PN 9.100-9.600 - CHATGPT Flashcards
Flashcard Questions and Answers:
-
Question: What is the purpose of Practice Note PN 9.101?
- Answer: The purpose is to highlight Building Act 2004 (BA04) matters relevant to NZIA architects, especially building consent issues, and provide guidance on preferred practices.
-
Question: What are some key definitions provided in the note?
- Answer: Definitions include “building,” “building consent authority,” “building code,” “building consent,” “building work,” “code compliance certificate,” “compliance schedule,” “licensed building practitioner,” “notice to fix,” “owner,” and “territorial authority.”
-
Question: Where can architects download the Building Act 2004 and Amendment Act 2005?
- Answer: Architects can download the Building Act 2004 and Amendment Act 2005 as PDF files from www.dbh.govt.nz/ba-get-a-copy or purchase them from Vic Books or Bennetts.
-
Question: What cautionary note is provided regarding architects and the new building control regime?
- Answer: Architects should be alert to conditions imposed on them without statutory authority and should not be pressured into signing statements or certificates transferring additional liabilities or responsibilities beyond what the Act requires.
-
Question: How does the note suggest architects handle building consent applications?
- Answer: The owner should sign the application, and the architect can be named as the “Contact person.” Architects should not be appointed as the owner’s agent unless there is a compelling reason.
-
Question: What advice does the note provide regarding amendments to a building consent?
- Answer: Amendments should be made as if applying for a new building consent, and architects should discuss variations with the building consent authority (BCA) before making an application.
-
Question: What are some varying council practices regarding building consent amendments, as mentioned in the note?
- Answer: Practices include using specific forms for amendments, bundling amendments at intervals, clear identification of changes, and the potential future requirement for producer statements.
-
Question: What liability alert does the note provide to architects?
- Answer: Architects, deemed to possess reasonable knowledge of BA04 requirements, may face liability if they fail to give adequate advice to owners and clients on the Act’s requirements.
-
Question: What references are mentioned in the note?
- Answer: References include the Building Act 2004, Amendments to the Building Act, “Information for designers, builders and specialist trades” (DBH folder), NZIA Standard Conditions of Contract, and an example of a council’s “Amendment to an existing building consent – application form” from Rodney District Council.
Flashcard Questions and Answers:
-
Question: What is the purpose of Practice Note PN 9.102?
- Answer: Practice Note PN 9.102 deals specifically with the code compliance certificate (CCC) process under the Building Act 2004 (BA04) and provides guidance on related matters.
-
Question: Define “Code Compliance Certificate” (CCC) as per the note.
- Answer: A “Code Compliance Certificate” (CCC) means a certificate issued by a building consent authority (BCA) under BA04 s.95. The note emphasizes that “Code of Compliance” does not make sense.
-
Question: What key points does the note highlight regarding the application for and granting of a CCC?
- Answer: Owners must apply for a CCC “as soon as practicable after the building work is completed” under BA04 ss.91–95. The application is assessed against the approved building consent plans and specifications, not the building code.
-
Question: What are the main changes in BA04 regarding CCCs, as mentioned in the note?
-
Answer:
- Compliance is assessed against building consent, not the building code.
- No interim CCCs are issued.
- Residential property developers cannot complete a sale or allow possession before a CCC is issued.
-
Answer:
-
Question: How does the note suggest handling the relationship between CCC and Practical Completion?
- Answer: A building may not qualify for a CCC at the same time as Practical Completion, and this varies from contract to contract. Items like client-supplied items and building services may preclude Practical Completion from aligning with the CCC.
-
Question: What are some “implied warranties” for residential contracts mentioned in the note?
- Answer: Implied warranties include proper and competent building work, suitable materials, consistency with the Building Act and Building Code, work done with reasonable care and skill, completion within the specified time, suitability for occupation, and fitness for the specified purpose.
-
Question: What is the significance of the implied warranties for residential contracts mentioned in the note?
- Answer: These implied warranties, applying to residential contracts after November 30, 2004, cannot be contracted out of and cover various aspects ensuring the quality, fitness, and compliance of the building work.
-
Question: What references are mentioned in the note?
- Answer: References include the Building Act November 2004, Amendments to the Building Act April 2005, “Information for designers, builders and specialist trades” (DBH folder), “Sales by residential property owners” (DBH folder), and NZIA Standard Conditions of Contract (NZIA SCC 2008 1st Edition © Dec 2006).
Question and Answer:
Q1: What is the purpose of Practice Note PN 9.103 regarding the Building Act?
A1: The purpose is to address the implications of alterations under the Building Act 2004 (BA04) section 112, considering differences from BA91 section 38. It clarifies compliance requirements and the possibility of relaxation for certain building code provisions.
Q2: What changes from BA91 are highlighted in the practice note?
A2: Notably, the removal of the phrase “to the same extent as if it were a new building” from BA04 section 112(1)(a) distinguishes it from BA91, providing clarity on compliance requirements. Additionally, section 112(2) introduces the potential for relaxing specific building code requirements under certain conditions.
