PRINCE2 - Practitioner 1 Flashcards
The Chief Executive Officer (CEO) of the record company requires the cost-benefit analysis of
every project to be recorded in a document called a ‘project rationale’. The executive is
preparing the draft ‘project rationale’ as part of the pre-project phase.
Which principle is being applied, and why?
A. ‘Continued business justification’, because the justification for starting the project needs
to be recorded in some form of a business case
B. ‘Continued business justification’, because it is the executive who drafts the outline
business case at the beginning of a project
C. ‘Learn from experience’, because it is important to consider lessons from previous
projects at the beginning of a new project
D. ‘Learn from experience’, because the project management team should learn from more
experienced corporate management
A. Correct. For all projects, PRINCE2 requires a justifiable
reason for starting the project, which must be recorded.
The format and formality of documentation may vary,
depending on organizational standards, needs and
circumstances. Ref 3.1
B. Incorrect. The principle being applied is ‘continued business
justification’. It is true that the executive may draft the outline
business case, however this does not explain why ‘continued
business justification’ is being applied in this situation. Ref 3.1,
14.4.4
C. Incorrect. The principle being applied is not ‘learn from
experience’. In the situation given, there is no description of a
lesson having been learnt from the current project or outside.
Ref 3.1, 3.2
D. Incorrect. The project should be aligned with the
commissioning organization’s strategy, and the project
management team members are expected to follow the
guidelines set by their corporate management. However, the
‘learn from experience’ principle is not being applied in this
situation as there is no description of a lesson having been
learnt from the current project, or outside. Ref 3.1
During the initiation stage, the Vice President stated that attendance at launch events held
on Monday evenings is low, and on previous projects this had resulted in lower album sales.
As a result, the launch event for this album will be held later in the week.
Which principle is being applied, and why?
A. ‘Continued business justification’, because there is sufficient reason to start this project
B. ‘Continued business justification’, because the project’s justification should remain
unchanged
C. ‘Learn from experience’, because project teams should learn from what occurred on
similar projects
D. ‘Learn from experience’, because the project should continue to learn from its own
experiences
A. Incorrect. The situation describes learning from the
experience of a similar launch event, and is not related to the
‘continued business justification’ principle. The ‘continued
business justification’ principle aims to ensure that the project
remains aligned to the benefits being sought that contribute to
the business objectives. Ref 3.2, 3.1
B. Incorrect. The situation describes learning from the
experience of a similar launch event, and is not related to the
‘continued business justification’ principle. The ‘continued
business justification’ principle aims to ensure that the project
remains aligned to the benefits being sought that contribute to
the business objectives. Ref 3.2, 3.1
C. Correct. When starting a project, previous or similar
projects should be reviewed to see if lessons can be
applied. It is the responsibility of everyone involved with
the project to look for lessons rather than wait for
someone else to provide them. The project manager
should communicate with the events coordinator to find
out more about the timing of the previous event. Ref 3.2
D. Incorrect. The project is in the initiation stage and so this is
learning from experience at the start of a project, not learning
as the project progresses. As the project moves into the
management stages after initiation the project should
continue to learn. Lessons should be included in relevant
reports and reviews. The goal is to seek opportunities to
implement improvements during the life of the project. Ref 3.2
Towards the end of stage 2, the project manager realized that not all of the ‘recorded sample
songs’ would be completed before the end of the stage. The project manager decided to
move the remaining work to stage 3. This enabled the project manager to report that stage 2
was completed within time tolerance.
Is this an appropriate application of the ‘manage by stages’ principle, and why?
A. Yes, because moving the work to stage 3 avoided an exception situation in stage 2
B. Yes, because stage 3 is not the final stage so work can be moved from stage 2
C. No, because the project board should assess project viability on completion of work
planned for stage 2
D. No, because work in stage 3 should start while work planned for stage 2 is being
completed
A. Incorrect. Application of the ‘manage by stages’ principle
provides review and decision points for the project board at
defined intervals. The project manager cannot decide to move
work from stage 2 to stage 3, as this is outside the project
manager’s delegated authority. This is also against the
principle of ‘manage by exception’, as exceeding time
tolerance for the stage must be reported. Ref 3.4, 3.5
B. Incorrect. Application of the ‘manage by stages’ principle
provides review and decision points for the project board at
defined intervals, rather than letting the project run on in an
uncontrolled way. The project board authorizes one stage of
the project at a time against a stage plan. Although the project
manager has discretion to make adjustments, this would not
include amending a stage baseline, such as moving work from
one stage to another. Ref 3.4
C. Correct. Application of the ‘manage by stages’ principle
provides review and decision points for the project board
at defined intervals, rather than letting the project run on
in an uncontrolled way. This is why the planned work that
remains in stage 2 cannot be moved to stage 3, without
the approval of an exception. Ref 3.4
D. Incorrect. Application of the ‘manage by stages’ principle
provides review and decision points for the project board at
defined intervals. The project board authorizes one stage of
the project at a time against a stage plan. Although the project
manager has discretion to make adjustments, this would not
include amending a stage baseline, such as moving work from
one stage to another. Delivery steps often overlap but stages
cannot. Ref 3.4, 9.3.1.1
The executive has appointed the company’s finance manager to provide business assurance,
to monitor whether the album sales will exceed the production costs as the project
progresses through each stage.
