Experience Area E - Contract Admin and Observations Flashcards

1
Q

SSC payment claim and payment timelines?

A

SSC:

Day 0: Payment Claim recieved
Day 5: Issue Payment Schedule
Day 8: Principal amendments
Day 10: Issue replacement payment schedule
Day 17: Last day pricipal has to pay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

NZS 3910 payment claim and payment timelines?

A

3910:

Day 0: Payment Claim recieved
Day 7: Issue Payment Schedule
Day 10: Principal amendments
Day 12: Issue replacement payment schedule
Day 17: Last day pricipal has to pay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What advice should you give to the clients at practical completion?

A
  • Write letter before completion, emphasizing client rights and responsibilities at practical completion with ample notice.
  • Limit insurance advice to facts; recommend seeking detailed advice from experts.
  • Confirm:
    • How you will assess of date of practical completion.
    • Cessation of contractor’s insurances.
    • Procedures for issuing notice of practical completion.
    • Circumstances deeming practical completion.
    • Start of defects liability period.
    • Timelines for claiming liquidated damages.
    • Release of retention moneys, bank guarantees, or bonds triggered by notice of practical completion.
  • Advise on:
    • Remaining works and conditions.
    • Actions taken and proposed.
    • Variations and response timelines.
    • Works incomplete at practical completion (deffered works)
    • Anticipated completion date and potential damages.
    • Assessment of moneys to be released or adjustments to bonds.
  • Recommend:
  • Discussing ongoing insurance with the client’s adviser.
  • Implement agreed matters promptly to avoid delays.
  • Discuss with the client and confirm discussions in writing.
  • Essential for client understanding; failure may cause them to suffer loss.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What advice should you give to the contractor regarding practical completion?

A
  • Write a letter to the contractor after confirming practical completion.
  • Remind the contractor that issuing the notice of practical completion starts the defects liability period.
  • Enclose the practical completion certificate and payment certificate for retentions.
  • Request guarantees, warranties, as-built drawings, maintenance manuals, and other required certificates.
  • Advise on finalizing incomplete works per the contract.

What happens next?
- Adjust bank guarantees or bonds, notify clients, and ensure the contractor provides requested information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What information should you give to the client regarding Defects?

A
  • Note defects during and after practical completion.
  • Obtain client agreement on assessments.
  • Allow the contractor to rectify defects early.
  • Inspect works with the contractor before issuing lists.
  • Confirm defects liability period.
  • Detail incomplete works and defects.
  • Request client advice and acceptance.
  • Promptly issue a letter for client input.
  • Next steps:
  • Follow up with the contractor to formally notify defects.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What information should you give to the contractor regarding Defects?

A
  • Provide defect list during the liability period.
  • Notify the contractor of all defects before the period ends.
  • Advise defects and incomplete works.
  • Instruct the contractor to submit a completion program.
  • Agree on a rectification program with the client and contractor.
  • Inspect after defects are addressed.
  • Issue the defects liability certificate upon completion.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does practical completion mean?

A

That the works can be used for their intendd purpose.

This excludes work that is: deffered, minor omission and defects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who should you not issue practical completion to?

A

Not to third parties (no one that is not in the contract!!!)

ie. a purchaser shouldnt be issued the practical completion document to purchase a property

The contract notes that “The certificate cannot be relied on for any other purpose.” and “They are NOT issued to any other
party and cannot be relied upon by any other party.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can you bring an outside expert to certify Practical Completion?

A

NO - The Architect can bring outside expertise in but the authority of the final decision/power rests with the Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What should you do if someone pressures you to issue PC?

A

Never issue such certificates prematurely under pressure from anyone.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When does the DLP start?

A

The Defects Liability Period is the period stated in the Specific Conditions of Contract. It commences from the date on which the Contractor achieved Practical Completion and continues for the stated period ending when the Contractor has completed all omissions, corrected all defects and completed all deferred work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you issue PC with conditions attached?

A

No - Practical Completion and Defects Liability Period certificates cannot be issued “subject to” or “conditional on” completion of listed items.

a list can be attached listing the minor omissions, minor defects and deferred work that has been agreed with the Contractor. This list is consistent with the definition of Practical Completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What do you need to do if you Payment Schedule does not match the Contractors Claim?

A

be sure to give adequate reasons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What action should members take regarding clients and slow payment or short-payment, and what potential consequences should clients be educated about?