Q3: How does the practice note suggest handling minor alterations that still require a building consent?
A3: Architects are advised to engage with the Territorial Authority/Building Consent Authority early to clarify requirements. This proactive approach is essential when dealing with minor, cosmetic alterations that necessitate a building consent.
Q4: What is the significance of BA04 section 112(2) regarding the relaxation of building code requirements?
A4: BA04 section 112(2) allows for the potential relaxation of certain building code requirements if alterations result in improved means of fire escape and facilities for persons with disabilities. This can occur when the overall benefits outweigh any potential detriments.
Q5: How does the practice note recommend handling design proposals leading to substantial upgrades in commercial building alterations?
A5: Architects are encouraged to review past determinations on the Department of Building and Housing (DBH) website to identify precedents. This research can be valuable when dealing with design proposals that might lead to significant costs associated with upgrading existing commercial buildings.
Q & A:
Q1: What’s the purpose of Practice Note PN 9.104 on the Building Act’s “Change of Use”?
A1: It outlines key aspects and implications of “Change of Use” in Building Act 2004 (BA04), recommending early discussions with the Territorial Authority/Building Consent Authority (TA/BCA) if relevant in a project.
Q2: What’s the significant change in BA04 section 115(a) regarding change of use?
A2: It specifies that a change of use occurs when incorporating household units that didn’t exist before, impacting residential architects more.
Q3: How is “change of use” defined in Building Regulations 2005?
A3: Defined in Regulation 5 and detailed in Regulation 6 with Schedule 2, reflecting fire safety purpose groups.
Q4: What’s subject to upgrading under BA04 section 115(b) for change of use?
A4: It covers a broader range, including means of escape, access, facilities for persons with disabilities, property protection, sanitary facilities, structural and fire rating performance.
Q5: What’s the form of approval and potential offense under BA04 for change of use?
A5: TA/BCA gives written notice of satisfaction, and not providing written notice of a change of use is an offense with a fine of up to $5,000.00 for the Owner.
Q & A:
Q1: What’s the purpose of Practice Note PN 9.105 on the Building Act’s “Compliance Schedules and IQP’s”?
A1: It provides guidance for architects on compliance schedules, focusing on changes in the Building Act 2004 (BA04) compared to the 1991 Act.
Q2: What role did architects traditionally play in compliance schedules under the 1991 Act?
A2: Architects generally had a limited role, with compliance schedules being seen as the domain of specialists like building services engineers. Architects’ involvement was often related to specific architectural features.
Q3: What are the main differences between BA91 and BA04 regarding compliance schedules?
A3: The practice note touches on some differences and briefly comments on the evolving role of architects in compliance schedules.
Q4: Under BA04, when is a compliance schedule required for a single household unit?
A4: A compliance schedule is required for a single household unit only if it has a cable car, as defined.
Q5: What types of systems require a compliance schedule under BA04, and who issues the building warrant of fitness annually?
A5: Systems like automatic sprinklers, emergency warning systems, lifts, etc., require a compliance schedule. The owner, not the TA, issues the building warrant of fitness annually based on IQP certification that all systems are well maintained.
Q6: Can you provide a synopsis of the compliance schedule process under BA04?
A6: The compliance schedule is issued by the Building Consent Authority (BCA) simultaneously with the Code Compliance Certificate (CCC). The IQP certifies to the owner, who must comply and apply to the TA for amendments if needed. The TA can also initiate inspections and charge fees.
Q: What is the purpose of Practice Note PN 9.106 regarding Producer Statements (PS)?
- A: It aims to promote consistent and appropriate practices in issuing and accepting PS from Registered Architects.
Q: What are the main types of PS mentioned in PN 9.106?
- A:
1. PS1 Design: Used for Building Consent, architects are advised caution.
2. PS2 Design Review: Intended for independent design review, recommended only for highly qualified practitioners.
3. PS4 Construction Review: Used for construction monitoring, architects are advised caution.
Q: What is the status of PS under the Building Act 2004?
- A: PS has no statutory status, and its acceptance is at the discretion of Building Consent Authorities (BCAs).
Q: How have changes, such as Risk-Based Consenting, impacted the relevance of producer statements?
- A: Despite changes, producer statements remain crucial. BCAs need a systematic approach to assess compliance.
Q: What responsibilities do authors of PS have according to the practice note?
- A: Authors must sign within their technical competence, state qualifications/limitations, and recommend peer review for complex work.
Q: How should BCAs approach the acceptance of PS?
- A: BCAs should assess compliance considering the nature, complexity, and importance of the work, focusing less on insurance details.
Q: What information should be included in a PS according to the practice note?
- A: Details about the author, building work, compliance, and information to help BCAs determine reliance.
Q: What is the role of insurance in PS according to PN 9.106?
- A: Insurance details are not for risk transfer. BCAs should focus on compliance-related information rather than insurance details.