How well does this apply the ‘manage by exception’ principle, and why?
A. It applies it well, because a PRINCE2 project should structure the project into
management stages to enable approval on a stage-by-stage basis
B. It applies it well, because the executive needs to be confident that controls and
tolerances are being implemented effectively
C. It applies it poorly, because roles should be combined in a small project as long as there
is no conflict of interest
D. It applies it poorly, because a PRINCE2 project should focus on delivering quality outputs
rather than on the work required to deliver the products
A. Incorrect. PRINCE2 breaks the project down into discrete,
sequential sections, called management stages, as part of the
‘manage by stages’ principle. However, this does not explain
why the project assurance role is required as part of the
‘manage by exception’ principle. Ref 3.4
B. Correct. As part of the ‘manage by exception’ principle,
an assurance mechanism should be put in place so that
each management layer can be confident that controls are
effective. Ref 3.5
C. Incorrect. As part of the ‘tailor to suit the project’ principle,
roles may be combined or split, provided that accountability is
maintained and there are no conflicts of interest, however this
is not mandatory. Ref 4.3.1
D. Incorrect. As part of the ‘focus on products’ principle,
PRINCE2 requires projects to be output-oriented rather than
work-oriented. However, this does not explain why the project
assurance role is required as part of the ‘manage by exception’
principle. Ref 3.6
During the ‘initiating a project’ process, it was decided that the sound quality of the album
should be the same, regardless of the delivery channel used. At the beginning of stage 4, the
project manager agrees this requirement with the team manager responsible for delivering
the album to the different channels.
Which principle is being applied, and why?
A. ‘Manage by stages’, because an output-oriented project should define the products prior
to producing them
B. ‘Manage by stages’, because users are more likely to be satisfied if the products are
agreed at the start of the project
C. ‘Focus on products’, because the work done will contribute to the products being
delivered to the required standards
D. ‘Focus on products’, because the project manager should make key decisions prior to
the start of detailed work
A. Incorrect. The ‘focus on products’ principle requires projects
to be output-oriented, not the principle ‘manage by stages’. Ref
3.6
B. Incorrect. Application of the ‘focus on products’ principle,
not ‘manage by stages’, reduces the risk of user dissatisfaction
by ensuring that there is agreement about what will be
produced. Ref 3.6
C. Correct. Ensuring that the work package includes the
requirements for the product(s) to be delivered is an
application of the ‘focus on products’ principle. This helps
to ensure that the team only carries out work that directly
contributes to the delivery of the desired product(s). Ref
3.6
D. Incorrect. Application of the ‘manage by stages’ principle,
not ‘focus on products’, ensures that key decisions are made
prior to commencing detailed work. Ref 3.4, 3.6
During stage 3, the Music Album Project board consists of the Vice President as the executive
and senior user, with no senior supplier.
Is this an appropriate application of the ‘defined roles and responsibilities’ principle, and
why?
A. Yes, because the Vice President can represent all three primary stakeholder interests
B. Yes, because appointing the Vice President provides an explicit project management
team structure
C. No, because the Vice President cannot judge if the project can be feasibly delivered by all
supply streams
D. No, because having defined roles should help each person to answer ‘what is expected
of me?
