Analysis and Learning Curve

A

Correct Option:C

EXPLANATION

To arrive at parametric estimate, you need historical data based on which you will be able to parametrize the variables and arrive at a mathematical relationship between such variables.

55
Q

129Which of the following is not a Project Artifact?
SELECT THE CORRECT ANSWER

Business Case

Assumptions

Minutes of Board Meeting

Constraints

A

Correct Option:C

EXPLANATION

A Project artifact is any document related to the management of a project. Minutes of board meeting is not a part of the project.

56
Q

132To Complete Performance Index is used to:
SELECT THE CORRECT ANSWER

Determine when the project would be complete

Determine the feasibility of the project

Identify the risks in the project

Determine the cost performance required to meet certain objectives

A

ANSWER D

EXPLANATION

TCPI is a measure of the ratio of the work remaining to the funds remaining.

57
Q

133You are managing a project, and based on risk identification, you feel very confident that the project will run smoothly. The next day, the lead architect indicates a risk that was not envisioned. She indicates a 10% possibility of the risk occurring and the effort involved in choosing an alternate path worth 2000 USD. The impact of alternate path implementation is that a lot of testing efforts worth 4500 USD would get reduced and the possibility being 30%, what would be the EMV?
SELECT THE CORRECT ANSWER

-200

1350

1150

1550

A

Correct Option:C

EXPLANATION

The correct answer is $1150. In the case of the rework effort, the EMV is -$200. The EMV of the side effect is $1350. So, the total EMV is $1150.

58
Q

138Which of the following is NOT part of a quality plan?
SELECT THE CORRECT ANSWER

Benchmarking

Cost of Quality

Mind mapping

Quality audits

A

Correct Option:D

EXPLANATION

Quality audits are part of the Manage Quality process.

59
Q

139As a senior member in the executive management team, you have asked project managers within your team to provide cost estimates for a huge project. You foresee the cost estimate of the project to run into millions of dollars. Along with the cost estimate, you are also expecting the Basis of Estimates. What would you expect to be included in the documentation for Basis of Estimates?
SELECT THE CORRECT ANSWER

Basis of estimate, assumptions, known constraints, range of estimate, confidence level

Cost at unit level and confidence level

WBS

None of the above

A

Correct Option:A

EXPLANATION

The correct answer is A, which states that all the necessary details that must be provided as the Basis of estimates.

60
Q

140Your team has just bagged a big software development project. Considering the complexity of the project, you decide to try and identify the possible risks. You get all relevant stakeholders together and conduct discussions. Together, you come up with a number of risks. However, based on your experience, you still feel that not all the risks have been identified. You decide to set aside some budget for the risks that you have not identified but are sure you will encounter. Where does this budget come from?
SELECT THE CORRECT ANSWER

Cost Management Plan

Cost Baseline

Contingency Reserves

Management Reserve

A

Correct Option:D

EXPLANATION

The type of risk here is an unknown risk. For known risks, risk responses can be proactively planned for. For the known risks, where we cannot plan proactively, we set aside a reserve called Contingency Reserves. For unknown risks, we set aside a Management Reserve. Cost management Plan deals with how you will manage costs on your project, and Cost baseline is the baselined cost expected to be expended on the project.

61
Q

143Which of the following statements is NOT true regarding WBS?
SELECT THE CORRECT ANSWER

Provides a graphical picture of the hierarchy of the project

Identifies all the work that needs to be performed

Helps estimate costs and schedule

Helps identify dependencies

A

Correct Option:D

EXPLANATION

WBS does not help identify dependencies.

62
Q

145You were handling a complex project involving a lot of challenges, but with good management and a motivated team, all deliverables have been completed successfully. What should you do next as a project manager?
SELECT THE CORRECT ANSWER

Perform Quality Control

Update lessons learned

Verify scope

Disband the team

A

Correct Option:B

EXPLANATION

The question is looking for details related to the closing process group. Scope verification is performed during the monitoring and controlling process group. This is also the case with Perform Quality Control. One of the most important things to do during project closure is to create the lessons learned prior to disbanding the team.