Flashcard Set: Practice Note PN 9.107 - Reasonably Practicable
-
Q: What is the purpose of Practice Note PN 9.107?
- A: To provide guidance on the meaning of “reasonably practicable” as used in the Building Act 2004.
-
Q: In which section of the Building Act 2004 does the term “reasonably practicable” appear?
- A: Section 112, specifically related to alterations to existing buildings.
-
Q: According to Section 112, for what aspects must an altered building comply with the building code?
- A: Means of escape from fire and access and facilities for persons with disabilities.
-
Q: Are new buildings exempt from complying with the building code under the “reasonably practicable” argument?
- A: No, all new buildings must comply with the building code.
-
Q: What does the term “reasonably practicable” mean in the context of the Building Act 2004?
- A: The term is not defined in the Act, but it involves compliance as near as reasonably practicable to the building code.
-
Q: In the case of Auckland City Council v NZ Fire Service (1996) NZLR 330, what principle was established?
- A: The principle of balancing the benefits of an upgrade against the costs or sacrifices of the upgrade.
-
Q: Give an example from Determination 2007/81 where the DBH weighed costs against benefits.
- A: Upgrading windows in a change of use to apartments; adding fire doors was deemed reasonable for safety benefits.
-
Q: In Determination 2006/104, why was a ramp or lift not considered reasonably practicable for Mt Victoria lookout?
- A: Due to cost considerations and the significant impact on the landscape’s cultural importance.
-
Q: In Determination 2007/73, why was it ruled not reasonably practicable to install a lift in a two-storey warehouse?
- A: Cost and the floor area taken up by a lift were deemed greater sacrifices than the benefits.
-
Q: What is the recommendation if the issue of “reasonably practicable” arises?
- A: Consult with the Building Consent Authority (BCA) at the earliest opportunity to determine compliance.
Flashcard Set: Practice Note PN 9.109 - Dispute Resolution / Arbitration Act
-
Q: What is the purpose of Practice Note PN 9.109?
- A: It provides an overview of dispute resolution for New Zealand construction projects and architects’ conditions of engagement.
-
Q: What dispute resolution processes are provided in NZIA standard contracts for construction?
- A: Formal architect’s decision, mediation, and arbitration.
-
Q: How does the Construction Contracts Act apply to construction contracts?
- A: It provides for adjudication, and any dispute under an NZIA standard construction contract could be referred to adjudication.
-
Q: What dispute resolution provisions do NZIA standard conditions of engagement for architects provide?
- A: Mediation and arbitration, and adjudication for fee disputes.
-
Q: What is mediation, according to the Practice Note?
- A: A confidential process where an independent person assists parties in reaching an agreement.
-
Q: What is adjudication under the Construction Contracts Act, and how is it different from arbitration?
- A: It is similar to arbitration but may not be final; it is enforceable and binding. It’s intended for fees disputes under NZIA conditions of engagement.
-
Q: Describe arbitration as mentioned in the Practice Note.
- A: A confidential process where an independent person decides a dispute based on available evidence; the award is enforceable, final, and binding.
-
Q: What is the structure of the Arbitration Act 1996?
- A: It comprises 20 sections, with the First Schedule covering legal aspects applicable to all arbitrations.
-
Q: What does Section 6 of the Arbitration Act 1996 require concerning the First Schedule?
- A: All arbitrations in New Zealand must comply with all provisions of the First Schedule.
-
Q: What does Clause 5.1(c) of the Second Schedule pertain to, and why might it be opted out of?
- A: It relates to consumer protection; it may be opted out to avoid challenging the award on legal grounds, maintaining cost-effectiveness and finality.
Flashcard Set: Practice Note PN 9.110 - Weathertight Homes Resolution Service Act 2006
-
Q: What is the purpose of Practice Note PN 9.110?
- A: It focuses on Weathertight Homes Resolution Service (WHRS) claims and procedures, applicable to “leaky building” claims.
-
Q: What are the objectives of the Weathertight Homes Resolution Service Act 2006?
- A: To assess damage related to leaking housing, resolve disputes arising from assessments, and provide remedies for owners to recover payments for remedial work.
-
Q: How is a claim initiated with the WHRS, and what does it involve?
- A: For a nominal fee, owners of “leaky buildings” can lodge a claim within ten years of building work. The claim is initiated by applying for an assessor’s report on the property.
-
Q: What is the process for resolution procedures in the WHRS?
- A: For claims with repair costs $20,000 or less, negotiation or mediation is the first step. If unsuccessful, an application can be made to the Weathertight Homes Tribunal for adjudication. Higher-value claims may be directly referred to the Tribunal.
-
Q: What does the adjudication process involve, and how does it differ from mediation?
- A: Adjudication involves pre-hearing communications, potential mediation, and a binding determination by the adjudicator. It is a public, judicial process, different from the mediation process, with parties possibly represented by non-legals.
-
Q: What does the Weathertight Homes Resolution Service Act not replace in a contract?