A

Members should educate Clients about the consequences of slow payment or short-payment so that the client may accommodate the risks as they see fit. They may otherwise seek retribution – on the basis of a latent but un-notified risk - when the Contractor walks off the job or stymies on-sale (or financing arrangements) by exercising their rights under the Act.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Do you need Form 1 for non-residential projects?

A

Yes now you do - I believe it was previously only for Residential projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How does CCA apply differently when it comes to residential vs commercial?

A

Adjudication processros are differnet.

Adjudicators can approve issuing a charging order (enforcement) over a construction site except under a residential construction contract.

Look at PN 9.501

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Maybe go through the CCA here in depth. or in the ACTS and SHIT deck

A

f

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What document is required to be issued by the Contractor when making a claim on a residential project under the CCA?

A

The Construction Contracts Regulations 2003 Form 1 must be issued by the Contractor when making a claim on a residential project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What risks should the architect be aware of when setting the requirement for a warranty, checking its wording, and ensuring its delivery to the client?

A

Be aware that in setting the requirement for a warranty, in checking the wording of the warranty offered and in ensuring that the signed warranty agreement is obtained from the contractor and delivered to the client, risk exists to the architect.

Be aware that requesting a warranty also incurs a cost addition to the contract sum and this additional cost included in the tender may not offer value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What challenge may arise for those pursuing a warranty for building work, especially concerning failures in workmanship?

A

Many who have tried to pursue a warranty for building work have discovered that, although a manufacturer may back up the product, one must look to the installer for a failure in workmanship. Proving the failure and pursuing the installer may take considerable effort.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What potential consequences might architects face if the installer is of no substance and the client relied on the comfort of the warranty?

A

If it transpires that the installer is of no substance and the client has relied on the comfort of the warranty, there could well follow accusations that the architect’s design was deficient and/or that the architect “failed to adequately supervise.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the definition of a Warrenty?

A

A warranty is an undertaking by one party to another (to make good defects in the contract works).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the defenition of a guarantee?

A

A guarantee is an undertaking by a third party in favour of the first party, to act in the event that the second party does not fulfil their obligations under the guarantee (to make good defects in the contract works).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are some examples of Guarantees in the building industry?

A

Master Builders New Home and Alterations & Additions 7-year Guarantee Agreement.

This is a true guarantee because in the event of the failure of the contractor, Master Build Services are required to make good (third party)

BuiltIn guarantee used at Apple Shed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What are the contrasting arguments regarding the duration of warranties for construction work?

A

On the one hand there are those who will argue that the contractor or subcontractor should be prepared to warrant their work for the full durability period required under the New Zealand Building Code.

On the other hand it can be argued that as consumers have protection under the Consumers Guarantee Act, Fair Trading Act and the Building Act no warranties should be required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What factors should architects consider when preparing a list of warranties for a construction contract?

A

ach architect preparing a list of warranties to be provided as part of a construction contract will have to make their own judgement call. Factors to consider might include:

(a) What period is normally offered?
(b) Client expectation (of warranties)
(c) The strength of the person from whom the warranty is being sought
(d) The likelihood of the warranty being called up.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What are some key construction items for which warranties might be considered in a construction contract?

A

Key items for which warranties might be considered include those relating to weathertightness, waterproofness, and others related to appearance matters.

This relates to B2 durability 50,15, and 5 year dates

(a) Tanking (bituminous and sheet) 15 years minimum
(b) Curtain walling 5 years minimum
(c) Metal cladding 15 years
(d) Roofing 15 years
(e) Aluminium joinery 2 years
(f) Tiling 2 years
(g) Timber strip and overlay flooring 1 year
(h) Vinyl, linoleum and cork surfacing 5 years
(i) Carpeting 5 years
(j) Painting 2 to 5 years
(k) Specialist protective coatings 5 years minimum
(l) Plumbing systems 2 years
(m) Drainage systems 2 years
(n) Electrical items 1 year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

When a warranty is required from a subcontractor (no direct contract link), how should the warranty be executed?

A

must be executed in the manner required under section 180 of the Companies Act 1993. This will vary from company to company. However as a general guide it might be expected that two directors will normally be required to sign. Where only one authorised person may sign, a witness may also be required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Why should you be cautious about accepting warrranties by the party wanntenting the work?

A

Be cautious in accepting warranties written by the party warranting the work. Such warranties are likely to have a generous sprinkling of pre-conditions and escape clauses.

Use the standard form of Warranty Agreement and ensure that contractors and subcontractors sign only these forms with no additions or alterations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is consequential loss?

A

For example a plumber may repair a leaking pipe in the wall but who makes good the wall? This case is normally covered by insurance in relation to consequential loss. The insurer will not cover the defect but will provide cover for consequential loss and making good any area affected by the defect.

