Introduction to processes Flashcards

1
Q

What is a process-based approach in PRINCE2?

A

A structured set of activities designed to achieve a specific objective by transforming defined inputs into defined outputs. PRINCE2 includes seven processes for successfully directing, managing, and delivering a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the seven processes in PRINCE2?

A

Starting up a Project, Initiating a Project, Directing a Project, Controlling a Stage, Managing Product Delivery, Managing Stage Boundaries, and Closing a Project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What happens in the pre-project phase in PRINCE2?

A

Defining the project mandate, which can range from a verbal instruction to a well-formulated and justified project definition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the role of the project board in PRINCE2?

A

Establishing direction and making key decisions throughout the project’s life, tasks covered by the Directing a Project process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does project initiation involve in PRINCE2?

A

Ensuring that the project is worthwhile and feasible, culminating in the production of a project brief and a stage plan for project initiation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What happens in the initiation phase in PRINCE2?

A

The project is planned to an appropriate level of detail, funding is secured, project management approaches and controls are established, the business case is developed, and benefits review planning takes place.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the primary outcome of the initiation phase?

A

The production of PID (Project Initiation Documentation), which is reviewed by the project board to decide whether to authorize the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How are subsequent stages of the project managed in PRINCE2?

A

The project board delegates day-to-day control to the project manager, who assigns work, ensures that products meet specifications, and keeps performance forecasts within agreed tolerances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does the product delivery management process involve?

A

Team managers or team members carry out assigned work packages, deliver products, and update the project manager on progress through checkpoint reports.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the role of the project manager at the end of each management stage?

A

The project manager requests authorization to proceed to the next stage, providing updates on the business case and planning the next management stage in detail.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the main activities in closing a PRINCE2 project?

A

Confirming the adoption of project products, archiving documentation, assessing project performance against the original plan, and releasing resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What happens in post-project benefits reviews in PRINCE2?

A

Evaluating realized benefits after project closure, identifying unrealized benefits, and planning corrective actions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the post-project phase in PRINCE2?

A

An evaluation phase to ensure that the project has contributed to the realization of benefits and to conduct benefits reviews.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does the PRINCE2 process model represent?

A

The PRINCE2 process model describes how processes align with the management levels of corporate, program, or customer, and it includes project direction, management, and delivery.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How are PRINCE2 processes aligned with management levels?

A

PRINCE2 processes are aligned to ensure that the project is directed, managed, and delivered in accordance with the requirements of corporate, program, or customer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are triggers between PRINCE2 processes?

A

Triggers are events or decision points that indicate when a process should start or finish, facilitating the transition between various project processes.

16
Q

What is the relationship between processes, activities, and actions in PRINCE2?

A

Each process comprises various activities, and each activity comprises recommended actions, which together will guide the project’s success.

17
Q

Why is the “Purpose” important in a PRINCE2 process?

A

It defines the reason for the existence of the process and its importance to the project.

18
Q

What is the significance of the “Objectives” of a PRINCE2 process?

A

They specify what the process aims to achieve for the success of the project.

19
Q

What is meant by “Activities” in a PRINCE2 process?

A

They are tasks or actions that lead to specific outcomes, essential for the progress of the process.

20
Q

What does “Tailoring” mean in PRINCE2?

A

It involves adapting the standard PRINCE2 processes to conform to the specificities of the project at hand.

21
Q

Why are “Responsibilities” important in PRINCE2 processes?

A

They indicate who is responsible for producing, reviewing, and approving the process’s products, ensuring role clarity.

22
Q

What conditions must be met when tailoring a PRINCE2 process?

A

PRINCE2 principles must be upheld, and the purposes and objectives of the process must not be compromised.

22
Q

How does the project’s risk level impact the tailoring of processes in PRINCE2?

A

High-risk projects may require more detailed documentation, while low-risk ones may suffice with more informal processes.

23
Q

Which aspects of the PRINCE2 process can be tailored?

A

Roles and responsibilities within processes can be modified to better fit the project’s context.

24
Q

What is essential when documenting processes in PRINCE2?

A

Ensuring that the documentation is subject to change control to keep all users informed of the current version.