- A: It does not replace dispute resolution provisions in a contract; if a leaky building matter is part of an arbitration or submitted to arbitration, adjudication cannot proceed.
-
Q: How is “dwellinghouse” defined in the Act?
- A: It includes apartments, flats, or units within a building used as housing, excluding hospitals, hotels, institutions, etc. A “leaky building” is one where water has penetrated due to design, construction, alteration, or materials in the preceding 10 years.
-
Q: What is the recommended action for architects under this Act?
- A: Architects need to be cautious about attending to repairs in an ad-hoc manner, and they should be prepared for potential areas of liability if served with a notice of claim.
-
Q: What is highlighted as a major risk in potential areas of an architect’s liability?
- A: The solvency of the building contractor is a significant risk, as damages claimed might be spread over various parties, including the architect.
-
Q: What issue has contributed to the costs of claims under this Act, and how can it be addressed?
- A: The suggested remediation being out of proportion to apparently minor defects. Addressing this may involve a rigorous debate during settlement negotiations or adjudication submissions.
Flashcard Set: PN 9.111 - Hazardous Substances Building Design
-
Q: What does PN 9.111 guide architects on?
- A: Designing buildings for hazardous substances, focusing on HSNO Act requirements.
-
Q: How does Clause F3 of the Building Code relate to HSNO Act?
- A: F3 references HSNO Act regulations for buildings with flammable substances.
-
Q: Key legislations for flammable substances storage?
- A: Hazardous Substances (Classes 1-5) Regs 2001, Transfer Notice 2004.
-
Q: Schedule 10 significance?
- A: Specifies construction and separation based on substance type and quantity.
-
Q: Types of construction in Schedule 10?
- A: A (platform), B (framed), C (fire-resistant), D1 (strong construction).
-
Q: How to seek a separation distance waiver?
- A: Apply to ERMA; add protection measures like vapor-tight walls or sprinklers.
-
Q: What determines controls for hazardous substances?
- A: Hazardous properties; classifications found on ERMA website.
-
Q: Key references for architects?
- A: Transfer Notice 2004, Emergency Management Regs 2001, Identification Regs 2001, Classes 1-5 Controls Regs, Codes of Practice.
-
Q: Importance of test certifier input?
- A: Ensures compliance with regulations for substances storage.
-
Q: Example scenario steps for isopropyl alcohol building design?
- A: Check hazard classification on ERMA, refer Schedule 10 for building type (e.g., Type D).
Flashcard Set: PN 9.112 - Restricted Building Work (RBW) Design
-
Q: What is the purpose of PN 9.112?
- A: To outline the regulations for Restricted Building Work (RBW) in building design from March 1, 2012.
-
Q: Who can perform RBW design from March 1, 2012?
- A: NZ Registered Architects, Chartered Professional Engineers, or Licensed Building Practitioners (LBPs).
-
Q: What is required for overseas architects to perform RBW?
- A: Apply to become an LBP or consider becoming a NZ Registered Architect.
-
Q: What does RBW in design cover?
- A: Primary structure design, external moisture management systems design, and fire safety systems design.
-
Q: Define the primary structure in RBW.
- A: Includes foundations, floors, walls, roofs, columns, beams, and bracing.
-
Q: Examples of External Moisture Management Systems in RBW?
- A: Damp proofing, roof/wall cladding, waterproofing.
-
Q: What is considered residential for RBW purposes?
- A: Houses and small-to-medium-sized apartment buildings, excluding commercial units, with a height under 10m.
-
Q: What documentation is required from March 1, 2012?
- A: Memorandum (Certificate of Design Work) (CoDesW) for RBW elements, alongside building consent applications.
-
Q: How does CoDesW differ from a Producer Statement PS1?
- A: CoDesW certifies RBW compliance but lacks details on the basis, verification method, and firm-related information.
-
Q: What should designers include in CoDesW?
- A: Design details, RBW compliance, LBP or registration numbers.
-
Q: How is RBW supervision handled?
- A: It can be carried out or supervised by NZ Registered Architects, Chartered Professional Engineers, or Design LBPs.
-
Q: Key information for clients about RBW?
- A: Engage trade LBPs for construction, provide trade LBP names to the council, report replacements, and ensure Record of Work after completion.
-
Q: What is the penalty for knowingly avoiding LBPs for RBW?
- A: It is an offense; clients must use LBPs for RBW.
Flashcard Set: PN 9.113 - Building Amendment Act 2013
-
Q: When did the Building Amendment Act 2013 come into effect?
- A: On January 1, 2015.
-
Q: What does PN 9.113 aim to advise practices about?
- A: Implications of the Building Amendment Act 2013.
-
Q: What are the major changes in the Amendment Act related to?
- A: Consumer rights and remedies in residential work.
-
Q: What obligations does the Building Contractor have before entering a residential building contract?
- A: Provide disclosure information, a checklist, and a written building contract for work over $30,000.