Consequential damages, otherwise known as special damages, are damages that can be proven to have occurred because of the failure of one party to meet a contractual obligation, a breach of contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is the role of the Enginner to the contract/Architect in regards to roles and responsibilities?

A
  • Expert adviser to representative of the owner(s)
  • Ordering of variations
  • Giving directions on behalf of owner(s)
  • Accountable to owner(s)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What are Project Control Group Meetings?

A

Held monthly to determine project progress, cost status, and authorities’ approvals, to confirm key design decisions, and to discuss user issues.

This refers to the key stakeholders who are involved with your project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What is the role of the Enginner to the contract/Architect in regards to being the owners representative?

A
  • Acts as agent for owner(s)
  • Issues all directions or instructions
  • May appoint engineer’s representative
  • Issues Certificate of Practical Completion
  • Issues Defects Liability Certificate
  • Has power to suspend the works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What is the role of the Enginner to the contract/Architect in regards to an Independent third party?

A
  • Impartial decision-maker
  • Values the work in progress
  • Issues Progress Payment Schedules hedules
  • Issues Final Payment Schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

How can variations arise?

A
  • Request from contractor
  • Site Instruction – identify client request items/no cost instructions
  • Variation Price Request – quotation, invoice requirements, dayworks, client request items
  • Variation Order – varies the contract sum
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What is a variation order?

A

an alteration to the scope of works in a construction contract in the form of an addition, substitution or omission from the original scope of works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What is the purpose of the CCA?

A
  • To facilitate regular regular and timely payments
  • Provide for the speedy resolution of disputes
  • Provide remedies for recovery of payment
  • Relates to residential construction contracts
  • No contracting out of the Act
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What can a site pre-start/Initial Meeting include?

A
  • Introduction of representatives
  • Communication and site responsibility issues
  • Scheduling of Project Control Group meetings
  • Confirmation of start date for the works
  • Reviewing of contractor’s programme
  • Confirmation of insurance cover for the works
  • Reviewing Payment Schedules and processes
  • Review list of sub-contractors and suppliers
  • Outline processes for dealing with Variations
  • BCA liaison and inspection requirements
  • Site security
  • Health and safety matters
  • Design clarification or procedural issues
  • Owner concerns or questions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What can PCG Meetings include?

A
  • Receive contractor’s progress report
  • Review of construction progress against programme
  • Relevant quality issues
  • Costs and comparison with budget
  • Construction activity issues
  • Unanticipated delays
  • Design clarifications
  • Contract variations
  • Owner concerns
  • Unforeseen variations
  • Health and safety matters
  • Often held two-weekly or monthly
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

How can you communicate with the clients regarding Budget updates?

A
  • Comparison of costs against budget
  • Explain reasons for cost escalation
  • Clearly identify betterment and client request items
  • Clearly explain additional fee costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

What is the CCC?

A

Code Compliance Certificate - A CCC is a formal statement confirming that the council are satisfied all building work has been completed in accordance with the building consent the council issued.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

What is a Record of Building Work? Form 6A

A

If you are an LBP and you have carried out or supervised restricted building work as part of a building consent, you need to complete and submit a Record of Building Work (Memorandum) as soon as possible to avoid delays issuing the Code Compliance Certificate (CCC) to the owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

When should Warranties and Guarantees be provided?

A

Warranties and guarantees should be provided prior to
issue of the Defects Liability Certificate and Final
Payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

How do the timelines differ from a normal payment cliam vs a final payment claim?

A
  • be in writing and be endorsed “Final Payment Claim”;
  • state that the due date for payment shall be 45 Working Days after the date the final
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

How do the timelines differ from a normal payment schedule vs a final payment schedule?

A

The Architect must within 20 Working Days of receiving the Contractor’s final Payment Claim issue a Final Payment Schedule to the Principal.

The Final Payment Schedule must note the date received and the due date for payment which shall be 45 Working Days from the date the final Payment Claim was received by the Architect;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

What action must the Architect take if the issue of the Final Payment Schedule exceeds 20 Working Days?

A

0,5,8,10,17 (this is the same as normal)

Day 0: Payment Claim recieved
Day 5: Issue Payment Schedule
Day 8: Principal amendments
Day 10: Issue replacement payment schedule
Day 17: Last day pricipal has to pay

Should the issue of the Final Payment Schedule take longer than 20 Working Days, the Architect must issue a certificate in the form of a Payment Schedule for all amounts due under the Contract that can be certified at that time.

