Knowledge Checks - Chapter 7 Flashcards
The estimate that takes little time to create, but is not very accurate, is known as an __ estimate
top down
The rough order of magnitude estimate ranges from __ % to __ %
-50%, 50%
The key output of the Estimate Costs process is __ __ __
activity cost estimate
A __ __ __ is a detailed analysis on how the cost estimate was derived
basis of estimate
The tool that addresses the variance between the funding limit and the planned expenditures for the project is called the __ __ __
funding limit reconciliation
The two types of monetary reserves on a project are identified as __ reserve and __ reserve
contingency, management
The main output of the Control Costs process is __
budget forecast
The cost baseline includes the __ __ whereas the cost (total) budget includes the __ and the __ __
contingency reserve, contingency, management reserves
What the work of the project is supposed to have cost by a specific point in the schedule is called the __ __, whereas the total amount that the work should cost for the entire project is called the __ __ __
planned value, budget at completion
The formula for CPI = __ / __
EV / AC
The formula for SPI = __ / __
EV / PV
A new budget forecast is created to address variances in the project and replaces the BAC. This new forecast is called the __ __ __
Estimate to complete (ETC)
The amount of money that remains to be spent on a project that is 1/3 complete is called the __ __ __
Estimate to completion
The formula for TCPI = __ - __ / __ - __
BAC-EV / BAC-AC
The formula for variance at completion (VAC) = __ - __
BAC - EAC