Resource Management Knowledge Area Flashcards

1
Q

Maslow’s Hierarchy of Needs

A

people can only ascend to a higher level after fulfilling each of the lower levels; the 5 levels are Physiological (food/water/shelter), Safety (security, stability, freedom from harm), Social (friends, family, love), Esteem (self-respect, self confidence), Self-Actualization (optimal performance, growth, learning)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Herzberg’s Hygiene Theory

A

certain factors in the workplace cause job satisfaction, while a separate set of factors could cause dissatisfaction; hygiene factors (status, job security, salary and fringe benefits) do no cause satisfaction, but if they are missing it could cause dissatisfaction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

McClelland’s Theory of Needs

A

people are motivated by either (1) achievement, (2) affiliation or (3) power and are managed accordingly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

McGregor’s Theory of X -Y

A

Theory X managers (authoritarian) believe people dislike work and employees must be watched closely. Theory Y managers (participatory) believe people are self-motivated and can be trusted to work hard on their own

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Expectancy Theory

A

employees are motivated by the expectation of realistic positive outcomes and related rewards; they remain motivated as long as rewards meet expectations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Responsibility Assignment Matrix (RAM)

A

a grid showing the relationship between work packages and team members

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

RACI Chart

A

Responsible (does the work), Accountable (ensures the work is done), Consult (input required from SME), Input (updated on status); a type of RAM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the forms of power?

A
Formal/Legitimate - power based on title/position
Expert
Reward
Referent
Punishment/Penalty
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Conflict Resolution Methods

A
Collaborating/Problem Solving
Compromising/Reconciling
Forcing/Directing
Smoothing/Accommodating
Withdrawal/Avoiding
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Team Development (Tuckman Ladder)

A
Forming
Storming
Norming
Performing
Adjourning
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Inputs, T&Ts and Outputs of Plan Resource Management

A

Inputs: Project charter, project management plan, project documents, EEF/OPAs

T&Ts: expert judgment, data representation, organizational theory, meetings

Outputs: Resource Management Plan, team charter, project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Inputs, T&Ts and Outputs of Estimate Activity Resources

A

Inputs: Project Management Plan, project documents, EEF/OPAs

T&Ts: Expert judgment, Bottom-up estimating, Analogous estimating, Parametric estimating, Data analysis, Project Management Information System, Meetings

Outputs: Resource requirements, basis of estimates, resource breakdown structure, Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Inputs, T&Ts and Outputs of Procure Resources

A

Inputs: Project Management Plan, Project documents, EEF/OPAs

T&Ts: Decision making, interpersonal and team skills, pre-assignment, virtual teams

Outputs: Physical resource assignments, project team assignments, resource calendars, change requests, project management plan updates, project documents updates, EEF/OPA updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Inputs, T&Ts and Outputs of Develop a Team

A

Inputs: Project Management Plan, Project documents, EEF/OPAs

T&Ts: Colocation, Virtual Teams, Communications technology, Interpersonal and team skills, Recognition and rewards, training, individual and team assessments, meetings

Outputs: Team performance assessments, change requests, project management plan updates, Project documents updates, EEF/OPA updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Inputs, T&Ts and Outputs of Manage a Team

A

Inputs: Project Management Plan, Project documents, Work Performance Reports, Team Performance assessments, EEF/OPAs

T&Ts: Interpersonal and Team skills, Project Management Information System

Outputs: Change requests, project management plan updates, project documents updates, EEFs updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Inputs, T&Ts and Outputs of Control Resources

A

Inputs: Project Management Plan, Project documents, Work Performance Data, Agreements, OPAs

T&Ts: Data analysis, problem solving, interpersonal and team skills, project management information system

Outputs: Work performance information , change requests, project management plan updates, project documents updates