This must be done within 5 working days

Here payment will be due 12 Working Days from the date the Payment Schedule is issued by the Architect;

The Principal must notify the Architect within 3 Working Days from the date the Payment Schedule was issued by the Architect of any amendments or deductions

5 Working Days from the date of the date the Payment Schedule was issued by the Architect, the Architect must issue a replacement Payment Schedule with the revisions required by that notice.

The Architect must continue to issue such Payment Schedules at monthly intervals until the Final Payment Schedule is issued.

This is what we did for Oratia(unknowingly). There were TWO payment claims after practical compltion!!!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

If the principal wants to make amendments or deductions from Final Payment Claim, when must they do this by?

A

The Principal must notify the Architect within 30 Working Days of the date the Architect received the final Payment Claim.

47
Q

if pricipal gives notice to make amendmennts or deductions on the final payment claim, when Architect must re-issue the Final Payment Schedule?

A

not later than 35 Working Days after the date the Architect received the final Payment Claim, the Architect must re-issue the Final Payment Schedule with revisions as required by that notice.

48
Q

Within what timeframe must the Principal pay the scheduled amount shown in the Final Payment Schedule?

A

The Principal must pay the scheduled amount shown in the Final Payment Schedule, along with the amount of goods and services tax payable, within 45 Working Days of the date the final Payment Claim was received by the Architect.

49
Q

What are the dates for the Final Payment Claim?

A

Day 0: Payment Claim recieved
Day 20: Issue Payment Schedule
Day 30: Principal amendments
Day 35: Issue replacement payment schedule
Day 45: Last day pricipal has to pay

50
Q

What is the interest rate if principal fails to pay?

A

The interest rate shall be 1.5 times the Reserve Bank of New Zealand monthly small to medium-sized enterprise overdraft rate over the relevant period.

51
Q

Within what time frame can the Final Payment Schedule not be disputed by the Contractor or the Principal?

A

The Final Payment Schedule cannot be disputed by the Contractor or the Principal more than 55 Working Days after the date the Contractor’s Final Payment Claim was received by the Architect, or more than 20 Working Days after any relevant Adjudicator’s Determination, whichever is the later.

52
Q

What may you give to the principal at Completion.

A
  • Technical Instructions (appliacnes etc)
  • As-Built drawings
  • Maintainance plans

(SGA completion book)

53
Q

What information might you gather for disputes?

A
  • Gather all the proof required to establish reasons for failure
  • Record reasons for failure
  • Don’t exaggerate or over-state extent of problems
  • Carefully record sampling processes
54
Q

How might you deal with body corporates?

A
  • Attempt to work only with a specific committee
  • Use a committee spokesperson as your contact
  • Listen to their point of view
  • Keep spokesperson and committee fully informed
  • Provide alternatives where possible and involve committee in decision-making process
  • Identify clear and achievable goals
  • Don’t over-inform and confuse people
55
Q

Should you provide Practical Completion Certificates if you have not been engaged to do Admin and Obs?

A

NO!

when the client requests a property inspection and the issuance of a Practical Completion Certificate, the architect should NEVER acquiesce and provide this service – no matter how qualified the PCC is.

DON’T PROVIDE A PCC FOR YOUR DESIGN PROJECT, UNLESS YOU HAVE PROVIDED FULL PROJECT ADMINISTRATION SERVICES.

56
Q

Shoudl you use client generated contracts/documents?

A

No - strongly advised against by the NZACS

57
Q

What are the four types of Producer Statements?

A

PS1 - Design
PS2 - Desing Review
PS3 - Construction (often used by the installers of proprietary systems)
PS4 - Construction Review

58
Q

What is a Producer Statement?

A

a producer statement is a document prepared by a Registered Architect confirming his/her professional opinion. This opinion is based on stated reasonable grounds that aspects of design of a building achieve compliance with the building code, or that elements of construction have been completed in accordance with the approved building consent.

A producer statement is a professional opinion based on sound judgment and specialist expertise. It is not a product warranty or guarantee of compliance.

A PS gives evidence that design or building work complies, or will comply, with the Building Code and helps teh Council make a decision to issue a building consent or a Code of Compliance Certificate (CCC).

The producer statement system is intended to provide Building Consent Authorities (BCAs) with reasonable grounds for the issue of a Building Consent or a Code Compliance Certificate, without having to duplicate design or construction checking undertaken by others.

Producer statements are typically used for specialist work, such as engineering, or where there is a proprietary product which is installed by appointed contractors.

