PRM SEM 01 - 16. Practical Completion Flashcards
Tasks at Practical Completion
The main contract administration tasks at the end of the job are to: make a snag list of defects, analyse the final account, make the final payment, ensure warranties are in place, and perhaps arrange for the Certificate of Code Compliance.
- Final TA (Council) Inspection
- Practical Completion (and Retentions)
- Defects Liability (and Retentions)
- Warranties and Bond
- Code Compliance Certificate
- Final Payment
It’s handy to look at the project through sections of the NZIA SCC 2018 Standard Construction
Contract. These notes are based on that with an architect administering. If a project manager is
involved it is likely the contracts and architects obligations will be different.
Target date of completion
The target date for completion (the end of the Contract Period) may have been adjusted by Extensions of Time (see lecture on Contract Administration: Section 11: Time for Completion)
Final TA Inspection:
NZIA SCC 2018 doesn’t mention Territorial Authority (Council) Building and Resource Consent
inspections.
It’s a good idea to ensure the Contractor organises the Council’s Final Building Consent Inspection before Practical Completion as this can help identify defects.
In the Contract you could make a Final Inspection a condition of gaining Practical Completion.
As part of this the TA will want Producer Statements from those responsible as these help provide evidence of Code compliance. We usually always require one from the Engineer but there can be a wide range of people responsible (see earlier lecture).
Electricians and Gasfitters need to supply Certificates certifying their work.
The Final Inspection also triggers the issue of the Code Compliance Certificate (see later).
In the SSC how long before Practical Completion must the contractor notify the architect?
The Contractor notifies the architect of Practical Completion “at least 10 working days before that date”. Section E1 in the Schedule contains a form for this.
What does Practical Completion mean?
The architect must inspect the works and assess whether they are practically complete.
This means “everything has been done except for minor omissions and minor defects” that don’t prevent the building being used and that “essential warranties have been supplied”.
If the architect deems the building not practically complete?
If the architect does not consider the building to be practically complete, the architect must explain why, work continues and the Contractor nominates another date.
What needs to happen if the Architect deems the building Practically Complete?
If practically complete, the Architect issues a Certificate of Practical Completion.
Practical Completion Separate sections of the Building
Separate Sections of the building works can be certified practically complete.
The Principal ( client) may occupy a section of the building before Practical Completion if 15 days notice is given to the Contractor and a Code of Compliance (or other approval if required) is obtained from the TA (Territorial Authority/ Council). The Contractor can claim additional costs or time as a Variation.
Practical completion - Approval for temporary use
The TA can also issue an approval tor temporary use as well, such as an opening or dedication function.
Practical completion Cleaning the site
As noted in Section 7 Site, the Contractor must clean and clear up at the end. Often cleaners need to go through twice!
Practical completion - insurance
The architect should ensure their client has their insurance organised to take over from the Contractors. See 6.7 Duration in Section 6 Insurance in the lecture Contract Administration.
Practical Completion Retentions
At Practical Completion the percentage of Retentions stated in Specific Conditions / Schedules are payable (Often 40%, in comparison the NZS 3910 contract releases 50% on Practical Completion.)
Defects Liability
“On the date of Practical Completion the Defects Liability Period begins” (Section 19 Interpretation). This is also often called the Maintenance Period.
The architect makes a “snag list’’ which lists “defective work, materials or fittings” and a timeframe to fix them. This should be done before occupancy as the client moving in frequently causes damage that isn’t the Contractors responsibility!
The Principal (client) generally occupies the building at this date, Practical Completion.
The Contractor must have reasonable access but not inconvenience the Principal.
The length of the Defects Liability Period is stated in the Specific Conditions and 3 months is usual.
Often the client’s occupation results in more defects being discovered and these can be added to the snag list.
The architect issues a certificate when Defects Liability Period finishes. but this doesn’t absolve the Contractor of any “liability to fulfil any obligation in the Contract” (also in 14.9.5).
If the Contractor hasn’t remedied the defects, the architect can notify them that someone else will do it at the Contractor’s expense.
Note that in law builders or anyone generally have a “right to remedy’’, they should be given the opportunity to fix things.
Defects Liability Period Retentions
At the end of the Defects Liability Period the rest of the Retentions (generally 60%) are released.
Practical Completion: Bonds
Uncommon these days (see lecture on Contract Administration), but if there are bonds then:
A Contractors Bond finishes at Practical Completion.
A Contractors Bond in lieu of Retentions lasts until Defects Liability obligations are met.
A Principals Bond finishes at Final Payment.