Glossary - D-I Flashcards
Gantt Chart
A graphic display of schedule-related information. In the typical bar chart, schedule activities or work breakdown structure components are listed down the left side of the chart, dates are shown across the top, and activity durations are shown as date-placed horizontal bars.
Grade
A category or rank used to distinguish items that have the same functional use (e.g., “hammer”), but do not share the same requirements for quality (e.g., different hammers may need to withstand different amounts of force).
Hammock Activity
See summary activity.
Historical Information
Documents and data on prior projects including project files, records, correspondence, closed contracts, and closed projects.
Human Resource Plan
A document describing how roles and responsibilities, reporting relationships, and staffing management will be addressed and structured for the project. It is contained in or is a subsidiary plan of the project management plan.
Identify Risks
The process of determining which risks may affect the project and documenting their characteristics.
Identify Stakeholders
The process of identifying all people or organizations impacted by the project, and documenting relevant information regarding their interests, involvement, and impact on project success.
Imposed Date
A fixed date imposed on a schedule activity or schedule milestone, usually in the form of a “start no earlier than” and “finish no later than” date.
Influence Diagram
A graphical representation of situations showing causal influences, time ordering of events, and other relationships among variables and outcomes.
Initiating Processes
Those processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase.
Input
Any item, whether internal or external to the project that is required by a process before that process proceeds. May be an output from a predecessor process.
Inspection
Examining or measuring to verify whether an activity, component, product, result, or service conforms to specified requirements.
Invitation for Bid (IFB)
Generally, this term is equivalent to request for proposal. However, in some application areas, it may have a narrower or more specific meaning.
Issue
A point or matter in question or in dispute, or a point or matter that is not settled and is under discussion or over which there are opposing views or disagreements.
Failure Mode and Effect Analysis (FMEA)
An analytical procedure in which each potential failure mode in every component of a product is analyzed to determine its effect on the reliability of that component and, by itself or in combination with other possible failure modes, on the reliability of the product or system and on the required function of the component; or the examination of a product (at the system and/or lower levels) for all ways that a failure may occur. For each potential failure, an estimate is made of its effect on the total system and of its impact. In addition, a review is undertaken of the action planned to minimize the probability of failure and to minimize its effects.
Fast Tracking
A specific project schedule compression technique that changes network logic to overlap phases that would normally be done in sequence, such as the design phase and construction phase, or to perform schedule activities in parallel. See also crashing and schedule compression.
Finish Date
A point in time associated with a schedule activity’s completion. Usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, baseline, target, or current.
Finish-to-Finish (FF)
The logical relationship where completion of work of the successor activity cannot finish until the completion of work of the predecessor activity. See also logical relationship.
Finish-to-Start (FS)
The logical relationship where initiation of work of the successor activity depends upon the completion of work of the predecessor activity. See also logical relationship.
Firm-Fixed-Price (FFP) Contract
A type of fixed price contract where the buyer pays the seller a set amount (as defined by the contract), regardless of the seller’s costs.
Fixed-Price-Incentive-Fee (FPIF) Contract
A type of contract where the buyer pays the seller a set amount (as defined by the contract), and the seller can earn an additional amount if the seller meets defined performance criteria.
Float
Also called slack. See total float and free float.
Flowcharting
The depiction in a diagram format of the inputs, process actions, and outputs of one or more processes within a system.
Forecast
An estimate or prediction of conditions and events in the project’s future based on information and knowledge available at the time of the forecast. The information is based on the project’s past performance and expected future performance, and includes information that could impact the project inthe future, such as estimate at completion and estimate to complete.
Forward Pass
The calculation of the early start and early finish dates for the uncompleted portions of all network activities. See also schedule network analysis and backward pass.