Closing a poject Flashcards
What is the purpose of the “Closing a Project” process in PRINCE2?
To confirm acceptance of the project’s product, verify the achievement of the original PID (Project Initiation Document) objectives or approved changes, and acknowledge that the project has completed its contribution.
What are the objectives of the “Closing a Project” process?
To verify user acceptance of the project’s products, ensure that the hosting site can support the products, review the project’s performance, assess benefits already realized and update the benefits management approach, and ensure the management of open issues and risks.
What are the distinctive characteristics of a PRINCE2 project at its conclusion?
A PRINCE2 project is defined by its finiteness. A clear conclusion acknowledges the achievement of objectives, the transfer of products to the customer, and the cessation of project management team responsibilities.
How is project closure planned and executed in PRINCE2?
Closure activities are planned in the final management stage. Inputs are prepared for the project board to obtain authorization for closure, and if necessary, closure is communicated to corporate, program management, or the customer. In the case of premature closure, the process must still be carried out, albeit adapted to the specific situation.
What are the main activities in the “Closing a Project” process in PRINCE2?
Prepare planned closure, prepare premature closure, deliver the products, assess the project, and recommend project closure.
What must the project manager confirm before recommending the closure of a project?
Ensure that all expected results have been achieved and delivered, and that the project has met what was defined in the project product description.
What steps are necessary to prepare for the planned closure of a project in PRINCE2?
Update the project plan with actual data from the final management stage, request a product status report, confirm that all project products have been approved and meet quality criteria, and verify that acceptance criteria have been met.
What is the last step before recommending the closure of a project in PRINCE2?
Obtain approval to notify corporate, program management, or the customer that resources can be (or are about to be) released.
When and why is premature closure prepared in a PRINCE2 project?
Premature closure is prepared when the project board instructs to close the project ahead of schedule. In this case, it is essential not to abandon ongoing work but to preserve what value has been created and manage the gaps left by the project’s cancellation.
What actions are recommended in PRINCE2 to manage the premature closure of a project?
Update the issue log with the request for premature closure, update the project plan with actual data, request a product status report, and determine the development, approval, and utility status of project products.
What steps are involved in product management and resource release during premature closure?
Agree on how to retrieve completed or in-progress products, including the possibility of additional work to complete or make products safe for use in other projects. Finally, obtain approval to notify the early release of resources.
What is the main task in the “Hand Over Products” process in PRINCE2?
To transfer the project’s products to the operational and maintenance environment, either as a single delivery at the end of the project or in progressive deliveries.
How is the delivery of products managed in premature closure?
Ensure that approved but not yet delivered products are transferred to the customer as per the project board’s instructions.
What preparations are necessary for product delivery and post-project support?
Update the benefits management approach to include post-project reviews and ensure that initial support requirements and service agreements are clearly defined.
What is the main objective of project evaluation in PRINCE2?
To compare the project’s results with the objectives and expected benefits outlined in the business case and use this information to enhance the planning of future projects.