-
Q: What contracts are advised for compliance with the law?
- A: NZIA SCC 2014 or National Building Contract 2015.
-
Q: What is the new 12-month defects notification/liability period?
- A: Builders must fix defects notified by homeowners within 12 months of completing the building work.
-
Q: What is the key issue regarding the completion of building work?
- A: Interpretation of completion concerning Practical Completion Certificate, end of Defects Liability Period, or final inspection.
-
Q: What is the NZIA position on when the building work is complete?
- A: Likely at Practical Completion unless a different interpretation is provided in the future.
-
Q: How long is the Defects Liability Period under contracts like NZIA SCC 2014?
- A: 3 months, and it remains unchanged.
-
Q: What responsibilities do architects have regarding the 12-month defects period?
- A: No responsibility under the Act, but a professional responsibility to advise clients of their rights.
-
Q: What does PN 9.113 say about retentions?
- A: No changes; they are released as stipulated in the contract, not necessarily at the end of the 12-month defects period.
-
Q: What additional obligations on builders are mentioned in PN 9.113?
- A: Further obligations related to implied warranties and durability.
-
Flashcard Set: PN 9.201 - NZIA Forms of Contract – Use
-
Q: What is the purpose of PN 9.201?
- A: To clarify who has the right to use NZIA forms of Standard Conditions of Contract for construction and who should be named as the person administering such contracts.
-
Q: Which NZIA forms are intended for use in alterations or new building work of simple nature and lower value?
- A: NZIA Standard Conditions of Contract Short Form – NZIA SCC – SF (year).
-
Q: Who can use NZIA SCC and NZIA SCC – SF according to PN 9.201?
- A: NZIA Practices holding an Architects Document Set License.
-
Q: What is emphasized regarding the Architect’s representative in NZIA SCC and NZIA SCC – SF?
- A: The representative doesn’t have to be an Architect, but their powers must be well defined, and approval of the contractor is required.
-
Q: How should complete copies of the rules embodied in the Standard Conditions be handled?
- A: They should be clearly included in the documents attached to the contract agreement, and not merely referred to, to avoid misunderstandings and disputes.
-
Q: What could happen in case of unauthorized use of NZIA documents?
- A: Breaches NZIA’s copyright, is unlawful, and may lead to penalties, including criminal prosecution.
-
Q: When must the NZIA Practice Principal or the Architect’s Representative sign or initial the Standard Conditions of Contract?
- A: Wherever the Standard Conditions of Contract require the Practice’s endorsement.
-
Q: What is the NZIA’s position on modifying the rules within the Standard Conditions?
- A: The rules cannot be modified in any way; however, there is flexibility in filling out the schedules/addenda, including special conditions.
-
Q: Which NZIA formats involve the Architect in the construction phase services?
- A: NZIA Standard Conditions of Contract – NZIA SCC (year) and NZIA Standard Conditions of Contract Short Form – NZIA SCC – SF (year).
-
Q: What is the NZIA’s stance on the use of NZIA forms without an Architects Document Set License?
- A: It is considered unauthorized use, breaches copyright, and may lead to penalties.
Flashcard Set: PN 9.202 - NZIA Forms of Contract - Options
-
Q: What is the purpose of PN 9.202?
- A: To advise Architects on the use of NZIA Conditions of Contract and the implications of using other forms of Contract.
-
Q: Which other Practice Notes should PN 9.202 be read in conjunction with?
- A: (a) PN 9.201 NZIA Forms of Contracts – Use, (b) PN 4.110 Procurement, (c) PN 9.203 NZIA SCC Overview, (d) PN 9.204 NZIA SCC – SF Overview.
-
Q: What does NZIA SCC stand for, and what is its purpose?
- A: NZIA SCC stands for NZIA Standard Conditions of Contract. It is a contract between a Principal and a Contractor for the construction of Contract Works, administered by the Architect on behalf of the Principal.
-
Q: Who can use NZIA SCC and NZIA SCC – SF?
- A: NZIA Practices holding an Architects Document Set License.
-
Q: What is NZIA NBC – G 2010, and when is it used?
- A: NZIA National Building Contract General. It is used for construction works where the Architect is not engaged to administer the Contract.
-
Q: What action is recommended regarding procurement in the design process?
- A: As early as possible, obtain the client’s agreement on the method of tendering, form of contract, and specific conditions. Refer to AAS (date) Section C for advised discussion stages.
-
Q: If a client prefers other forms of contract conditions, what should the Architect consider?
- A: Calculate fees appropriate to administer these contracts and seek written approval from the client.
-
Q: What advantages do NZIA Conditions of Contract offer, as per PN 9.202?
- A: (a) Recognized role of an Architect during construction, (b) Competitive bidding due to familiarity, (c) Easier administration of terms and conditions, (d) Well-defined role for the Architect.
-
Q: What should be done if the client decides not to use NZIA Conditions of Contract?