63
Q

147You have just created a schedule network diagram. You have come up with the estimates, defined the durations, and subsequently identified the Critical Path. You now decide to do a Forward Pass through the Schedule Network Diagram. What would you be calculating?
SELECT THE CORRECT ANSWER

The Early Start and Early Finish for each activity

The latest start and latest finish for each activity

The duration of the other paths

The duration of the critical path

A

Correct Option:A

EXPLANATION

Options C and D are incorrect as the Forward Pass is not used to calculate the duration. In fact, the critical path is calculated based on duration. Option B talks about Late Start and Late Finish, which are calculated using Backward Pass. Using Forward Pass, we calculate the Early Start and Early Finish of all the activities in the network diagram.

64
Q

148You are working on identifying risks in a project. You have done extensive brainstorming and discussions with your team. You have also looked up the Organizational process assets and have come up with an exhaustive list of risks. You feel fairly confident now that you know all the risks. You decide to prioritize the risks and only focus on the high-priority ones. A team member indicates that a large number of risks have very low priority. She suggests you simply ignore them. You disagree and decide to maintain a list of such low-priority risks. Where will you maintain these low-priority risks?
SELECT THE CORRECT ANSWER

Risk Register

Risk Management Plan

Watch List

Issue Log

A

Correct Option:C

EXPLANATION

The risks have been identified in the Risk register. Based on prioritization, risk priorities are also updated in the risk register. All risks that are deemed low on priority are maintained in the Watch List specifically. The Risk Management Plan and the Issue Log are not meant to note or log risks. So, the correct answer is Watch List.

65
Q

150A software development project has been awarded a vendor. Your company and the vendor have agreed to build this project using the Waterfall Methodology. The vendor informs you that the actual development can only start after the completion of design. Which type of relationship best describes the dependency between design and actual development?
SELECT THE CORRECT ANSWER

Finish-to-Finish

Finish-to-Start

Start-to-Start

Start-to-Finish

A

Correct Option:B

EXPLANATION

Finish-to-Start means that the Successor Activity cannot start without the Predecessor activity being completed. In this case, the Design is the Predecessor activity and Development is the Successor Activity. So, Development (Successor Activity) cannot start without completion of Design (Predecessor Activity).

66
Q

158You are managing a project that is responsible for setting up an alcohol distillery. Your team is in its eighth month of execution. One of the vendors informs you that the delivery of agitators is going to be delayed by a week. You look up the project management plan and the schedule baselines and decide to set up all the reactors first. By moving tasks around based on your analysis, you see that there would be no impact on any of the performance measurement baselines. What should you do next?
SELECT THE CORRECT ANSWER

Go ahead and execute the rescheduled tasks as there is no impact on any of the baselines

Write up a change request and submit it to change control for approval

Analyze the impact of the change on the triple constraints and then submit a change request

Do nothing as this would cause changes to the baselines

A

Correct Option:A

EXPLANATION

In this case, the change is not going to impact any of the baselines. The project manager has the authority to make changes to the project if there is no impact on the baselines. This is one condition where changes can be made without undergoing change control, but note that this is done after ensuring that there is no impact on the baselines.

67
Q

159Which of the following statements is true regarding Control Account?
SELECT THE CORRECT ANSWER

Used as a Tool and Technique in Activity Definition process

Used to estimate cost at a level lower than the work package

Used to control costs of the project

Used in Integrated Change Control

A

Correct Option:A

EXPLANATION

Control Accounts are used to provide a cost estimate at a level higher than the work package. They are used as a technique in activity definition process. They are not used to control costs of the project or in Integrated change control.