59
Q
A
60
Q
A
61
Q
A
62
Q
A
63
Q
A
64
Q

Do Architects need to provide PS1s?

A

NZIA advice to members is that we do not believe that a PS1 is required. If you have to, you should only sign a PS1 for the elemental part of the building work that the PS1 refers. If there are a number of elements that the BCA requires a PS1 for, you should a separate PS1 for each element.

Do not sign a PS1 that covers everything in the documentation as complying with the building code.

A PS1 should not be required for RBW as a Memorandum of Design Work must be signed by the architect in its place.

65
Q

Do Architects need to provide PS2s?

A

The NZIA recommends that only highly qualified practitioners with a high level of competence in the area of the building work to be reviewed consider signing a PS2.

PS2 is intended for use by a suitably qualified, independent, competent design professional (i.e. Registered Architect) as a statement of opinion, based on a review of design documents (which have been prepared by others) and on stated reasonable grounds, that certain aspects of proposed building work will comply with the building code, if the work is constructed in accordance with the referenced documentation.

66
Q

Who should sign PS3s?

A

This PS3 is generally signed by the building contractor and sub-contractors and should not be signed by an architect.

67
Q

Who should sign PS4s?

A

The NZIA recommends that you do not sign a PS4. If you have to, you should only sign a PS for the elemental part of the building work that the PS1 refers and look to other suitably qualified people to supply supporting information.

Refer to the PS1’s that you have signed at building consent stage. These are the only elements you should sign a PS4 for.

An engineer might provide this

Intended for use by a suitably qualified independent design professional who undertakes construction monitoring of the building works where the BCA requests a producer statement prior to issuing a Code Compliance Certificate. This must be accompanied by a statement of completion of building work (Schedule 6).

68
Q

Do Producer statements have any statutory status?

A

Producer statements have no statutory status under the Building Act 2004.

69
Q

Is a PS a product warranty or guaarantee of complicance?

A

a producer statement is not a product warranty or guarantee of compliance. It is a professional opinion.

70
Q

Can Architects say no to a a Councils request for a producer statement?

A

A BCA can reasonably request a PS1 producer statement to accompany an application for building consent. However if the consent applicant doesn’t want to or isn’t able to provide this, then the BCA must consider other options for establishing code compliance. (e.g. engage its own engineer to undertake a review).

A BCA may reasonably request a PS2 producer statement to accompany an independent Design Review, if it is to accept that review. A BCA may also reasonably request a PS4 producer statement for Construction Review of specifically designed elements and some will seek to make it a condition of granting consent. A BCA cannot refuse to issue a building consent or code compliance certificate simply because it cannot be provided with a producer statement. In this situation the BCA will need to assess compliance in another way (e.g. engage its own engineer to undertake a review or inspection).

71
Q

Can a firm sign a producer statement?

A

The author of a producer statement must be a natural person (rather than a corporate/legal entity) because the value of the statement is dependent on the individual competence of the author.

Nevertheless, the author’s affiliation to a legal entity (such as an employee of a company) is a relevant matter in relation to risk mitigation information. Authors should ensure they have legal/contractual authority to commit the design firm/entity to the liabilities implicit with the issuing of producer statements.

72
Q

Does signing producer statements increase your liability?

A

Because producer statements are not provided for in the Building Act 2004, information about professional indemnity insurance on producer statements is not a legislative requirement (either Building Act 2004 or BCA accreditation regulations). As such the level of insurance cover should have no direct relevance to the statutory decision to determine compliance with the building code or approved building consent.

73
Q

WHat is a Variation Request?

A

– used to establish the cost of proposed Variations
– Not a direction to carry out the work
– Architect assesses, Client approves

Variation Price Requests (VPRs) are not referred to in SCC1 and must not be confused with Variations or other Architect’s Directions. A VPR is a request to the Contractor to price (and, if applicable, claim an extension of time) for a contemplated change in the contract works. It must be made clear to the contractor that a VPR is simply a request for a price and that they are not to precede with the work unless further directed.

74
Q

What is a Variation Order?

A

– Directions to carry out work that makes changes to the contract with respect to:
* Cost
* Time – Extensions of Time
* Cost and time – Extensions of Time

75
Q

If Architect is not adminstrating the contract, how much power do they have under the contract? ie directions

A

If they are not admistering the contract this means the Architect-CLient agreement is a limited services agreement. The Architect can only advise. The project manager or client will have to give variation orders

76
Q

What information is needed for a CCC?

