PMP TEST 3.1 Flashcards
9Key members of a project are in the process of defining and assigning individual and team responsibilities. Which of the following is most critical for this team while the project management method is still not finalized?
SELECT THE CORRECT ANSWER
Understanding the location and time zone of team members
Knowing the attitudes of team members
Having open communication and effective collaboration
Skill and experience of team members
Correct Option:C
EXPLANATION
Project responsibilities within a team Open communications and effective collaboration are critical regardless of the specific project management method chosen
12An important feature in Agile is to maintain a prioritized list of backlog. Which of the following is NOT a prioritization technique?
SELECT THE CORRECT ANSWER
Monte Carlo simulation
Kano model
MoSCoW analysis
100 Points Method
Correct Option:A
EXPLANATION
Monte Carlo simulation is a technique used to understand the impact of risk and uncertainty in prediction and forecasting models.
14Estimations are fundamental in every project. Which of the following is used as an estimate in Agile projects?
SELECT THE CORRECT ANSWER
Absolute time estimate
Relative measures
Three point estimate
Hours of effort
Correct Option:B
EXPLANATION
Story Point estimating uses relative measures, which can be helpful as an integrated assessment to provide time estimates.
15Teams in Agile approach take accountability to ensure that all the work required for an iteration is delivered. Which of the following statements is not true?
SELECT THE CORRECT ANSWER
Agile teams are self-organized.
Task accountability need not be tracked.
Team members pull work for an iteration.
User stories are decomposed into required tasks.
Correct Option:B
EXPLANATION
Accountability of tasks should be tracked in an Agile approach.
17The Project Manager of a team observes that the project team is spending too much time during standups though this is meant to be a 15-minute ceremony every day. What could be the possible cause of this?
SELECT THE CORRECT ANSWER
Team members might not be sticking to the agenda
The team might be trying to find solutions to problems that were brought up.
Team might not be making effective use of parking lot to discuss issues post the standup meeting
All of the above
Correct Option:D
EXPLANATION
Standup meetings should be focusing on the following 3 questions for every team member and are typically timeboxed for 15 minutes: What did you do yesterday? What will you do today? Are there any impediments?
18It is important to have a clear vision for every project. Sam states that Vision is about bridging the gap between where we are and where we want to be. John mentions that Vision is about satisfying customer needs based on the requirements provided. Vinod says that Vision is only meant for the organization as a whole and not required for a project. Joe states that Vision is a desired end state. Who among them is correct about Vision?
SELECT THE CORRECT ANSWER
Sam and John
Vinod and Joe
Joe
Vinod
Correct Option:C
EXPLANATION
Vision is a desired end-state and it is critical to have a clear vision of the desired end objectives for a new project.
20Agile has certain ceremonies like daily standup, sprint review, and sprint retrospective. Which of the following is not true about the ceremonies?
SELECT THE CORRECT ANSWER
Daily standups are status meetings.
Sprint planning is a collaborative event for planning the project release.
Both A and B are wrong
Both A and B are correct
Correct Option:C
EXPLANATION
Sprint planning plans the work for the current sprint, not an entire project. Daily standups are not status meetings. The are required for a team to reaffirm commitment to its objectives, coordinate work among team members, and surface potential blockers.
25Which is of the following techniques puts customers/stakeholders in the position of a marketer of the product?
SELECT THE CORRECT ANSWER
XP Metaphor
Product box exercise
Planning poker
None of the above
Correct Option:B
EXPLANATION
Product Box Exercise gets stakeholders to describe aspects of a solution in the same way a marketer might describe product features and benefits. It helps team understand the most critical value aspects of the solution.
27A senior member from the portfolio team of your organization has requested you to prepare a document to validate the benefits of a component since they do not have enough information. Which document would you prepare in this case?
SELECT THE CORRECT ANSWER
Project implementation plan
Business needs document
Charter
Business Case
Correct Option:D
EXPLANATION
Business case is a documented economic feasibility study used to establish the validity of the benefits of a selected component when there is a lack of sufficient information.
28Agile Practice Guide categorizes project life cycle into 2 major types:
SELECT THE CORRECT ANSWER
Agile and Predictive
Predictive and Adaptive
Predictive and Incremental
Incremental and Iterative
Correct Option:B
EXPLANATION
Two major types of project life cycle as per Agile Practice Guide are predictive and adaptive.
31Which technique allows a large number of ideas to be classified into groups for analysis?
SELECT THE CORRECT ANSWER
Mind mapping
Affinity diagram
Plurality
Benchmarking
Correct Option:B
EXPLANATION
Affinity diagram is a technique that allows large numbers of ideas to be classified into groups for review and analysis.
