Experience Area D - Procurement Flashcards
What are the general steps of the tender process?
Select your tenders (selective tendering vs public tnedering
Preparation and submission of tender doucments including instructions
3-4 weeks should be given to prepare tenders
Notice to tenders if required
Tender is recieved prior to the date of submission. Late submissions not valid.
Evaluate the tender sumbissions as soon as possible
Let pricipal know your thoughts and get their agreement of winning tenderer
Notify winning tenderer with a Letter of Acceptance - here a contract exisits
Each tenderer should be sent a list of the tendered sum submitted by each tenderer together with the name of the successful tenderer.
Where a schedule of quantities has been provided, the priced schedule should be submitted as required by NZIA SCC Schedule C2 Schedule of Quantities
Typically how many tenders would you approach?
3-4, max 6
What should the tenders receive as part of the tender documents?
identical documents including:
* drawings
* specifications
* contract pro-forma
* two copies of the tender form
* submission instructions (tender schedules)
* a schedule of quantities if applicable
What is a Notice to Tenders?
A letter with attached doument idenfying additonal information to be given to all tenderers. This will include attachments for related doucments.
How long do you have to evalue the tenders?
Do as quickly as possible. Typically a tender is deemed to remain in force for one calender month
How long should generally be allowed for Tenders
3-4 weeks
What is a letter of acceptance?
A letter to inidicate a successful tender.
What is a PCE?
Preliminary Cost Estimate
Used in ECI
A preliminary estimate is made before the tender of a project when there’s limited information available.
What is an EOI?
Expression of Interest (we can send this to a contractor).
This is one way of getting a list of tenderers
An expression of interest (sometimes referred to as ‘request to participate’) is a submission made by a prospective tenderer in response to an advert (or contract notice) for the supply of goods or services.
What methods are there to get tenderers?
compile a list of capable builders based on past
- collaborations
- client recommendations,
- industry professional recommendations
And EOIs
What is Early Contractor Involvement?
Early contractor involvement is a type of construction contract where the principal contractor is engaged at an early stage in a project to offer input into the design phase.
What are the pros and cons of a CRC?
Pro:
You are paying for what is done
CON:
Unknown final costs
What is Open/Public Tendering?
This method involves inviting contractors to apply for a project through a public forum, providing them
with adequate information to submit their applications.
What is Selective Tendering?
SGA uses a selective tender process by requesting Expressions of Interest (EOI) from potential
contractors. We compile a list of capable builders based on past collaborations, client recommendations,
and industry professional recommendations.
What are Pros and Cons of Early Contractor Involvement (ECI)?
Pro:
a less complex and time-efficient approach compared to a selected tender process.
Figure out details early on
Transparency
Con:
Tension if ECI goes to tender
Ensure no intellectual property conflicts if contractor not awarded to the contractor
What other tender processes exist outside of the NZIA processes?
3910 tendering schedules
Government Electronic Tenders Service (GETS)
If the tender is accepted, what does the client become and what does the tenderer become?
Principal and Contactor
LOOK AT PN 4.110 and make cue cards
ok
What date should you put on the in the Specific Conditions when tendering?
Practical Completion date. Or time in working days to acheive PC
What happens if the Pricipal requests PC in the shortest period of time when Preparing tender doucments?
Where the Principal seeks Practical Completion in the shortest possible time, alternative times for Practical Completion may be stated in the Tender Documents and referred to in the Tender Form
Tenderers can provide alternative prices, for shorter or longer construction periods, on a clearly defined basis.
What happens if tenders ask the Architect for names of subbies?
During the Tender period, the Architect may, if requested by tenderers, provide the names of subcontractors who have indicated to the Architect willingness to quote for their particular portion of the work. - nominated subcontractors
What information may the Architect provide to subcontracting companies upon request? Why might increasing the number of subcontract quotations be advantageous for the Principal?
The Architect may provide the names of tenderers to any subcontracting company requesting this information.
Increasing the number of subcontract quotations may be to the advantage of the Principal.
(Most practicing Architects believe this information should only be released in the final few days of the Tender period to minimise any opportunity for subcontractors to act as a conduit for exchange of pricing information that might disadvantage the Principal).
How should the Architect handle additional Tender information during the Tender period?
The Architect should number each additional issue sequentially (as Notice to Tenderer No….), date them, and ensure they reach all tenderers in time to allow them to act on the information provided.
What requirement should tenderers fulfill in response to the issuance of additional Tender information?
Tenderers should state in their Tenders that they have received the additional information. The tender form should include a pre-prepared statement to this effect.