A

You need to include:

  • Documents provided by your Licensed Building Practitioners or registered professionals, e.g. Memorandum: Record of Building Work
  • Warrenties and User Manuals from the Contractor
  • Schedule of Inspections/Conditions of the Building Consent (i.e. PS1’s, PS3’s, Energy Works Certificate, etc.)
  • Final PASSED Inspection from Building Inspector
  • Additional documents requested during inspections.
77
Q

What information is needed before Practical Completion?

A

Schedule E1

Clause 4.7 of SCC: “Documents required at Practical Completion”

  • Warranties and other information required from the Contractor which are essential for the Principal’s use of the Contract Works.
  • Documentation required for Certificate For Public Use application.
  • Documentation required for Code Compliance Certificate application.

At Apple Shed we asked for (but I think most of these are more relevant for CCC:

Schedule E1
Schedule G1 Contractors Warranty Agreement
Warrenties and User Manuals from the Contractor
Schedule E2 (this is no longer a thing I think)
Schedule of Inspections/Conditions of the Building Consent (i.e. PS1’s, PS3’s, Energy Works Certificate, etc.)
Final PASSED Inspection from Building Inspector
Documentation for Code of Compliance

78
Q

Difference between COWs and ROWs?

A

Certificate of Design Work – submit with consent application (to do with design)

Records of Building Work – submit with application for a code compliance certificate at the end of the project (to do with construction)

79
Q

What is the difference between the proformas “Architects directions - variation” vs “Architects Direction”?

A

The Architect issues all Directions to the Contractor (Rule 4), which includes Variations to change the Contract Works (Refer 9.0 Variations).

SCC1 Section 19 defines “Direction” to cover a wide range of matters. Attached is a pro forma for general use in matters, which do not constitute a Variation.

80
Q

What’s happens if a contractor fails to fix the defects?

A

seek legal advice as you may be able to have another tradesperson repair the work and have the contractor pay the costs

From SCC:

If the Contractor does not correct a defect or complete deferred work on time, the Principal may employ another Person to correct the defect. The Architect must give the Contractor 5 Working Days notice of this intention. The Contractor must pay the Principal’s cost for correcting the defect. The Principal can deduct any cost for correcting the defect from money owed by the Principal to the Contractor.

This is similar under CGA

81
Q

What is a certificate of public use?

A

If you want to let the public use a building before we issue a code compliance certificate, you must apply for a Certificate for Public Use.

Public premises can only be occupied if a Code Compliance Certificate (CCC) has been issued or a CPU is in place

A CPU maybe applied for at the same time as the building consent, if the proposed work involves alterations or additions to an existing building and this work affects public access to the premises. Work cannot commence until such time as a CPU is in place.
In the case of a new building, if a CCC has not been issued, the premises cannot be occupied unless a CPU is in place.

82
Q

What do you need for an application of public use?

A

Form 15

Building consent applicants must provide information about how the public will be protected whilst building work is underway

Plans showing the relevant areas for CPU

List of Active Specified Systems/Compliance Schedule

Relevant producer statements (structural, fire, access etc)

How the public will be protected can include but not limited to the following issues:

• What parts of the building are occupied and or will the public have access too?
• What access / egress routes will be compromised by the building work (walking near or through building work)?
• What hazards will the public potentially face as a result of the building work?
• What protection measures can be put in place to protect the public?
• What safety systems are in place to protect the public or building occupants (i.e. will specified
systems be operational during construction)?
• What mitigation measures can be implemented to ensure the safety of the users where life safety
features have been disconnected / decommissioned?
• What alternative safety features can be utilised to provide the same or better security in terms of the
health and safety of the public, where safety features are not operational?
• What protection measures are in place?
o Paving and ramps
o Fencing off the construction area
o Hoardings - protection from falling objects

83
Q

What is the difference between mediation, arbitration and adjudication?

A

Mediation focuses on helping parties find their own solution through negotiation, while arbitration involves a third party making a decision on the dispute.

If both parties agree to it, you could try mediation, where both parties try to come to an agreement with the help of a mediator. Often the contract will include a requirement for early mediation of disputes.

Like mediation, arbitration requires both parties to agree to participate and also agree on the arbitrator. The building contract may require that disputes are resolved through arbitration. The arbitrator’s decision (called an Award) is binding and enforceable by a legal court. However the process is less formal than court.

Adjudication is an alternative dispute resolution process for resolving construction and build disputes. During adjudication, a neutral third-party or adjudicator will resolve the conflict which arrises under the construction contract. This outcome reached by the adjudicator is termed a determination. Adjudication happens under CCA

84
Q

What happens if the client wants to do part of the building work?

