Starting up a project Flashcards

1
Q

What is the purpose of the “Project Initiation” process in PRINCE2?

A

To ensure that the prerequisites for initiating a project are in place, assessing whether the project is feasible and worth starting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What needs to be established before beginning to plan a PRINCE2 project?

A

To confirm that the necessary foundational information for rational decisions is defined and that key roles and responsibilities are allocated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the main objectives of the “Project Initiation” process?

A

To establish a business justification, necessary authority, scope definition, project approach selection, and initiation planning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why is the “Project Initiation” process essential?

A

To prevent wasting resources on projects based on shaky assumptions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What triggers the initiation of a project in PRINCE2?

A

The project mandate, provided by a sponsoring authority, such as corporate, program management, or the customer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What information does the project mandate contain?

A

It provides the project’s terms of reference and identifies at least the potential executive of the project board.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the purpose of the project brief in PRINCE2?

A

To provide the project board with sufficient information to decide whether to initiate the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How does the effort required in Project Initiation vary in PRINCE2?

A

It varies significantly from project to project; in program projects, much of the work is reduced as the program provides the project brief and appoints project board members.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What activity is crucial during Project Initiation?

A

Regular and frequent interaction between the project manager, project board members, and other stakeholders to clearly define requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is the outline business case developed during the Project Initiation process?

A

It is elaborated and refined in parallel with the project brief and then extended into the PID during the Project Initiation process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the first step in the PRINCE2 project initiation process?

A

Appointment of the executive and project manager, which is crucial for project decision-making and day-to-day management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the role of the executive in a PRINCE2 project?

A

They represent the business interests and ensure that the project is justified and aligned with the business needs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the role of the project manager in PRINCE2?

A

To manage the project day-to-day on behalf of the executive and ensure that the project progresses according to the plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who appoints the executive and project manager in PRINCE2?

A

The sponsoring organization, such as corporate, program management, or the customer, appoints the executive, while the executive appoints the project manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the Daily Log in PRINCE2?

A

It is a repository for project information that has not yet been captured elsewhere, used to record daily notes and decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why is it important to capture lessons from previous projects in PRINCE2?

A

Lessons learned from previous projects can influence the design of the management team, the preliminary business case, the project brief, and the phase plan for initiation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the first step in capturing lessons learned?

A

Create a lessons log to document experiences and insights gathered from similar previous projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who creates the lessons log and who reviews it?

A

The lessons log is created by the project manager and reviewed by the executive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How are lessons learned collected from previous projects?

A

Review related lessons from similar projects, including the results of project audits and reviews, and consult individuals with relevant experience.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How can lessons be effectively captured during project initiation?

A

Organize a workshop with stakeholders and those who have worked on similar projects to share and document lessons learned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What should be done when transitioning from an overview to a detailed view in the PRINCE2 process?

A

Repeat the lessons collection activity to include any relevant external lessons that may have emerged.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Why is the project management team structure important in PRINCE2?

A

It ensures that the right people are in the right roles with the authority, responsibility, and knowledge needed to make timely decisions, representing the interests of all involved parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What steps are involved in creating role descriptions within the project management team?

A

Prepare the team structure, create role descriptions for members of the project board and for project assurance, team manager, and project support positions.

22
Q

What is the process for selecting project management team members in PRINCE2?

A

The process includes estimating the time and effort required for each role, identifying suitable candidates, confirming their availability and understanding of the roles, and finally, officially assigning them to the identified roles.

23
Q

What aspect of role descriptions should be confirmed before appointing the project management team?

A

Reporting and communication lines should be confirmed within the role descriptions to ensure effective project management.

24
Q

What should be done if risks are identified during the design and appointment of the project management team?

A

Add any identified risks to the daily log for continuous monitoring and management.

25
Q

Why is it important to prepare an outline business case in the “Project Initiation” process?

A

It provides an agreed-upon foundation for a more detailed business case and helps maintain the focus on why the project is necessary, as well as what and how it will be delivered.

26
Q

What are the executive’s responsibilities in preparing the outline business case?

A

The executive, in consultation with the senior user, senior supplier, and project manager, drafts the outline business case based on the project mandate, considering the objectives, contribution to business objectives, and funding methods.

27
Q

What is the role of the project manager in creating the Project Product Description?

A

The project manager consults with the executive, senior user, and senior supplier to define what the project will deliver and creates the project product description, capturing quality expectations and acceptance criteria.

28
Q

How are risks managed in the outline business case?

A

Risks are captured in the daily log, and key risks that affect project feasibility are summarized in the outline business case.

29
Q

What happens after the outline business case is written?

A

If necessary, the outline business case is submitted for approval to the corporate, program management, or the client.

30
Q

Why is it crucial to define the project approach in PRINCE2?