32A project manager requests his subject matter experts to build visuals to represent the project outcome with an intent to illustrate the functioning of a product. Which of the following is the project manager expecting from the SMEs?
SELECT THE CORRECT ANSWER
Work breakdown structure
Storyboarding
Join application design
Quality function deployment
Correct Option:B
EXPLANATION
Storyboarding is a prototyping method that can use visuals or images to illustrate a process or represent a project outcome.
33Planning packages in WBS are:
SELECT THE CORRECT ANSWER
Activities meant for creating a plan
Components of known content without detailed schedule activities
Components in WBS with detailed steps to achieve a deliverable
All of the above
Correct Option:B
EXPLANATION
Planning package is a WBS component below the control account with known work content but without detailed schedule activities
34Code of Accounts in WBS is used:
SELECT THE CORRECT ANSWER
As a management control point
As a tracking system by finance to verify costs
As a work package with dependencies
To identify components
Correct Option:D
EXPLANATION
A code of accounts is a numbering system used to uniquely identify each component of the WBS.
35Which of the following can a Scope Baseline include?
SELECT THE CORRECT ANSWER
Cost baseline
Benefits plan
Planning package
Business case
Correct Option:C
EXPLANATION
A scope baseline may include any of the following components: Project scope statement, WBS, Work package, Planning package, WBS dictionary
38A typical user story contains:
SELECT THE CORRECT ANSWER
Risks
Constraints
Assumptions
Value
Correct Option:D
EXPLANATION
User stories describe the value/objective.
39Which of the following is NOT a tool/technique for verifying scope?
SELECT THE CORRECT ANSWER
Definition of Done
Definition of Ready
Acceptance Criteria
Team review comments
Correct Option:D
EXPLANATION
DOD, DOR, and Acceptance criteria are tools and techniques for verifying the scope.
40A project manager is reviewing a checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use. What is the checklist called?
SELECT THE CORRECT ANSWER
Definition of Ready
Validation of Scope
Definition of Done
Acceptance Criteria
Correct Option:C
EXPLANATION
Definition of Done is a team’s checklist of all the criteria required to be met so that a deliverable can be considered ready for customer use.
43A charter for a simple project without much dependency is approved, and the team is working on Iterative scheduling. Which of the following is NOT true about Iterative scheduling?
SELECT THE CORRECT ANSWER
The method uses progressive elaboration
Iterative scheduling works best for complex projects with dependency
Stories that provide the highest value are prioritized
Stories are prioritized based on how long they take
Correct Option:B
EXPLANATION
Iterative scheduling with a backlog does not work well with activities that have complex dependency relationships.
45When do we use Agile methodologies in a project?
SELECT THE CORRECT ANSWER
During Initiation and Conclusion
During Execution
During Monitoring and Control
All of the above
Correct Option:D
EXPLANATION
Agile is a framework used across the lifecycle of the project.
47An Agile team is preparing for its retrospective. Which of the following is NOT correct about retrospectives?
SELECT THE CORRECT ANSWER
A retrospective is a review of what went well
A retrospective is a review of what could have been done better
A retrospective assesses team collaboration.
The product owner is not included as this is for the agile team
Correct Option:D
EXPLANATION
A retrospective meeting consists of the agile team, product owner, and key stakeholders
49Minimum business increment best works for:
SELECT THE CORRECT ANSWER
A new product ideation
Creating MVP for a new product release
Products that are live and in-use
None of the above
Correct Option:C
EXPLANATION
Minimum Business Increment works best when the product and functions are understood or for improving products that are live and in-use.
51Diversity is an important element to implement effective leadership. One should be aware that the working style of individuals varies based on:
SELECT THE CORRECT ANSWER
Experience
Job role
Age
All of the above
Correct Option:D
EXPLANATION
Motivations and working styles of individuals and groups vary greatly based on their experiences, age, culture, job roles, and many more influencers.
53Value stream mapping is used to:
SELECT THE CORRECT ANSWER
Develop earned value management
Develop expected monetary value
Analyze flow of information
Compute overall value of the project
Correct Option:C
EXPLANATION
Value stream mapping is used to document, analyze, and improve the flow of information or materials required to provide a product or service for a customer.
55Impediments and blockers can be identified at various stages by the team. Which of the following is NOT true about impediments?
SELECT THE CORRECT ANSWER
Can be uncovered during daily standups.
Can be represented using sticky notes on a whiteboard
Can be tracked using sophisticated software
Cannot be a result of project risks
Correct Option:D
EXPLANATION
Impediments may be due to or as a result of project risks or issues.
57Personality profile assessment can help assess and present the personality profile of each individual, which suggests ways to work with them. Which of the following is not a personality style assessment for individuals?
