Introduction to processes Flashcards
What is a process-based approach in PRINCE2?
A structured set of activities designed to achieve a specific objective by transforming defined inputs into defined outputs. PRINCE2 includes seven processes for successfully directing, managing, and delivering a project.
What are the seven processes in PRINCE2?
Starting up a Project, Initiating a Project, Directing a Project, Controlling a Stage, Managing Product Delivery, Managing Stage Boundaries, and Closing a Project.
What happens in the pre-project phase in PRINCE2?
Defining the project mandate, which can range from a verbal instruction to a well-formulated and justified project definition.
What is the role of the project board in PRINCE2?
Establishing direction and making key decisions throughout the project’s life, tasks covered by the Directing a Project process.
What does project initiation involve in PRINCE2?
Ensuring that the project is worthwhile and feasible, culminating in the production of a project brief and a stage plan for project initiation.
What happens in the initiation phase in PRINCE2?
The project is planned to an appropriate level of detail, funding is secured, project management approaches and controls are established, the business case is developed, and benefits review planning takes place.
What is the primary outcome of the initiation phase?
The production of PID (Project Initiation Documentation), which is reviewed by the project board to decide whether to authorize the project.
How are subsequent stages of the project managed in PRINCE2?
The project board delegates day-to-day control to the project manager, who assigns work, ensures that products meet specifications, and keeps performance forecasts within agreed tolerances.
What does the product delivery management process involve?
Team managers or team members carry out assigned work packages, deliver products, and update the project manager on progress through checkpoint reports.
What is the role of the project manager at the end of each management stage?
The project manager requests authorization to proceed to the next stage, providing updates on the business case and planning the next management stage in detail.
What are the main activities in closing a PRINCE2 project?
Confirming the adoption of project products, archiving documentation, assessing project performance against the original plan, and releasing resources.
What happens in post-project benefits reviews in PRINCE2?
Evaluating realized benefits after project closure, identifying unrealized benefits, and planning corrective actions.
What is the post-project phase in PRINCE2?
An evaluation phase to ensure that the project has contributed to the realization of benefits and to conduct benefits reviews.
What does the PRINCE2 process model represent?
The PRINCE2 process model describes how processes align with the management levels of corporate, program, or customer, and it includes project direction, management, and delivery.
How are PRINCE2 processes aligned with management levels?
PRINCE2 processes are aligned to ensure that the project is directed, managed, and delivered in accordance with the requirements of corporate, program, or customer.