A. Incorrect. The Vice President cannot represent all suppliers,
especially as some are from third-party organizations. All three
stakeholder interests must be represented - two out of three
stakeholder interests are not enough. Ref 3.3
B. Incorrect. To be successful, projects must have an explicit
project management team structure. However, this requires all
three stakeholder interests (business, user and supplier) to be
represented, which would not be the case if the project board
has no supplier representation. Ref 3.3
C. Correct. The Vice President cannot represent all
suppliers, especially as some are from third-party
organizations. All three stakeholder interests must be
represented - two out of three stakeholder interests are
not enough. Ref 3.3
D. Incorrect. Having roles and responsibilities defined helps
each person to know what is expected of them. However, this
does not explain why having no senior supplier on the project
board is not appropriate. Ref 3.3
The work package to create the ‘artwork’ will commence in stage 3. The graphic design
company uses their own development method to deliver products. They have appointed
their Graphic Designer as the team manager to complete this work package. The project
manager will review the appointment at the end of the stage.
Which principle is being applied by the review, and why?
A. ‘Manage by stages’, because the project manager reviews the contents of the project
initiation documentation when planning stage 4
B. ‘Manage by stages’, because the project manager reviews the status of stage 3 products
at the end of the stage
C. ‘Manage by exception’, because the project board delegates the authority to the project
manager on a stage-by-stage basis
D. ‘Manage by exception’, because the team manager’s performance should be reviewed
before authorizing the next work package
A. Correct. Applying the ‘manage by stages’ principle
ensures that key decisions are made prior to the detailed
work needed to implement them. For that reason, the
project manager reviews the components of the project
initiation documentation as part of planning the next
stage. Ref 3.4, 19.4.1, A.20.2
B. Incorrect. The principle being applied is ‘manage by stages’.
However, when reviewing the status of stage 3, the project
manager is not required to wait until the end of it. Using the
‘controlling a stage’ process, the project manager reviews the
stage status throughout the stage. Ref 3.4, 17.4.4
C. Incorrect. The principle being applied is ‘manage by stages’,
not ‘manage by exception’. Although it is true that the project
board delegates the authority to the project manager on a
stage
-by
-stage basis, the situation described is not concerned
with delegation or deviation from any project objective. Ref
3.4, 3.5
D. Incorrect. The principle being applied is ‘manage by stages’,
not ‘manage by exception’. The project manager reviews the
team’s performance as part of the ‘report management stage
end’ activity and is expected to assess the team manager’s
performance before delegating the authority to work on the
next relevant work package, as part of applying the ‘learn from
experience’ principle. However, the situation described is not
concerned with delegation or deviation of any project
objective. Ref 3.2, 3.4, 3.5, 19.4.4
The project is in the initiation stage. The Vice President requests that management products
be produced in the form of slides, to be presented at project board meetings. This is in line
with company policy.
Is this an appropriate application of the ‘tailor to suit the project’ principle, and why?
A. Yes, because the controls applied need to be appropriate to the organization’s
governance
B. Yes, because this provides control points during the project for decisions to be made
C. No, because producing slides takes more effort than producing written documents
D. No, because applying the ‘manage by exception’ principle removes the need for
meetings
A. Correct. This is a correct application of the ‘tailor to suit
the project’ principle. The purpose of tailoring is to ensure
that the project controls are appropriate to the project’s
scale, complexity, importance, team capability and risk.
Ref 3.7
B. Incorrect. This is a correct application of the ‘tailor to suit the
project’ principle. However, it is the application of the ‘manage
by stages’ principle that provides review and decision points,
giving the project board the opportunity to assess the project’s
viability at defined intervals, rather than let it run on in an
uncontrolled manner. Ref 3.4
C. Incorrect. This is a correct application of the ‘tailor to suit the
project’ principle. Tailoring requires the project board and the
project manager to make pro
-active choices and decisions on
how PRINCE2 will be applied. When tailoring PRINCE2, it is
important to remember that effective project management
requires information (not necessarily documents). Therefore, it
is appropriate to produce slides, irrespective of the effort
involved. Ref 3.7
D. Incorrect. This is a correct application of the ‘tailor to suit
the project’ principle as management products should be
tailored to the requirements and environment of each project
and can be in the form of slides. Also, the ‘manage by
exception’ principle does not remove the need for meetings,
although it does provide for efficient use of senior
management time. Ref 3.5, App A
Here are three actions related to managing business justification for the Music Album Project.
Which role (A-F) should be responsible for each action?
Choose only ONE role for each action. Each role can be used once, more than once, or not at all.