A

Eg a retaining wall like they did in Oratia. Or cabinetry like in England Street

Is it exempt under Building Act Schedule 1?

Do they have an owner builder exemption?

If working alongside a builder how does this work in regards to their insurance.

If client contract works insurance the insurance company would need to be informed

Will this work affect the integrity of the building.

RBW

What is the contract works, this this included? Are you reviewing it (don’t)?

85
Q

If the Architect doesnt agree with the principals amendment to the payment schedule, can Architect override?

A

No - even if it may be deemed unfair

86
Q

Does payment indicate an acceptance of contract?

A

No, but it does indicate A contact but not the conditions of the contract.

I believe you would therefore default to common law/unlimited liability/tort

87
Q

What is a critical path?

A

Timeline of construction sequencing - deviation from critical path will cause delays and hence may affect practical completion date

88
Q

Who are SiteSafe?

A

A national non-profit origination that promo sites improved H&S culture in NZ.

Education and resources

Offers training
Courses
Resource material

Issues voluntary qualification. Consultant passport, contractor passport

89
Q

What are the typical inspections taken by council inspectors?

A

Noted on the inspection booklet given with your approved RC. Can include:

pre-pour (before concrete is poured, for example, for piles, footings, slabs, in situ walls or blockwork infill)

tanking/waterproofing (before back-filling retaining walls, covering membranes on decks or laying tiles in wet areas such as showers)

pre-clad (before wrapping the building in building paper or building wrap and installing the cladding)

post-clad (before applying coatings to fibre cement or polystyrene systems, possibly including inspections during plastering)

pre-line (with insulation installed but before installing internal linings. This inspection may include checking the plumbing installation under pressure test)

drainage (before filling in trenches and covering the in-ground pipework). Pipework should be under test for this inspection. Drainage testing can include smoke, air or water testing
final inspection for plumbing, building and drainage work (once the work described in the building consent is complete).

90
Q

Who affects the insurances in a tenancy? (Building owner vs tenant)

A

Residential tenancies Act 1986

Building Owner - Landlord Insurance
Tenant - Contents Insurance

91
Q

What is the difference between Annual Run-off and Annual Cut-Off Insurance?

A

Annual Run-off:
Cover continues until the completion of the project

Annual Cut-off:
Cut-off means that the policy lapses T the expiry date of the policy unless specially renewed

92
Q

What is the PPSR register?

A

An online noticeboard where details of security interests in personal property can be recorded and searched

The PPSR is effectively an online noticeboard where you can register a legal claim to personal property, and check if there is any debt or obligation attached to goods you may wish to buy.

In relation to Personal Properties Securities Act 1999

93
Q

How is information requested by the builder? And is this recorded by Architect or Project Manager?

A

RFIs

Recorded and tracked through an RFI register

RF1#, date received, due date, response date

94
Q

What can a QS provide in regards to Payment Claims?

A

Payment recommendation/progress evaluation

95
Q

What construction items might you request shop drawing early on due to long lead times?

A

Structural steel, pre cast concrete, window systems, cabinetry

96
Q

What happens if the contractor/subbie goes into receivership or liquidation during construction?

A

Refer to contract. SCC notes that principal may end Contract
Get legal advice
Call up bond
Guarantee may be useful in this scenario
Secure site

97
Q

How are shop drawings processed?

A

Usually 10 working days

Shop drawings should be stamped with NZIA disclaimer

Architects only should review shop drawings and not approve

98
Q

Who is responsible for coordinating council checks during construction as required for the consent?

A

Contractor on behalf of the principal

99
Q

How do you ensure that your fee covers the scope of work required by the architect during contract admin?

A

Either;
Perform services on a ‘time charge’ basis. Hourly rates defined in AAS Part C.
identify Contract’s completion date and advise Client that overruns will be dealt with on a ‘time charge’ basis.
percentage based on ‘Adjusted Cost of Contract Works’
NB: 15% default for Admin/Observation in typical fee structure is deemed insufficient in today’s climate refer to recent NZIA webinar 25.08.18 (20%+).

100
Q

What is the process for an extension of time request /claim?