68
Q

160Given a project which reports a CPI less than 1, you have asked one of your managers to generate the TCPI. Which formula should the project manager use in this case?
SELECT THE CORRECT ANSWER

( BAC - EV ) / ( BAC - AC )

( BAC - EV ) / ( EAC - AC )

EV / AC

EV / PV

A

Correct Option:B

EXPLANATION

( BAC - EV ) / ( BAC - AC ) -when the project is within budget. In
this case, the CPI value is less than 1,
so the project is not within budget.
( BAC - EV ) / ( EAC - AC )- when the project is over budget
EV / AC - not TCPI formulas. They are the CPI and SPI calculations
EV / PV - not TCPI formulas. They are the CPI and SPI calculations

The correct answer is Option B. Option A is to be used when the project is within budget. In this case, the CPI value is less than 1, so the project is not within budget. Option B is to be used when the project is over budget, which is the case here. So, it is the correct formula to use. Options C and D are not TCPI formulas. They are the CPI and SPI calculations and thus are not the correct choice.

69
Q

163Which hierarchical chart shows all the tasks in a list?
SELECT THE CORRECT ANSWER

RBS

OBS

WBS

Scope statement

A

Correct Option:C

EXPLANATION

Work Breakdown Structure shows all the tasks.

70
Q

164Which of the following is NOT part of the Control Quality process?
SELECT THE CORRECT ANSWER

Fishbone Diagram

Quality Audits

Checksheet

Histogram

A

Correct Option:B

EXPLANATION

Quality audits are part of the Perform Quality Assurance process.

71
Q

174You are managing a project that is scheduled to run for an entire year. Things were looking good after the first two months. However, due to some mistakes made by the construction crew at the end of the third month, you realize that the expected work to be completed at this stage is not complete. As a result, the project is behind schedule and is also over budget. However, there are stiff penalties in the contract if the project is not complete within the stipulated timelines. As a result, your senior management has committed to additional staff to the project if required. What would be the Estimate at Completion for this project?
SELECT THE CORRECT ANSWER

EAC = BAC/CPI

EAC = AC + BAC - EV

EAC = AC + (BAC - EV/(CPI * SPI )

EAC = AC + Bottom-up Estimate

A

Correct Option:C

EXPLANATION

Option A is to be used if past CPI is expected to continue. Option B is to be used if future work is going to be performed at the planned rate. Option D is to be used when the initial plan is no longer valid. Option C is to be used if deadlines must be met, and both CPI and SPI influence remaining work. Here, the project must be completed within stipulated timelines.

72
Q

178A project is reporting a negative Cost Variance. What does this mean?
SELECT THE CORRECT ANSWER

The project is under Budget.

The project is over Budget.

The project is running as per Budget.

None of the above

A

Correct Option:B

EXPLANATION

CV = (EV - AC). So, if the Cost Variance is in the negative, the Actual Cost is greater than the earned value, which means the project is running over budget.

73
Q

179Which of the following is NOT a Risk Identification tool or technique?
SELECT THE CORRECT ANSWER

Risk Register

Documentation analysis

Brainstorming

Interviewing

A

Correct Option:A

EXPLANATION

Documentation reviews help identify risks based on the plans and assumptions, so this is a Risk Identification tool. Brainstorming deals with getting together various stakeholders and identifying potential risks. Interviewing experienced project participants, stakeholders, and subject matter experts is also a great way of identifying risks. Risk Register is not a tool; it is the document in which identified risks are documented. The Risk Register is not a Risk Identification tool.

74
Q

180As a project manager of a large product, you and your team have shipped the deliverables to your customer. However, the customer has reported a number of serious issues in the quality of deliverables. As a result of this, the cost of quality of your project is deemed high. In the above scenario, which of the following would have decreased the cost of quality?
SELECT THE CORRECT ANSWER

Less Rework

Higher productivity

Lower costs

Stakeholder satisfaction

A

Correct Option:D

EXPLANATION

Options A, B, and C are benefits of meeting Quality Requirements. The question is about the reason for increase in cost of Quality. Generally, when stakeholders are not satisfied with the deliverables, there is rework involved. This increases the cost of quality. Hence, option D is correct.