- Ensure that the law firm that is working on the contract
between the singer and the record company will make
a profit - At a benefits review of the album launch, state whether
the album sales met the targets specified in the
business case - Monitor monthly spend against the agreed budget on
behalf of the record company
A. Executive
B. Senior user
C. Senior supplier
D. Project manager
E. Team manager
F. Project assurance
9)
C 2.1.1b C. Correct. The law firm is an external supplier and
therefore the senior supplier should be accountable for
the supplier’s business case. Ref tab 6.1
A, B, D, E, F. Incorrect. Ref tab 6.1
10)
B 2.1.1b B. Correct. At benefit reviews the senior user should
provide statements of actual benefit achievements
compared to forecast benefits. Ref tab 6.1
A, C, D, E, F. Incorrect. Ref tab 6.1
11)
F 2.1.1b F. Correct. Project assurance should monitor project
finance on behalf of corporate, programme management
or the customer. Ref tab 6.1
A, B, C, D, E. Incorrect. Ref tab 6.1
The Music Album Project is part of a programme to contract new singers. The ‘artwork’ is
being produced by an external graphic designer. The graphic designer’s profit has been
documented in the record company’s business case.
Is this appropriate, and why?
A. Yes, because project costs should be recorded as part of the project’s business case
B. Yes, because the project’s business case should record any benefits for the project’s
stakeholder
C. No, because the project, as part of a programme, should be provided with the approach
to the business case
D. No, because the graphic designer’s business justification should not be part of the
project’s business case
A. Incorrect. The customer’s business case should include all
costs. However, the graphic designer’s business justification
should not be part of the project’s business case. Ref A.2.2,
6.3.3
B. Incorrect. The customer’s business case should include the
benefits to the customer, but the graphic designer’s business
justification should not be part of the project’s business case.
Ref A.2.2, 6.3.3
C. Incorrect. It is true that where the project is part of the
programme, the programme will typically define both the
approach to business case development and provide an
outline business case for the project. However, this does not
explain why the supplier should have a separate business
case. Ref 6.3.4
D. Correct. The project’s business case for a customer’s
project is separate from a supplier’s business justification
for bidding for, and working on that customer’s project.
The customer needs to ensure that their project is viable
and risks are acceptable, bearing in mind the suppliers
chosen. A supplier would have to ensure that they will
benefit from the work they undertake on the project. Ref
6.3.3
The project is in the initiation stage. When negotiating with the record company on behalf of
the singer, the singer’s agent stated that this type of music represents 3% of the total music
market. The singer’s agent understands the music industry and has been asked to specify
how much profit the record company should expect to make from the sales of this album.
Is this appropriate, and why?
A. Yes, because the agent has the skills required to be responsible for forecasting the
album sales
B. Yes, because the agent identified the size of the market for this type of music during the
initiation stage
C. No, because the senior user should be responsible for the development of the detailed
business case
D. No, because the senior user should be accountable for specifying the benefits which
justify the project
A. Incorrect. Even though the singer’s agent has experience of
the market and skills to forecast sales, it is the senior user who
specifies the benefits for the project. Ref tab 6.1
B. Incorrect. Even though the singer’s agent understands the
size of the market, it is the senior user who specifies the
benefits for the project. Ref tab 6.1
C. Incorrect. The project manager is responsible for the
development of the business case, but the benefits are
specified by the senior user. Ref tab 6.1, C.5
D. Correct. The singer’s agent is an external supplier who
cannot be responsible for the benefits in the record company’s
business case. The senior user is accountable for specifying the
benefits. Ref tab 6.1, C.3
ORGANIZATION
Here are three roles relating to the Music Album Project.
Which individual (A-F) would be most appropriate for each role?
Choose only ONE individual for each role. Each individual can be used once, more than once, or
not at all.
14. Delegated user assurance
15. Project manager
16. Project support
A. Vice President
B. Production Manager
C. Production Assistant
D. Marketing Manager
E. Music lawyer
F. Events Organize
14 D 2.2.1c D. Correct. The Marketing Department will use the product by
marketing the album. The Marketing Manager is the right
person to undertake the user assurance role by assessing
whether the album meets the user’s needs. Ref C.7.1, 7.2.1.5
A, B, C, E, F. Incorrect. Ref 7.1, C.5, C.7.1, C.9.1
15 B 2.2.1c B. Correct. The Production Manager has experience of
managing album projects and, of the options that are
provided, would be most appropriate for this role. Ref C.5
A, C, D, E, F. Incorrect. Ref 7.1, C.5, C.7.1, C.9.1
16 C 2.2.1c C. Correct. Provision of administrative support is one
responsibility of project support. Ref C.9.1
A, B, D, E, F. Incorrect. Ref 7.1, C.5, C.7.1, C.9.1
As a result of previous lessons, this recommendation has been made: “If an executive is
appointed who does not have an understanding of PRINCE2, someone with experience of
applying PRINCE2 should undertake business assurance.” The Recording Studio Manager has
therefore been appointed as business assurance for stage 2.
