Knowledge Checks - Chapter 7 Flashcards

1
Q

The estimate that takes little time to create, but is not very accurate, is known as an __ estimate

A

top down

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The rough order of magnitude estimate ranges from __ % to __ %

A

-50%, 50%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The key output of the Estimate Costs process is __ __ __

A

activity cost estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A __ __ __ is a detailed analysis on how the cost estimate was derived

A

basis of estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The tool that addresses the variance between the funding limit and the planned expenditures for the project is called the __ __ __

A

funding limit reconciliation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The two types of monetary reserves on a project are identified as __ reserve and __ reserve

A

contingency, management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The main output of the Control Costs process is __

A

budget forecast

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The cost baseline includes the __ __ whereas the cost (total) budget includes the __ and the __ __

A

contingency reserve, contingency, management reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What the work of the project is supposed to have cost by a specific point in the schedule is called the __ __, whereas the total amount that the work should cost for the entire project is called the __ __ __

A

planned value, budget at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The formula for CPI = __ / __

A

EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The formula for SPI = __ / __

A

EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A new budget forecast is created to address variances in the project and replaces the BAC. This new forecast is called the __ __ __

A

Estimate to complete (ETC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The amount of money that remains to be spent on a project that is 1/3 complete is called the __ __ __

A

Estimate to completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The formula for TCPI = __ - __ / __ - __

A

BAC-EV / BAC-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The formula for variance at completion (VAC) = __ - __

A

BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly