Cost Management Knowledge Area Flashcards

1
Q

Define Cost Management

A

primarily focused on costs of resources needed to complete project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define Earned Schedule

A

an extension of Earned Value Management leveraged in conjunction with actual time (AT). ES is used to calculate an alternate form of SPI and SV using ES/AT and ES - AT respectively

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define Cost Estimates

A

estimation of cost of all resources applied and presented in either summary or detail form, may be represented as a range at varying levels of confidence and may include contingency and management reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define Funding Limit Reconciliation

A

Adjustments made to project expenditures to account for funding limits (e.g. quarterly budgets)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define Financing

A

acquiring funds (internally or externally) for the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define Cost Baseline

A

Authorized, time-phased, total project budget, excluding management reserves, which is used to measure, monitor & control cost performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Define Variance Analysis

A

measuring the difference between planned and actual (used for both costs and duration)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define Earned Value Management

A

an objective mathematical approach to measure cost and schedule performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define Contingency Reserves

A

amounts set aside by the PM to cover known risks and are included in the baselines (can take the form of time and money)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define Management Reserves

A

amount management sets aside to cover unknown risks and not included in the baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define Net Present Value

A

present value of a future income stream, offset against initial investment amount

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Define Payback Value

A

amount of time needed to recoup the project’s investment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Inputs, T&Ts, Outputs of Plan Cost Management

A

Inputs: project charter, project management plan, EEF/OPAs

T&Ts: Expert judgment, data analysis, meetings

Outputs: cost management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Inputs, T&Ts, Outputs of Estimate Costs

A

Inputs: Project management plan, project documents, EEF/OPAs

T&Ts: expert judgment, analogous estimating, parametric estimating, bottom-up estimating, three-point estimating, data analysis, project management information systems, decision making

Outputs: cost estimates, basis of estimates, project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Inputs, T&Ts, Outputs of Determine Budget

A

Inputs: Project management plan, project documents, business documents, agreements, EEF/OPAs

T&Ts: expert judgement, cost aggregation, data analysis, historical information review, funding limit reconciliation, financing

Outputs: cost baseline, project funding requirements, project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Inputs, T&Ts, Outputs of Control Costs

A

Inputs: project management plan, project documents, project funding requirements, work performance data, OPAs

T&Ts: expert judgment, data analysis, To-complete performance index (TCPI), Project management information system

Outputs: Work performance information, cost forecasts, change requests, project management plan updates, project documents updates

17
Q

What is a definitive estimate?

A

A progressively-elaborated cost estimate range of accuracy between -5% to +10%

18
Q

When is a Rough Order of Magnitude used?

A

Initiation Phase

19
Q

What is a Rough Order of Magnitude?

A

An initial cost estimate range of accuracy between -25% to +75%