Planning Process Group Flashcards
Define the Planning Process Group
the processes necessary to establish the total scope of the effort, define and refine the objectives and develop a course of action to obtain those objectives
___________ are set as part of the planning process group
Baselines
Planning is an __________ process and may require revisiting one or both of the initiating processes
iterative
Output of Develop Project Management Plan (4.2)
Project Management Plan; details HOW the PM team will manage the project; HOW the work will be executed; HOW changes will be monitored and tracked; HOW the project will be closed
What are the (24) processes in the Planning process group?
(4. 2) Develop Project Management Plan
(5. 1) Plan Scope Management
(5. 2) Collect Requirements
(5. 3) Define Scope
(5. 4) Create WBS
(6. 1) Plan Schedule Management
(6. 2) Define Activities
(6. 3) Sequence Activities
(6. 4) Estimate Activity Durations
(6. 5) Develop Schedule
(7. 1) Plan Cost Management
(7. 2) Estimate Costs
(7. 3) Determine Budget
(8. 1) Plan Quality Management
(9. 1) Plan Resource Management
(9. 2) Estimate Activity Management
(10. 1) Plan Communications Management
(11. 1) Plan Risk Management
(11. 2) Identify Risks
(11. 3) Perform Quantitative Risk Analysis
(11. 4) Perform Qualitative Risk Analysis
(11. 5) Plan Risk Response
(12. 1) Plan Procurement Management
(13. 2) Plan Stakeholder Engagement
Who should sign the project management plan?
project manager, the sponsor, the project team, and key stakeholders
Key Project Management Plan Components
Change Management Plan; Configuration Management Plan; Performance measurement baseline; Development Approach
Who or what determines the change control procedures set forth in the plan?
PM or OPA
At what point in the project can we stop consulting the Project Management Plan?
After closing
Can we make changes to the Project Management Plan without following the formal change control procedure?
when in draft/planning = yes
once baselined/signed = no
At what point in the project should we have a fully completed project management plan?
end of the planning process group
What is the objective of project scope management?
To ensure all required work is done and no unnecessary work is done (in scope vs out of scope)
Project scope is measured against…
the project management plan
Product scope is measured against…
the product requirements
What are the inputs of plan scope management?
(1) Project charter
(2) Project management plan
What are the outputs of plan scope management?
(1) Scope management plan; a document that describes how the scope will be defined, developed, monitored, controlled and verified.
(2) Requirements management plan; How requirements will be planned, tracked and report
What are some data gathering techniques?
brainstorming, focus groups, benchmarking (comparison vs a standard), document analysis, observation/conversation
Outputs of collect requirements (5.2)?
(1) Requirements documentation
(2) Requirements traceability matrix; links products back to business need, opportunity, goal, objective; project objectives, scope/WBS deliverables, product design, etc.
What is define scope (5.3)?
The process of developing a detailed description of project and product
What are the outputs of define scope (5.3)?
(1) Project Scope Statement: describes in detail the deliverables (product scope); sets forth constraints and assumptions along with how deliverables will be created (project scope)
(2) Project Documents updates
What level of detail should be reflected in the scope statement?
In detail (very detailed)
What is the difference between project scope and product scope?
How I am building it vs what I am building
How does the scope statement differ from the Charter?
Level of detail associated with each document. Scope statement is very detailed while the charter is high level
Define Create WBS
Process of subdividing (decomposing) the project deliverables and project work into smaller, more manageable components