Is this appropriate, and why?
A. Yes, because the Recording Studio Manager is responsible for the delivery of the
‘recorded album’
B. Yes, because the Recording Studio Manager has the experience required to deliver the
‘recorded album’
C. No, because the Recording Studio Manager’s business justification may conflict with the
interests of the executive
D. No, because the Recording Studio Manager will not be available throughout the project
lifecycle
A. Incorrect. The Recording Studio Manager is responsible for
the delivery of the recorded album. However, business
assurance should be undertaken by someone from the
customer organization, to avoid a conflict of interest. Ref
7.2.1.10
B. Incorrect. Although the Recording Studio Manager has the
required knowledge and experience, the business assurance
role should be undertaken by someone from the customer
organization. The Recording Studio Manager is a supplier and
therefore this would be a conflict of interest. Ref 7.2.1.10
C. Correct. There may be conflict between customer and
supplier business justification. The business assurance
role should be undertaken by someone from the customer
organization as the Recording Studio Manager is a
supplier. Ref 7.2.1.10
D. Incorrect. Ideally, those with project assurance
responsibilities should be able to carry out the role throughout
the project, although it is possible for someone to provide
project assurance during a specific stage. This is not the reason
why it is not appropriate for the Recording Studio Manager to
undertake the role. Business assurance should be undertaken
by someone from the customer organization to avoid a conflict
of interest. Ref 7.2.1.10, C.7.2
The Contracts Manager has been appointed as the project manager for the Music Album
Project. In a previous job, the Contracts Manager worked as a graphic designer and, when
planning for stage 3, decided to also take on the role of team manager for the ‘artwork’
production.
Is this an appropriate application of the ‘organization’ theme, and why?
A. Yes, because the project manager can take on a team manager role if they have the
specialist skills
B. Yes, because in a commercial environment the project manager should understand
supplier contractual obligations
C. No, because the team manager should come from the graphic design company to avoid
conflicts of interest.
D. No, because the project manager should plan roles during the ‘starting up a project’
process
A. Correct. The project manager can always choose to be
the team manager. In a commercial environment, the
supplier’s staff may fulfil a team manager role on the
project - this is not mandatory and can introduce a conflict
of interest. Ref 7.2.1.8, 7.3.4
B. Incorrect. It is important that the project manager has a
good understanding of the supplier contractual obligations in a
commercial environment. However, this does not explain why
the project manager and team manager roles may be
combined in the situation described. Ref. 7.3.4
C. Incorrect. The graphic design company is a third-party
supplier and there could be a reporting line between the team
manager and the senior supplier. This link would need to be
understood in order to avoid conflicts of interest. However,
appointing the team manager from the third-party supplier
would introduce the conflict of interest, not avoid it. Ref 7.2.1.8
D. Incorrect. The project manager should plan roles during the
‘starting up a project’ process. However, this does not explain
why the project manager and team manager roles may be
combined in the situation described. Ref 7.2.1.8, 14.4.3
QUALITY
Here are three items of information that will be included in the project product description for
the ‘album ready for launch’.
Under which heading (A-F) should they be recorded?
Choose only ONE heading for each item of information. Each heading can be used once, more
than once, or not at all.
19. ‘Recorded album’, ‘registered artwork’ and ‘launch
event plan’
20. The singer will give final approval of the ‘artwork’
21. The ‘artwork’ must comply completely with relevant
equality legislation
A. Purpose
B. Composition
C. Development skills
required
D. Project-level quality
tolerances
E. Acceptance method
F. Acceptance responsibilities
19 B 2.3.1a B. Correct. The ‘composition’ heading includes a
description of the major products and/or outcomes to be
delivered by the project. Ref A.21.2
A, C, D, E, F. Incorrect. Ref A.21.2
20 F 2.3.1a F. Correct. The ‘acceptance responsibilities’ heading
defines who will be responsible for confirming acceptance.
PRINCE2 uses the term ‘acceptance’ to describe the
ultimate approval of the project’s product. Ref A.21.2,
8.3.17
A, B, C, D, E. Incorrect. Ref A.21.2
21 D 2.3.1a D. Correct. The ‘project-level quality tolerances’ heading
specifies any tolerances that may apply for the acceptance
criteria. In this case the tolerance is zero. Ref A.21.2
A, B, C, E, F. Incorrect. Ref A.21.2
The record company must comply with music industry regulations when producing the
‘artwork’.
