Glossary - A-C Flashcards
Acceptance Criteria
Those criteria, including performance requirements and essential conditions, which must be met before project deliverables are accepted.
Acquire Project Team
. The process of confirming human resource availability and obtaining the team necessary to complete project assignments.
Activity
A component of work performed during the course of a project.
Activity Attributes
. Multiple attributes associated with each schedule activity that can be included within the activity list. Includes activity codes, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
Activity Code
One or more numerical or text values that identify characteristics of the work or in some way categorize the schedule activity that allows filtering and ordering of activities within reports.
Activity Duration
The time in calendar units between the start and finish of a schedule activity. See also Duration.
Activity Identifier
A short unique numeric or text identification assigned to each schedule activity to differentiate that project activity from other activities. Typically unique within any one project schedule network diagram.
Activity List
. A documented tabulation of schedule activities that shows the activity description, activity identifier, and a sufficiently detailed scope of work description so project team members understand what work is to be performed.
Actual Cost / Actual Cost of Work Performed
(AC / ACWP). Total costs actually incurred and recorded in accomplishing work performed during a given time period for a schedule activity or work breakdown structure component. It can be direct labor hours alone, direct costs alone, or all costs including indirect costs. See also earned value management and earned value technique.
Actual Duration
The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish date if the schedule activity is complete.
Administer Procurements
. The process of managing procurement relationships, monitoring contract performance, and making changes and corrections as needed.
Analogous Estimating
. An estimating technique that uses the values of parameters, such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar activity as the basis for estimating the same parameter or measure for a future activity.
Application Area
A category of projects that have common components significant in such projects, but are not needed or present in all projects. They are usually defined in terms of either the product (ie: by similar technologies or production methods), the type of customer (ie: internal vs external, gov’t vs commercial), or the industry sector (ie: utilities, auto, aero, IT, etc). Application areas can overlap.
Approved Change Request
. A change request that has been processed through the integrated change control process and approved.
Assumption
A factor that, for planning purposes, is considered to be true, real, or certain without proof or demonstration.
Assumptions Analysis
. A technique that explores the accuracy of assumptions and identifies risks to the project from inaccuracy, inconsistency, or incompleteness of assumptions.
Authority
The right to apply project resources, expend funds, make decisions, or give approvals.
Control
Comparing actual performance with planned performance, analyzing variances, assessing trends to effect process improvements, evaluating possible alternatives, and recommending appropriate corrective action as needed.
Control Account
. A management control point where scope, budget (resource plans), actual cost, and schedule are integrated and compared to earned value for performance measurement. See also work package.
Control Chart
. A graphic display of process data over time and against established control limits, and that has a centerline that assists in detecting a trend of plotted values toward either control limit.
Control Costs
. The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline.
Control Limits
The area composed of three standard deviations on either side of the centerline, or mean, of a normal distribution of data plotted on a control chart that reflects the expected variation in the data. See also specification limits.
Control Schedule
. The process of monitoring the status of the project to update project progress and managing changes to the schedule baseline.
Control Scope
. The process of monitoring the status of the project and product scope and managing changes to the scope baseline.
Controlling
See control.
Corrective Action
Documented direction for executing the project work to bring expected future performance of the project work in line with the project management plan.
Cost Management Plan
. The document that sets out the format and establishes the activities and criteria for planning, structuring, and controlling the project costs. The cost management plan is contained in, or is a subsidiary plan of, the project management plan.
Cost of Quality (COQ)
. A method of determining the costs incurred to ensure quality. Prevention and appraisal costs (cost of conformance) include costs for quality planning, quality control (QC), and quality assurance to ensure compliance to requirements (i.e., training, QC systems, etc.). Failure costs (cost of nonconformance) include costs to rework products, components, or processes that are non-compliant, costs of warranty work and waste, and loss of reputation.
Cost Performance Baseline
A specific version of the time-phased budget used to compare actual expenditures to planned expenditures to determine if preventive or corrective action is needed to meet the project objectives.