Study Cards - Chapter 6 Flashcards
The time management planning processes are…
- Define activities
- Sequence activities
- Estimate activity resources
- Estimate activity durations
Activities are…
- The foundation of providing estimates for budgets, scheduling, executing, and monitoring & controlling the project
The time management M&C process is…
- Control schedule
The define activities inputs are…
Output from Create WBS
- Scope baseline
EEFs
OPAs
The define activities processes are…
- Decomposition
- Rolling wave planning
- Templates
- Expert judgement
The define activities outputs are…
- Activity list (key)
- Activity attributes
- Milestone list
The sequence activities inputs are…
Outputs from Define Activities
- Activity list
- Activity attributes
- Milestone list
Outputs from Define Scope
- Project scope statement
OPAs
The sequence activities processes are…
- Precedence Diagraming Method (PDM)
- Dependency determination
- Applying leads and lags
- Schedule network templates
The sequence activities outputs are…
- Project schedule network diagrams
- Project documentation updates
A network diagram is useful for…
- Illuminates dependencies
- Assigns duration to each activity
- Graphically identifies the workflow
- Justifies time estimate for project
- Identifies critical path
The four relationships in the Precedence Diagramming method are…
- Finish to start
- Start to start
- Finish to finish
- Start to finish
Three types of network diagrams are…
- Precedence Diagramming Method (Activity on Node)
- Activity on Arrow
- GERT (looping)
Three types of network dependencies are…
- Mandatory dependency (must have)
- Discretionary dependency (nice to have)
- External dependency (third party)
A milestone list becomes part of…
- The project plan
- The project scope statement
- The WBS dictionary
Can be applied in the sequence activities process to affect timing…
- Leads (schedule compression)
- Lags (imposed delay)
The estimate activity resources inputs are…
Outputs from Define Activities
- Activity list
- Activity attributes
Outputs from Develop PM Plan (subsidiary plan)
- Resource calendars
EEFs and OPAs
The estimate activity resources processes are….
- Expert judgement
- Alternatives analysis
- Published estimating data
- Bottom-up estimating
- PM software
The estimate activity resources outputs are…
- Activity resource requirements (key)
- Resource breakdown structure
- project document updates
The estimate activity durations inputs are…
Outputs from Define Activities
- Activity list
- Activity attributes
Output from Estimate Activity Resources
- Activity resource requirements
Outputs from Develop PM plan (subsidiary plan)
- Resource calendars
Outputs from Define Scope
- Project scope statement
EEFs and OPAs
As the project manager, you are responsible for the following when estimating activity resources and activity durations…
- Obtaining historical information
- Creating your own estimates
- Forecasting your own estimates to completion
- Reviewing estimates
- Looking to shorten the project timeline
- Basing estimates on the WBS
- Ensuring that SMEs are delivering the estimates
- Managing to the schedule baseline
- Knowing when to implement a change
- Create most accurate estimate possible
- Meeting agreed estimates
Analogous Estimating
- Project ‘A’ is like 3 previous projects
- Quick and low cost
- Very ‘rangy’
- A form of expert judgement