- A: Seek legal and professional indemnity insurer’s advice on proposed alternative conditions. Advise the client in writing of professional risk, quality assurance limitations, and the definition of the Architect’s role.
-
Q: If special conditions are needed, what must happen?
- A: The client must agree to these special conditions, and they should adequately provide for the intended role of the Architect.
Flashcard Set: PN 9.207 - Guaranteed Maximum Price Contracts
-
Q: What is the purpose of PN 9.207?
- A: To discuss Guaranteed Maximum Price (GMP) contracts and evaluate their advantages and disadvantages.
-
Q: How is GMP defined in this practice note?
- A: Fixing the Maximum Price of a project at the completion of Sketch Plan or Developed Design, where the contractor can vary the work to maintain price and program.
-
Q: What are the potential advantages for the client in a GMP?
- A: Cost is fixed with no risk, time is generally fixed with no direct cost penalty for delays, and the contractor may carry certain risks like ground conditions.
-
Q: What quality-related risks does a GMP pose for the client?
- A: Quality is at risk unless contract or sketch plans are very thorough, and there might be a premium paid to the contractor for cost risk.
-
Q: What quality-related risks does a GMP pose for the consultant?
- A: If the quality is not clearly established at the outset, it may be compromised to meet the budget, risking the consultant’s professional responsibility and liability.
-
Q: How can variations on cost/risk sharing be implemented in a GMP?
- A: Some elements with risk aspects may be identified at the pricing stage, and savings or costs are shared between the builder and the client based on actual costs.
-
Q: What alternative building funding and ownership models are mentioned in this practice note?
- A: BOT (Build Operate Transfer), BTO (Build Transfer Operate), DBOT (Design Build Operate Transfer), DBOM (Design Build / Operate Manage), BOO (Build Own Operate), BOOT (Build Own Operate Transfer).
-
Q: What is the central issue in GMP contracts according to the practice note?
- A: Defining the roles, scope, financial, and design responsibilities of each party involved.
-
Q: What are the three basics emphasized in the context of GMP contracts?
- A: Time, Cost, and Quality.
-
Q: Why is it important for architects to define roles and responsibilities early in GMP contracts?
- A: To avoid getting trapped in situations where traditional liabilities exist without the privilege of time, fees, or professionalism from other parties. Architects must ensure a clear brief and understanding of the consequences of the chosen option.
Flashcard Set: PN 9.208 - Cost Reimbursement Contracts
-
Q: What is the purpose of PN 9.208?
- A: The purpose is to provide two new sections that can be used with SCC 2011 and SCC SF 2011 to convert them into Cost Reimbursement Contracts (CRC), also known as Charge-Up Contracts.
-
Q: When are Cost Reimbursement Contracts (CRC) appropriate to use?
- A: CRCs are appropriate when it is challenging to determine a precise total contract price at the Tender Stage, especially in cases like remediation work after events such as the Christchurch Earthquake.
-
Q: What are the two new sections provided with this Practice Note?
- A: (1) Schedules Tendering CRC Specific Conditions of Tender and (2) Schedules CRC Special Conditions – Cost Reimbursement Contract.
-
Q: How can SCC 2011 and SCC SF 2011 be converted to Cost Reimbursement Contracts?
- A: Replace the existing Schedules with the two new sections provided in this Practice Note.
-
Q: What duty does the CRC put on the Architect administering the contract?
- A: The CRC puts an increased duty on the Architect to monitor costs regularly and keep the Principal informed.
-
Q: What should the Contractor provide at the Tender Stage in a CRC?
- A: The Contractor should provide an estimate of direct costs and lump sum items when possible to establish a notional Contract Price, even if it needs revision as the project progresses.
-
Q: In what context is the use of CRCs highlighted in the Practice Note?
- A: The use of CRCs is highlighted in situations where it is difficult to be precise about a total contract price, especially during remediation work such as that resulting from the Christchurch Earthquake.
Flashcard Set: PN 9.210 - Warranties and Guarantees
-
Q: What is the purpose of PN 9.210?
- A: The purpose is to discuss matters related to warranties, particularly examining contractor and subcontractor warranties, and providing a sample warranty agreement form.
-
Q: What is the definition of a “guarantee” as per the Practice Note?
- A: A guarantee is an undertaking by a third party in favor of the first party to act if the second party does not fulfill their obligations under the guarantee, particularly to rectify defects in the contract works.
-
Q: How does the Practice Note differentiate between “guarantee” and “warranty”?
- A: A guarantee involves three parties, while a warranty is an undertaking by one party to make good defects in the contract works.
-
Q: What was the result of the unresolved issue between the Registered Master Builders Federation and the New Zealand Institute of Architects regarding warranties and guarantees?
- A: A new form of warranty agreement was negotiated that can be used for either main contractor warranties or subcontractor warranties.
-
Q: What is emphasized as important for architects when dealing with warranties?
- A: Architects should clearly define roles and responsibilities at an early stage, tailoring documents to the situation, and ensuring a professional and transparent process.
