PMP Key Terms and Definitions / Formulas Flashcards

1
Q

Planned Value (PV)

A

Budgeted value of work planned to be done at a given time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned Value (EV)

A

Budgeted value of work actually completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Actual Cost (AC)

A

Actual cost of work completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Budget at Completion (BAC)

A

The original cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Estimate at Completion (EAC)

A

Expected total project cost (forecasted based on performance to date)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Estimate to Completion (ETC)

A

Expected remaining cost (now until project completion)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Variance at Completion (VAC)

A

Expected variance over/under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Variance (CV) Formula

A

EV - AC; Negative is bad, positive is good, zero is on budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

SV Schedule Variance (SV) Formula

A

EV - PV; Negative is bad, positive is good, zero is on budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost Performance Index (CPI) Formula

A

EV/AC; Under 1 is bad; over 1 is good; exactly 1 is on budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule Performance Index (SPI) Formula

A

EV/PV; Under 1 is bad; over 1 is good; exactly 1 is on schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Estimate at Completion (EAC) Formula

A

AC + (BAC-EV) AC plus work remaining, use budget rate (VARIANCES ATYPICAL);
BAC/CPI assumes same rate of spending will continue (VARIANCES TYPICAL);
AC + [(BAC-EV)/(CPI*SPI)] Assumes current cost and scheduled performance will continue

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Estimate to Completion (ETC) Formula

A

EAC - AC; Expected cost of work remaining

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Variance at Completion (VAC) Formula

A

BAC - EAC; Negative is bad, positive is good, zero is on budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

To Complete Performance Index (TCPI)

A

(BAC-EV)/(BAC-AC); CPI needed to compete project within budget;

(BAC-EV)/(EAC - AC); CPI needed to hit EAC - assuming original budget unachievable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is float determined?

A

The float (AKA slack) is determined by Late Finish (LF) - Early Finish (EF)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is critical path?

A

The critical path is the longest duration path through the network diagram. Any delays along the critical path will delay the project. The tasks that have float can be delayed by the amount of float and not delay the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Enterprise Environmental Factors (EEF)

A

the environment you work in that can impact your project; corporate culture, industry standards, infrastructure, political climate; market conditions, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Organizational Process Assets (OPA)

A

any documented processes and procedures; corporate knowledge base (e.g. project archives); organizational knowledge repositories

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is a project life cycle?

A

Series of phases a project passes through from start to finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is tailoring?

A

The appropriate combination of processes, inputs, tools, techniques, outputs and life cycle phases to manage a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is a project?

A

a temporary endeavor undertaken to create a unique product, service or result

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is project initiation context?

A

initiated in response to business factors broken down into four categories: regulatory/legal, stakeholder needs, business change/tech strategies, build/improve products, processes or services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is project management?

A

application of knowledge, skills, tools, techniques, to project activities to meet project requirements effectively and efficiently while integration PM processes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is a program?

A

a group of related projects coordinated to allow for more control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is a portfolio?

A

a collection of projects and programs aligned to achieve strategic business objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What are phases?

A

a group of related project activities allowing for more control and often completes major deliverables; may leverage a phase gate at the end to validate performance and progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What is organizational project management?

A

the alignment of projects, programs, and portfolios and aligning them to strategic organizational goals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What is performance measurement baseline?

A

the original approved plan plus/minus all approved changes; the current approved version of the plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is a system?

A

a set of formal policies, procedures, rules or processes that defines how things are done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is progressive elaboration?

A

an iterative approach (to planning) of increasing the level of detail in the plan as greater amounts of information or more accurate estimates become available; plans are created in multiple passes rather than all at once

32
Q

What is historical information?

A

documents or data from previous projects which are used to assist in future project decisions

33
Q

What is a functional organization structure?

A

a departmentalized structure where employees work for only one manager; project manager has little or no power

34
Q

What is a matrix organization structure?

A

employees report to both a functional manager and a project manager (power is shared)

35
Q

PM has little power, functional manager has most of the power

A

weak matrix

36
Q

PM has moderate power

A

balanced matrix

37
Q

PM nearly has full power, functional manager has little power

A

strong matrix

38
Q

What type of structure does the PM have little or no power?

A

Organic or simple, functional, multi-divisional

39
Q

What type of structure does the PM have total power?

A

Project oriented Organization Structure

40
Q

What is Project-oriented Organization Structure?

