Glossary - T-Z Flashcards

1
Q

Validation

A

The assurance that a product, service, or system meets the needs of the customer and other identified stakeholders. It often involves acceptance and suitability with external customers. Contrast with verification.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Value Engineering

A

An approach used to optimize project life cycle costs, save time, increase profits, improve quality, expand market share, solve problems, and/or use resources more effectively.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Variance

A

A quantifiable deviation, departure, or divergence away from a known baseline or expected value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Variance Analysis

A

A method for resolving the total variance in the set of scope, cost, and schedule variables into specific component variances that are associated with defined factors affecting the scope, cost, and schedule variables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Verification

A

The evaluation of whether or not a product, service, or system complies with a regulation, requirement, specification, or imposed condition. It is often an internal process. Contrast with validation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Verify Scope

A

The process of formalizing acceptance of the completed project deliverables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Virtual Team

A

A group of persons with a shared objective who fulfill their roles with little or no time spent meeting face to face. Various forms of technology are often used to facilitate communication among team members. Virtual teams can be comprised of persons separated by great distances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Voice of the Customer

A

A planning technique used to provide products, services, and results that truly reflect customer requirements by translating those customer requirements into the appropriate technical requirements for each phase of project product development.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Work Authorization

A

A permission and direction, typically written, to begin work on a specific schedule activity or work package or control account. It is a method for sanctioning project work to ensure that the work is done by the identified organization, at the right time, and in the proper sequence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Work Authorization System

A

A subsystem of the overall project management system. It is a collection of formal documented procedures that defines how project work will be authorized (committed) to ensure that the work is done by the identified organization, at the right time, and in the proper sequence. It includes the steps, documents, tracking system, and defined approval levels needed to issue work authorizations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Work Breakdown Structure (WBS)

A

A deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables. It organizes and defines the total scope of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Work Breakdown Structure Component

A

An entry in the work breakdown structure that can be at any level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Work Breakdown Structure Dictionary

A

A document that describes each component in the work breakdown structure (WBS). For each WBS component, the WBS dictionary includes a brief definition of the scope or statement of work, defined deliverable(s), a list of associated activities, and a list of milestones. Other information may include: responsible organization, start and end dates, resources required, an estimate of cost, charge number, contract information, quality requirements, and technical references to facilitate performance of the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Work Package

A

A deliverable or project work component at the lowest level of each branch of the work breakdown structure. See also control account.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Work Performance Information

A

Information and data, on the status of the project schedule activities being performed to accomplish the project work, collected as part of the direct and manage project execution processes. Information includes: status of deliverables; implementation status for change requests, corrective actions, preventive actions, and defect repairs; forecasted estimates to complete; reported percent of work physically completed; achieved value of technical performance measures; start and finish dates of schedule activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Workaround

A

A response to a negative risk that has occurred. Distinguished from contingency plan in that a workaround is not planned in advance of the occurrence of the risk event.

17
Q

Team Members

A

See project team members.

18
Q

Technical Performance Measurement

A

A performance measurement technique that compares technical accomplishments during project execution to the project management plan’s schedule of planned technical achievements. It may use key technical parameters of the product produced by the project as a quality metric. The achieved metric values are part of the work performance information.

19
Q

Technique

A

A defined systematic procedure employed by a human resource to perform an activity to produce a product or result or deliver a service, and that may employ one or more tools.

20
Q

Template

A

A partially complete document in a predefined format that provides a defined structure for collecting, organizing, and presenting information and data.

21
Q

Threat

A

A condition or situation unfavorable to the project, a negative set of circumstances, a negative set of events, a risk that will have a negative impact on a project objective if it occurs, or a possibility for negative changes. Contrast with opportunity.

22
Q

Three-Point Estimate

A

An analytical technique that uses three cost or duration estimates to representthe optimistic, most likely, and pessimistic scenarios. This technique is applied to improve the accuracy of the estimates of cost or duration when the underlying activity or cost component is uncertain.

23
Q

Threshold

A

A cost, time, quality, technical, or resource value used as a parameter, and which may be included in product specifications. Crossing the threshold should trigger some action, such as generating an exception report.

24
Q

Time and Material (T&M) Contract

A

A type of contract that is a hybrid contractual arrangement containing aspects of both cost-reimbursable and fixed-price contracts. Time and material contracts resemble costreimbursable type arrangements in that they have no definitive end, because the full value of the arrangement is not defined at the time of the award. Thus, time and material contracts can grow in contract value as if they were cost-reimbursable-type arrangements. Conversely, time and material arrangements can also resemble fixed-price arrangements. For example, the unit rates are preset by the buyer and seller, when both parties agree on the rates for the category of senior engineers.

25
Q

Time-Scaled Schedule Network Diagram

A

Any project schedule network diagram drawn in such a way that the positioning and length of the schedule activity represents its duration. Essentially, it is a bar chart that includes schedule network logic.

26
Q

To-Complete-Performance-Index (TCPI)

A

The calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal, such as the budget at completion (BAC) or the estimate at completion (EAC). It is the ratio of “remaining work” to the “funds remaining.”

27
Q

Tool

A

Something tangible, such as a template or software program, used in performing an activity to produce a product or result.

28
Q

Total Float

A

The total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating a schedule constraint. Calculated using the critical path method technique and determining the difference between the early finish dates and late finish dates. See also free float.

29
Q

Trend Analysis

A

An analytical technique that uses mathematical models to forecast future outcomes based on historical results. It is a method of determining the variance from a baseline of a budget, cost, schedule, or scope parameter by using prior progress reporting periods’ data and projecting how much that parameter’s variance from baseline might be at some future point in the project if no changes are made in executing the project.