A

It establishes how the project work will be carried out, influencing choices such as internal or external development, the use of commercial products or customized solutions, and the adoption of agile methods.

31
Q

What is the role of the project brief in the “Starting Up a Project” phase?

A

The project brief establishes a clear and shared starting point for the project, describing its purpose, objectives, and the anticipated approach.

32
Q

How are potential project delivery solutions evaluated?

A

By analyzing lessons from the past, considering corporate strategies and industry regulations, and assessing the suitability of various delivery options.

33
Q

Why is an agreed project brief crucial in PRINCE2?

A

It provides a common and well-defined basis of the project’s initiation, ensuring that all stakeholders have a shared understanding and allowing for the addition of further details and precision in the Project Initiation Document (PID) later on.

34
Q

Who is responsible for defining the project approach in PRINCE2?

A

The project manager is responsible for defining the project approach, while the executive and senior supplier provide critical review, with the executive having the role of approval (A) for the chosen direction.

35
Q

What role does the project manager play in the process of assembling the project brief?

A

The project manager assembles the project brief, ensuring it accurately reflects the project’s objectives and scope, with input and review from the executive and senior supplier.

36
Q

Who drafts the role descriptions for additional team members?

A

The project manager prepares the role descriptions for additional team members, ensuring that all responsibilities are clear and well-defined.

37
Q

What is the purpose of planning the initiation phase in a PRINCE2 project?

A

Ensure that the initiation phase is well-structured and not haphazard, establish appropriate management controls, and align the planning with any broader program plans.

38
Q

How are management controls decided during the initiation phase?

A

Based on the project approach, review lessons learned related to project controls, and define reporting and control agreements for the initiation phase.

39
Q

Who is responsible for creating the phase plan for the initiation phase?

A

The project manager creates the phase plan for the initiation phase, taking into account time and cost constraints and utilizing PRINCE2 planning principles and techniques.

40
Q

What is the final step in planning the initiation phase of a PRINCE2 project?

A

Requesting authorization to initiate the project, confirming that all preliminary stages have been completed, and the project is ready to proceed.

41
Q

Why is tailoring important in the “Starting Up a Project” process?

A

Tailoring ensures that activities adapt to the project context while maintaining the integrity of the interface with the “Directing a Project” process and adhering to the PRINCE2 principle of learning from experience.

42
Q

How can the lessons log be tailored in the project initiation process?

A

Capturing lessons learned should follow the PRINCE2 principle, but the formality of recording can vary depending on project needs.

43
Q

What elements make up the project brief in PRINCE2, and how can its structure vary?

A

The project brief includes the outline business case and the project product description. It can be a standalone document or reference corporate documents, programs, or client reports like feasibility studies. Its complexity can range from a simple statement to a more detailed description.

44
Q

How is the management team structure handled in the project brief during project initiation?

A

The management team structure may only be partially complete at this stage and should adhere to organizational constraints. Options and solutions may still be undefined, and the project approach should outline how these will be determined.

45
Q

How are role descriptions presented in the project brief?

A

Role descriptions can vary from summaries of existing formal documentation to customized descriptions tailored to the project’s needs.

46
Q

What is the scope of content in the outline business case within the project brief?

A

The outline business case can range from a simple statement of the project’s necessity to a more complex and detailed analysis and description.

47
Q

What does the project product description include when solution products have not yet been identified?

A

The project product description can include statements about desired outcomes related to solving business problems, outlining objectives without yet detailing solution products.

48
Q

What are the guidelines for tailoring the phase plan for the initiation phase?

A

The phase plan can include different components and formats tailored to the project’s complexity and may be fully or partially contained within planning tools.

49
Q

What happens if a project manager has not been appointed at the beginning of the project initiation process?

A

If the project manager has not been appointed, the required management products can be created by the executive or someone delegated by them. It is crucial to maintain a single point of responsibility for each role.

50
Q

How do you manage the initiation of a simple project in PRINCE2?

A

For simple projects with acceptable risks, the process can be less formal. However, the executive and project manager should not skip it entirely. The project brief may be an expansion of the mandate, with details about the business issue, roles, and a plan for the initial phase.

51
Q

What are the considerations for initiating projects with an agile approach?

A

It is crucial to assess the suitability of an agile approach, examining pros and cons, such as team co-location. It is important to consider the impact of frequent releases on aspects like quality management and product delivery method.

52
Q

How do you manage the initiation of a project from a supplier’s perspective?

A

From a supplier’s perspective, the process begins pre-contract, in response to a customer’s request for information or proposal. It is an important phase for establishing the project’s foundations.

53
Q

How do you initiate a project within a program?

A

Within a program, the initiation process can be primarily managed by the program manager. This includes appointing executives and project managers, preparing the project brief, and assembling an initial project management team.