A

employees work directly for and report only to the project manager; project manager has full power and authority

41
Q

What is a stakeholder?

A

a person or organization actively involved in the project, or whose interests may be positively or negatively impacted by the project, or who might exert influence over the project

42
Q

What is a business case?

A

Reasons to do a project - market demand, business need or strategic opportunity, customer request, technological advance, legal requirement, ecological impact, social need

43
Q

What is a project manager?

A

tasked with achieving the project objectives; lead person responsible for communicating with all stakeholders including sponsor; may report to a functional manager or program or portfolio manager

44
Q

Organizational structure types

A

FUNCTIONAL, MATRIX (3 types), multi-divisional, PROJECT-ORIENTED, virtual, hybrid, PMO, organic

45
Q

What is the role of the PM?

A

leadership; competencies (technical, leadership, strategic/business management); performing integration tasks

46
Q

Who is the project team?

A

“worker bees”; the PM, the PM team and the team members

47
Q

Responsibilities of the project team

A

carry out the work; collaborate with PM to determine which processes are needed AKA tailoring, prepare estimates, initially resolve interpersonal conflict, develop or contribute to development of team charter

48
Q

Who is the project management team?

A

A subset of the Project team that is directly responsible for the project management and leadership activities of the project

49
Q

What are the project selection models?

A

Mathematical approach;

Comparative approach

50
Q

What are types of mathematical approaches?

A

linear programming; integer programming; dynamic programming; multi-objective programming

51
Q

What are types of comparative approaches?

A

Scoring models (MDMP -> weighted criteria and select highest output),

peer review (PROS vs CONS),

murder boards (intense peer reviews),

economic models (Benefit - Cost analysis, payback period, discounted cash flows, Net Present Value (value of money over time), Internal Rate of Return (IRR)

52
Q

Economic models (comparative approaches): What is benefit-cost analysis?

A

compares the project benefits to the costs to derive a ratio from which a decision can be made

53
Q

Economic models (comparative approaches): What is payback period?

A

Number of periods required to recover a project’s cost

54
Q

Economic models (comparative approaches): What is discounted cash flows?

A

Calculates in today’s (discounted) terms what the value of a project would be given cash inflows and/or outflows over a period of time

55
Q

Economic models (comparative approaches): What is Present Value (PV)?

A

Formula calculates the value today of a future cash flow (income)

56
Q

Present Value (PV) formula

A

PV = FV / (1 + i)^n

57
Q

Economic models (comparative approaches): What is Net Present Value?

A

The sum of a series of discounted future cash flows, offset against initial investment

58
Q

Economic models (comparative approaches): What is Internal Rate of Return (IRR)?

A

The discount interest rate when NPV equals zero; always choose the project with the highest positive IRR; reject negative.

59
Q

Net Present Value (NPV) Formula

A

Sum of [Future Cash Flows / (1 + i)^n] - initial costs

60
Q

Define sunk costs

A

project costs spend to date

61
Q

Define working capital

A

current assets minus current liabilities

62
Q

(2) types of depreciation

A

straight - line (same amount each year), accelerated (ex. buying a car)

63
Q

Define constraint

A

a factor that limits the project team’s options; any restriction placed on the project (ex. include: resources, schedule, budget, scope, etc)

64
Q

Define requirement

A

condition or capability that is required to be present in product/service/result, satisfy an agreement or other formally imposed specification

65
Q

Define Opportunity cost

A

The potential benefit sacrificed by selecting a different course of action.

*Select lower number

66
Q

Project selection methods: values should be as high as possible when selecting between projects:

A

Benefit-cost ratio;
NPV;
IRR;
Return on investment (ROI)

67
Q

Project selection methods: values should be as low as possible when selecting between projects:

A

Opportunity Cost;

Payback Period

68
Q

How many processes are there?

A

49

69
Q

Define process

A

series of activities directed towards causing an end result; one or more inputs create one or more outputs

70
Q

Each individual process has:

A

inputs, tools, techniques, and outputs

71
Q

What is a tool?

A

often something tangible, such as a template, chart or software program; usual used in performing an activity to produce a product or results

72
Q

What is an input?

A

any item required by a process before process proceeds

73
Q

What is a technique?

A

a defined, systematic procedure to perform an activity and may employ one or more tools

74
Q

What is an output?

A

A product, service, or result generated by a process

75
Q

What is a process group?

A

logically-grouped sub-sets of project management processes (which do not always occur sequentially)