-
Q: What are the common items for which warranties might be considered, according to the Practice Note?
- A: They include tanking, curtain walling, metal cladding, roofing, aluminum joinery, tiling, flooring, surfacing, painting, plumbing systems, drainage systems, and electrical items.
-
Q: What is recommended regarding warranties and insurance of existing structures?
- A: It is recommended to discuss with the insurance advisor the effect that a claim might have on future premium levels and deductibles in the insurance.
-
Q: What actions are suggested for architects regarding warranties?
- A: Be cautious in accepting warranties written by the party warranting the work, use the standard form of Warranty Agreement, and ensure all tenderers are issued with the standard form of warranty agreement.
Flashcard Set: PN 9.211 - Labour Only Contracts
-
Q: What is the purpose of PN 9.211?
- A: To provide guidance on the challenges and considerations associated with “labour only” contracts and to address the absence of a commonly available set of “general conditions of contract” for such contracts.
-
Q: What is the common misunderstanding related to the term “labour only” in house building?
- A: It is often a misnomer; what is meant is that there is no “main contractor” in the traditional sense, and the owner engages separate contractors for different trades.
-
Q: Why are there no commonly available sets of “general conditions of contract” for “labour only” contracts?
- A: There are several separate contracts with overlap and interface between them, making it difficult to clearly define roles and responsibilities. Additionally, each situation is different.
-
Q: Can NZIA’s NCBC-G1 (2010) form of contract be adapted for “labour only” situations?
- A: Yes, it can be adapted by special conditions of contract to a “labour only” situation, with each separate contract being between a Principal and a Contractor for specific work and an agreed consideration.
-
Q: What are the challenges in defining respective responsibilities in “labour only” situations?
- A: Defining responsibilities is challenging because different contractors work on the same site, often simultaneously, influencing each other’s performance in hard-to-anticipate ways.
-
Q: What statutory responsibilities exist under the Building Act in a “labour only” situation?
- A: The owner who obtains the Building Consent is primarily responsible for building to the building code, but this responsibility can be contractually off-loaded onto contractors, including the architect.
-
Q: What challenges exist under the Health and Safety in Employment Act in “labour only” situations?
- A: “Strict liability” ensures each person bears their own degree of responsibility, and in a “labour only” situation, the architect acting as project manager could be in the firing line.
-
Q: What is highlighted as a potential issue for architects attempting to run multi-contract jobs?
- A: Architects may lack the experience, ability, and “clout” to effectively manage trades and may face challenges in getting trades to perform when needed.
-
Q: What caution is given to architects considering “labour only” contracts?
- A: Architects must inform their professional indemnity insurers about their intentions, and insurers may not be willing to keep architects covered for such endeavors.
Flashcard Set: PN 9.215 - NZIA Standard Construction Contracts (2016 Edition)
-
Q: What is the purpose of Practice Note PN 9.215?
- A: The purpose is to provide information on the changes made to the 2016 editions of the NZIA Standard Construction Contract (NZIA SCC) and the National Building Standard Construction Contract (NBC).
-
Q: Which contracts are now superseded by the 2016 editions?
- A: The NZIA SCC:2014, SCC SF:2014, NBC General:2015, and NBC Small Works:2015 are now superseded.
-
Q: What are the current versions of the contracts?
- A: The current versions are NZIA SCC:2016, SCC SF:2016, NBC Standard Construction Contract:2016, and NBC Standard Construction Contract – Short Form:2016.
-
Q: How are the contracts intended to be used?
- A: NZIA Standard Construction Contracts are for use when an architect administers and observes the construction, while National Building Contracts are for situations where the architect is not engaged for such services.
-
Q: What name change has occurred in the contracts?
- A: The “National Building Contract – Small Works” has been changed to “National Building Contract – NBC Standard Construction Contract – Short Form” to align with NZIA SCC versions.
-
Q: What legislative changes are reflected in the 2016 editions?
- A: Changes to health and safety legislation and the Construction Contracts Act 2002 have been incorporated. The Health & Safety in Employment Act has been replaced with the Health and Safety at Work Act 2015.
-
Q: How have retentions been addressed in the 2016 editions?
- A: Retentions provisions have been revised, aligning with NZS 3910 cl.12.3.2(c). The balance of retentions is now payable at the end of the defects notification period, less the cost of any uncompleted work.
-
Q: What changes have been made to the indemnity section (S.5)?
- A: The indemnity provisions related to personal harm have been replaced in total to better reflect the current situation regarding claims.
-
Q: What revisions have been made to the Insurance Schedules?
- A: The Insurance Schedules have been revised to accurately record the types of insurance and specify whether they are in joint names of the Contractor and the Principal or only in the Contractor’s name.
-
Q: What changes have been made to Schedule E2?
- A: Schedule E2 (Producer Statement) has been deleted as it was considered no longer serving a useful purpose.
-
Q: What is the status of these documents for future revisions?