A
  • Contractor to lodge a extension of time using general conditions (11.5 claims for an extension of time in SCC as a reference)
  • Architect to review scenario and evaluate whether there are suitable grounds to grant a EOT
  • If required get contractor to substantiate the claim in greater detail with reference to items critical to achieving PC
  • Important for contractor to submit regular updated programmes
  • Discuss critical path
  • Discuss with Principal
  • Confirm any extension of time in writing
  • Use NZIA proforma

What is the process for an extension of time request /claim?
Contractor lodges Notice of Delay (NOD) i.e. caused by ‘inclement weather’ or variation has ‘time implications’ or has resulted in ‘concurrent delays’

Extension of Time (EOT)
NZIA SCC 2016; 11.0 ‘Time for Completing the Contract Works.’ (5 Working Days Contractor to apply for EOT + 10 Working Days for Architect to respond).
NZS 3910; 10.0 ‘Time for Completion’
(20 Working Days for Contractor to submit EOT +20 Days Engineer to respond).

101
Q

What is acceleration and under what conditions could the contractor claim them?

A

What is acceleration and under what conditions could the contractor claim them?
Refer to NZS3910:2013 General Conditions 10.3.6
i.e. likely if strict opening date (Hotel or public event).
“Acceleration – Whenever the Contractor may be entitled to an extension of time, then in lieu of granting a time extension for all or part of the delay, the Engineer, following consultation with the Contractor, may require the Contractor to, (if practicable in the reasonable opinion of the Engineer), overcome all or part of the delay by applying additional resources, working longer hours or in whatever manner is required, at a cost to be determined as a Variation.”

102
Q

Is it acceptable to provide incentives to a contractor to complete the project on time?

A

Yes - NZIA SCC 2016 Clause 14.11.1 ‘Bonus for Early Competition.’ (Clause 14.10 Liquidated Damages).
NZS3910 Clause 10.6 ‘Bonus for early completion.’
(Clause 10.5 Damages for late completion
).

103
Q

What typically needs to be collated at the time of PC?

A

Practical Completion Certificate
Defect Liability Certificate
Warranties/Guarantees
As-built documents
Operation & Maintenance Manuals
Consent Compliance (CPU/CCC preferably)

104
Q

Can your client occupy before PC? What about before CCC?

A

NZIA SCC 2016 Clause 12.4 ‘Early Occupancy’
NZS3910 Clause 10.7 ‘Occupation by the Principal’

Residential - not recommended. Principal must have correct insurances in place, and agreement with Contractor regarding H&S, strategy to complete defective works period and ‘record’ the Contractor’s scope of works (i.e. photo evidence recommended as potential for accidental damage by Principal).
Commercial - only if ‘Certificate of Public Use’ granted by Council.

105
Q

Who applies for and who pays for a CCC?

A

Principal – Contractor on their behalf

106
Q

Can you get a CCC for separable portions?

A

Yes - but only if Building Consents have been staged. i.e. foundations in groundwork season or demolition, then fast-track build.

Example;
“A household unit being built specifically for sale cannot normally be transferred without a code compliance certificate. However, the owner or builder can stage the [building] consents so that a code compliance certificate can be obtained for each unit.”

107
Q

What is on the final payment schedule?

A

Same as other paymernt claims but have to note “final payment claim” and that due in 45 days

108
Q

What to do if you notice the works are not being built in accordance with the contract documents?

A

Communicate with both the client and contractor

Refer to contract.
The contractor must complete the works to the architects satisfaction

109
Q

How are deposits treated in 3910 and SCC (if contractor asks for material deposit)

A

3910 notes that Schedule 14 (offsite goods) cannot be used for deposits.

No comments about this in SCC

110
Q

How do you assess how many days for Extension of Time?

A

Based on contract - often contractor will provide how many days they need.

111
Q

When may expert witnessing be needed?

A

In an arbitration setting when the Arbitrator needs to become fully familiar with the problem

112
Q

What contract should you use as an expert witness?

A

AAS - refer PN 3.119

113
Q

How do you enforce a contract?

A

Prepare adequate Contract Docs
Administer according to conditions
Keep accurate records
Be clear on your and your clients responsibilities
Act promptly in consultation with client and client legal advisers
CONFRONT PROBLEMS EARLY

114
Q

What is the difference between a liquidator and a reciver?

A

Receivers are commonly appointed by debenture holders such as banks.

Receivers in these circumstances:
* Fight to get their client’s money back
* Pay themselves, any outstanding wages, holiday pay, GST, PAYE
* Pay debenture holders
* Move out

Liquidators are:
* Appointed by the High Court
* Divide what is left of the company after the receiver has taken its share
* Sell assets
* Pay rest of creditors according to rank

115
Q

What if you are not comfortable in a receivership situation?

A

Advice principal that you feel uncomfortable dealing with these matters and cannot continue as administrator. Legal advice should be sought

Section 16 of SCC