SELECT THE CORRECT ANSWER
DiSC model
Theory of Psychological types
Tuckman’s model
True colors methodology
Correct Option:C
EXPLANATION
Tuckman’s model articulates team formation cycle and is not about individual styles
60Project risks are captured, tracked, and managed using a risk register. Which of the following is true in relation to compliance with legal and regulatory requirements?
SELECT THE CORRECT ANSWER
Risks related to compliance should include risk owner and impact.
Compliance validation must be assured as the project deliverables are created.
Risks are meant for the project team and are not related to compliance.
Both A and B
Correct Option:D
EXPLANATION
Identified risk, owner, impact and risk responses should be tracked to establish compliance with legal and regulatory requirements. It is also necessary to assure compliance validation as the deliverables are created.
64Which of the following is NOT a non-functional requirement?
SELECT THE CORRECT ANSWER
Security of confidential information during transaction
Capacity of enough supply to meet demand
Product feature to enable online purchase
Both A and B
Correct Option:C
EXPLANATION
Non-functional requirements focus on usability and level of service warranty of the deliverables.
66Which of the following is done by QA?
SELECT THE CORRECT ANSWER
Review the deliverable so that it meets functional and nonfunctional requirements
Suggest potential improvements
Make recommendations to address any noncompliance
All of the above
Correct Option:D
EXPLANATION
As the project team produces deliverables, quality assurance (QA) will review the deliverable, verify that it meets functional and nonfunctional requirements, and often identify and suggest potential improvements. QA will validate whether the deliverables align with compliance requirements and provide feedback on any variances.
68Quality audits are used to verify compliance and are generally conducted by an external team. Audits are generally used to: (Choose all options that are correct)
SELECT THE CORRECT ANSWER(S)
Share good practices from other projects in the organisation or industry
Highlight contributions to lessons learned
Identify critical path
None of the above
Correct Option:A, B
EXPLANATION
Quality audits are used to verify compliance with organizational policies, processes, and procedures. They are generally used to identify good practices being used, share good practices from other projects, proactively offer improvements to improve productivity, and highlight contributions to lessons learned.
69Which of the following are components of Business value?
SELECT THE CORRECT ANSWER
Employee knowledge
Customer value
Channel partner value
All of the above
Correct Option:D
EXPLANATION
Shareholder value, customer value, channel partner value, and employee knowledge are all part of business value.
70A project management plan can contain many subsidiary plans. Which of the following is not correct about Benefits Management Plan?
SELECT THE CORRECT ANSWER
It describes how the benefits of a project will be derived.
It describes how the benefits are measured.
It is a subsidiary component of the project management plan.
It describes when the benefits will be realized, usually by project phase.
Correct Option:C
EXPLANATION
Benefits Management plan is a business document and is not a subsidiary component of the project management plan.
73PESTLE factors are:
SELECT THE CORRECT ANSWER
Techniques used to build project schedule
Used in aggregation of costs
Used to prioritize backlog items
Used to identify impact on business case
Correct Option:D
EXPLANATION
It is critical that project managers are aware of PESTLE factors that can impact their projects business case and be prepared to adapt accordingly.
75Which of the following is NOT true about continuous improvement?
SELECT THE CORRECT ANSWER
It is an ongoing effort.
You can make small incremental improvements.
It is a business strategy
It is not for large, breakthrough improvements
Correct Option:D
EXPLANATION
Continuous improvement is a business strategy that is developed at the organizational level for projects and can bring small, incremental or large, breakthrough improvements.
76TQM is an approach to improve business results. Which of the following is NOT true about TQM implementation by quality theorists?
SELECT THE CORRECT ANSWER
Juran trilogy breaks quality management into quality planning control and improvement.
Taguchi method emphasizes that quality should be designed into the product.
Deming cycle is focused on one-time fix for quality to meet customer needs.
Six sigma emphasizes responding to customer needs by systematically removing defects.
Correct Option:C
EXPLANATION
Deming cycle focuses on continuous process improvement in which quality must be continuously improved to meet customer needs.
77Which of the following is NOT true about continuous improvement approaches? (Select all that apply)
SELECT THE CORRECT ANSWER(S)
Small development cycles in Agile project management give teams opportunity for continuous improvements.
Kaizen believes in large breakthroughs as small incremental improvements are not efficient.
Agile teams frequently go through the complete development process.
Kaizen believes in research, as improvement ideas come from researchers rather than workers themselves
Correct Option:B, D
EXPLANATION
Kaizen features include: Improvements based on many small changes Ideas come from workers themselves, rather than from expense research, consultants, or equipment.