- A: Except for minor corrigenda and erratum, these documents will not be subject to further review until 2018 at the earliest.
Flashcard Set: PN 9.301 - Tendering Procedures
-
Q: What is the purpose of Practice Note PN 9.301?
- A: The purpose is to provide guidance to NZIA members on tendering procedures as the preferred method of building procurement.
-
Q: How are the recommendations tailored in these procedures?
- A: The recommendations are prepared with a special application to projects of “average” type and size but may need modification for larger or smaller projects.
-
Q: What documents should be made available to each tenderer during the tendering period?
- A: Documents should include drawings, specifications, NZIA Standard Conditions of Contract, a copy of the schedule of quantities (if applicable), and two copies of a tender form.
-
Q: What are the time recommendations for tender preparation?
- A: Generally, at least three weeks for small projects, and four weeks for substantial or complex projects.
-
Q: How does the architect handle additional tender information during the tender period?
- A: Additional information should be sequentially numbered, dated, and sent to all tenderers in a timely manner. Tenderers should acknowledge receipt of such information in their tenders.
-
Q: Why is public opening of tenders not recommended?
- A: It can lead to misunderstandings as many tenders include qualifications that may influence evaluation. It’s advised to avoid public openings to prevent misinterpretations.
-
Q: What steps should be taken if a tender appears unreasonably low or contains errors?
- A: The architect should notify the tenderer to confirm the tender price or withdraw the tender. Any tenderer can withdraw a tender before acceptance.
-
Q: How long does each tender remain valid unless qualified differently?
- A: Unless qualified otherwise, each tender remains valid for one calendar month from the submission date.
-
Q: What is the purpose of selective tendering?
- A: The purpose is to obtain tenders from builders believed capable of successfully completing the project. A list of suitable builders is prepared, and a maximum of six tenderers is considered sufficient for competitive tendering.
-
Q: Is a tender deposit required for selected tenderers in selective tendering?
- A: A tender deposit may not be required for selected tenderers as they have been chosen based on their ability to successfully carry out the work.
Flashcard Set: PN 9.302 - Tendering Pro-formas
-
Q: What is the purpose of Practice Note PN 9.302?
- A: The purpose is to assist NZIA members using NZIA SCC and NZIA SCC – SF in obtaining tenders that meet the requirements of SCC and ensuring necessary information is obtained when tenders are submitted. The provided pro-formas are for guidance, not mandatory for use, and may be adapted for specific contracts.
-
Q: What are the key points to note in the Tender Submission pro-forma?
-
A:
- Choose the preferred alternative for submitting tenders and inform tenderers accordingly.
- Ensure equivalence by acknowledging Notices to Tenderers in each tender.
- Note if a Tender Deposit is not required.
-
A:
-
Q: What is the purpose of the Trade Summary pro-forma (Pro-forma 1a)?
- A: The Trade Summary is essential for tender evaluation, and the pro-forma needs adaptation to reflect the trades involved in the specific contract.
-
Q: What is the alternative for Trade Summary for subscribers to MasterSpec™?
- A: Subscribers may use the Tender Summary form included in MasterSpec™ STANDARD and MasterSpec™ BASIC (Pro-forma 1b in CBI classification).
-
Q: What does the Trade Summary - Monetary Allowances - Prime Cost Sums pro-forma (Pro-forma 2) cover?
-
A:
- Prime Cost Sum, excluding costs related to material installation.
- Declaration by the Contractor in the tender of the margins allowed for adjustment of margins, overhead, and profit.
-
A:
-
Q: What is the purpose of the Trade Summary - Monetary Allowances - Provisional Allowances pro-forma (Pro-forma 2)?
-
A:
- Provisional Allowance, covering Contractor’s margins, overhead, and profit.
- Provides for a declaration by the Contractor in the tender of margins (etc) for adjusting Provisional Allowances.
-
A:
-
Q: What do the pro-formas 3 and 4 cover?
- A: Pro-forma 3 provides for the acceptance of tender on behalf of the client, and Pro-forma 4 covers the notification of unsuccessful tenderers.
Flashcard Set: PN 9.303 - Principal Supply Items
-
Purpose:
- To guide exceptions to the Contractor’s obligation to supply all items, known as Principal or Client Supplied Items.
-
Reasons for Principal Supply Items:
- Clients may choose to supply goods they already own or believe they can purchase for the contract.
-
Examples of Principal Supply Items:
- Hardware, sanitary ware, tapware, tiles, light fittings, kitchen cabinets.
-
Responsibility:
- Principal remains responsible even after items are fixed in the building.
-
Disadvantages:
- Incorrect orders, increased time, potential shortages or defects.
-
Recommended Actions (Do’s):
- Advise having the main Contractor supply all goods.
- Use a monetary allowance for unselected items.
- Include a detailed list in the tender.
- Verify the construction programme for delivery dates.
- Ensure timely supply for inspection.
- Value items for insurance at full replacement cost.
- Make the Principal aware of time considerations.