Knowledge Checks - Chapter 6 Flashcards
The four possible precedence relationships in an AON network diagram are: __ - __ - __, __ - __ - __, __ - __ - __ and __ - __ - __
start to finish, start to start, finish to finish, finish to start
The diagramming method that allows for conditional looping is called __
GERT
The three types of network dependencies are known as: __, __ and __
mandatory, discretionary, external
The completion of a key deliverable or a phase in the project is called a __
milestone
Starting a successor activity before the predecessor is complete is called a __, while a delay in starting a successor activity is defined as a __
lead, lag
The five processes in the Planning process group for Time Management are: __ __, __ __, __ __ __, __ __ __, __ __
define activities, sequence activities, estimate activity resources, estimate activity duration, develop schedule
Another name for the three point estimate is called __
PERT
The most accurate and time consuming of the estimates is called __ estimating
bottom-up
The sigma percentages are 1 Sigma = __ %,2 Sigma = __ %and 3 Sigma __ %
68.26%, 95.46%, 99.73%
The time an activity can be delayed without delaying the project end date is called __ __
total float
The earliest you can begin an activity is called the __ __, while the latest time in the network schedule that an activity can begin without impacting the late finish (LF) is called the __
early start, late start
Conformance to target values is defined as __, while the precision of the measurement is expressed as __ __
accuracy, standard deviation
The __ __ in a network diagram is the longest path through the network that produces the shortest possible completion time for the project
critical path
The time a project can be delayed without delaying the start of a successor project is called __ __
project float
The two primary schedule compression techniques are called __ and __ __
crashing, fast tracking