Change Flashcards
What is the purpose of the Change theme in PRINCE2?
The purpose of the Change theme is to identify, assess, and control any potential and approved changes to the project’s baseline. It is important to systematically manage changes to ensure the project remains responsive to stakeholders and under control.
What are the different types of issues and change requests in PRINCE2?
Types include change requests (alterations to the project baseline), non-conformities (absence or non-compliance of a product), and issues/concerns (any other matter requiring action). Each requires assessment and management response.
How are changes managed in relation to baselines in PRINCE2?
Changes are assessed based on their impact on the current baselines. Baselines are reference levels against which items are monitored and controlled. Changing a baseline involves creating a new version of the item while keeping the original baseline unchanged.
What are configuration items and configuration records in PRINCE2?
Configuration items are project objects that require control and baselining. Configuration records describe the state and version of these items. Configuration control ensures changes are authorized and tracked.
What is a Product Status Account in PRINCE2?
It is a report on the status of project products. It provides up-to-date details on the status and versions of products, facilitating the management and control of changes.
What is PRINCE2’s approach to change control?
PRINCE2 requires a defined approach to change control, including the identification and management of issues, assessing the impact of issues on the business justification, and clear roles and responsibilities.
What are the essential products for change management in PRINCE2?
PRINCE2 requires an issue register to track formally managed issues and an approach to change control to manage the protection and control of project products.
What does the issue register contain in PRINCE2?
The issue register documents all formally managed issues, including details of options, recommendations, and decisions made.
When are controls for issues and changes established in PRINCE2?
Controls for issues and changes are defined during the project initiation process and updated at the end of each management stage.
Is PRINCE2 flexible in its approach to change management?
Yes, PRINCE2 recommends an approach to issue management and change control but is not prescriptive. Any approach that meets the described requirements aligns with PRINCE2.
What is the role of the Senior User in the change control process?
The Senior User focuses on issues that impact expected benefits, provides guidance, and makes decisions on escalated issues.
What are the main responsibilities of the Executive in change control?
The Executive determines change authority and budget, assesses the severity of issues, and makes decisions on significant matters, with a focus on business justification.
What are the functions of the Senior Supplier in change control?
The Senior Supplier deals with supply-related issues, ensuring the integrity of the solution and responding to consultation requests.
What are the primary tasks of the Project Manager in change control?
The Project Manager manages the approach to change control, maintains the issue register, and implements corrective actions.
How do the Team Manager and Project Support contribute to change control?
The Team Manager implements corrective actions. Project Support manages documentation and assists in issue management.