Which action should the project manager take, and why?
A. Record the need to meet this requirement during stage 2, because the ‘artwork’ will be
delivered to the specified quality criteria during stage 3
B. Record the need to meet this requirement during stage 2, because the product
description for the ‘artwork’ will specify the required quality criteria
C. Record the requirement in the quality management approach, because compliance with
external standards should be addressed when determining the approach to quality
D. Record the requirement in the quality management approach, because independent
quality assurance needs to be planned at the beginning of the project
A. Incorrect. The project may be subject to external quality
standards, for example when the project is within a regulated
environment. These various circumstances must be addressed
when determining the project’s approach to quality. It would
be too late to consider this requirement during stage 2. Ref
8.3.2, A.20.2
B. Incorrect. The project may be subject to external quality
standards, for example when the project is within a regulated
environment. These various circumstances must be addressed
when determining the project’s approach to quality. It would
be too late to consider this requirement during stage 2. Ref
8.3.2, A.20.2
C. Correct. The project may be subject to external quality
standards, for example when the project is within a
regulated environment. These various circumstances must
be addressed when determining the project’s approach to
quality. Ref 8.3.2, A.20.2
D. Incorrect. Quality assurance is defined in the quality
management approach. However, this is not why the quality
standards need to be identified in the quality management
approach. Ref A.20.2
During stage 2, the ‘recorded sample songs’ will be delivered and made available to
members of focus groups. Feedback from the focus groups will be used to improve the
‘recorded album’. The Production Manager has asked the singer to assess the recordings of
the sample songs. This has been planned as part of the quality management approach.
Why is this an appropriate action?
A. The quality that the singer expects from the ‘recorded sample songs’ needs to be
documented
B. The quality checking of the ‘recorded sample songs’ needs to be aligned with the
incremental delivery approach
C. The acceptance criteria for the ‘recorded sample songs’ need to be prioritized by the
singer
D. The acceptance criteria for the ‘recorded album’ could change as a result of recording
the sample songs
A. Incorrect. The customer’s quality expectations should be
agreed early in the ‘starting up a project’ process. The
expectations are captured in discussions with the customer
and then refined for inclusion in the project product
description, rather than the quality management approach.
The singer is not the customer, even though he is representing
the customer during the quality checking. Ref 8.3.6
B. Correct. It is important that the approach to managing
quality works with, and supports, the chosen delivery
approach, and not against it. For example, when using an
agile approach, the high frequency of quality checking (in
the form of reviews, demos or tests) may have a
significant impact on how a project is planned. This will
affect the incremental delivery of the project’s products
and how they are released. Ref 8.3.3
C. Incorrect. It is true that the acceptance criteria need to be
prioritized by the customer. However, the singer is not the
customer and this also does not explain why the quality
management approach needs to take into account the
incremental delivery approach. Ref 8.3.8, 8.3.3
D. Incorrect. It is true that acceptance criteria could evolve as a
result of the initial sample recordings. However, this does not
explain why the approach to quality needs to work with and
support the chosen delivery approach. Ref 8.3.9, 8.3.3
PLANS
Here are three statements that are considered when planning the Music Album Project.
Which step (A-F) in PRINCE2’s recommended approach to planning do they apply to?
Choose only ONE step for each statement. Each step can be used once, more than once, or not at
all.
24. The dependency between ‘recorded sample songs’ and
‘signed contract’ should first be identified
25. The Music Album Project will have four stages
26. A workshop will be held to identify the components
that will make up the ‘recorded album’
A. Designing a plan
B. Defining and analysing the
products.
C. Identifying activities and
dependencies
D. Preparing estimates
E. Preparing a schedule
F. Documenting a plan
B. Correct. As part of PRINCE2’s recommended approach to
defining and analysing the products, a product flow
diagram is created to identify the sequence in which the
products of the plan will be developed. Ref 9.3.1.2
A, C, D, E, F. Incorrect. Ref 9.3.1.1
-
7
Q
A Syllabus Ref Rationale
25
A 2.4.1c A. Correct. One of the decisions made during the
‘designing a plan’ activity is about the number of
management stages in the project. Ref 9.3.1.1
B, C, D, E, F. Incorrect. Ref 9.3.1.1
-
7
26
B 2.4.1c B. Correct. As part of PRINCE2’s recommended approach to
defining and analysing the products, a product breakdown
structure is created. This is when an approach such as
brainstorming is chosen to identify products. Ref 9.3.1.2
A, C, D, E, F. Incorrect. Ref 9.3.1.1
-
7