#1 - Mock Test Flashcards

1
Q

Which statement about controls is Correct?

A highlight report is an event driven control
An exception report is a time-driven control
A Daily log is an event driven control
A checkpoint report is a time-driven control

A

A checkpoint report is a time driven control

Explanation: an objective of the ‘controlling a stage’ process is to ensure attention is focused on delivery of the stage products. Any movement away from the direction of products agreed at the start of the stage is monitored to avoid uncontrolled change and loss of coups. The ‘controlling a stage’ describes the work of the project manager in handling day-to-day management of the stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Identify the missing words in the following sentence. “Any change to the products agreed at the start of a stage is monitored as part of the [ ? ] process, on a day-to-day basis.
Directing a project
Controlling a stage
Managing a stage boundary
Closing a project

A

Controlling a stage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which two statements about the ‘continue business justification’ principle are CORRECT?

  1. The business justification for a project should be documented
  2. The Project manager should be responsible for the business justification.
  3. A project must be stopped if the business justification changes.
  4. compulsory projects still require business justification.
A

1 and 4

Even compulsory projects should be supported by a business justification that demonstrates value for money

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When is it confirmed whether a project’s objectives have been achieved?

  1. During the ‘closing a project process’
  2. During the final end stage assessment
  3. During the controlling a stage process
  4. During the managing product delivery process
A
  1. During the ‘closing a project’ process

The purpose of the ‘closing a project’ process is to provide a fixed point at which acceptance of the project product is confirmed and to recognize that objectives set out in the original project initiation documentation have been achieved, or that the project has nothing more to contribute.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which is a purpose of the ‘controlling a stage’ process?

1.To agree, perform and deliver project work
2. to draft a plan for the next stage.
3. To agree tolerances for the stage
4. To take action so that the stage remains within tolerances.

A
  1. To take action so that the stage remains within tolerances.

The purpose of the ‘controlling a stage’ process is to assign work, monitor it, deal with issues, report progress and take corrective action to ensure that the stage remains within tolerances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

In which situation might the ‘controlling a stage’ process be used?

  1. To manage a long initiation stage of a complex project
  2. To manage the activities of a complex Programme
  3. To organize support activities following the handover of products to operations.
  4. To create an exception plan to replace the current stage plan.
A
  1. To manage a long initiation stage of a complex project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which is a step in PRINCE2’s ‘initiating a project’ process?

  1. to ensure that there is authority to initiate the project.
  2. To prepare the plans for the subsequent delivery stages.
  3. To summarize how the organizations project management method will be tailored for the project.
  4. To request authority from Programme, corporate management or the customer to deliver the project.
A
  1. To summarize how the organizations project managment method will be tailored for the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If a work package is forecast to exceed its tolerances, how should a team manager inform the project manager?

  1. By submitting an exception report
  2. By submitting an exception plan
  3. By raising an issue
  4. By raising a risk
A
  1. By raising an issue.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which is a minimum requirement for applying the quality theme?

  1. To define the use and format of quality records.
  2. to define the projects approach to quality assurance.
  3. To define proxy measures that indicate achievable benefits
  4. To define the projects approach to project assurance.
A
  1. To define the projects approach to project assurance.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the purpose of the quality theme?

  1. To establish the mechanisms to judge whether a project is desireable and achievable.
  2. To look for ways to improve the effectiveness of management of the project.
  3. To control uncertainty to improve the ability of the project to succeed.
  4. To establish mechanisms to control any unacceptable deviation .
A
  1. To look for ways to improve the effectiveness of management of the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which statement about a useful tool for recording when reviewing progress is Incorrect?

A Highlight report is an event-driven control
An exception report is a time-driven control
A daily log is an event-driven control
A Checkpoint report is a time-driven control

A

A daily log is an event driven control is a useful tool for recording actions when reviewing progress, but it is not defined as a PRINCE2 control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which statement correctly describes project assurance and quality assurance?
A) Project assurance provides assurance to the project stakeholders whereas quality assurance provides assurance to the wider corporate Programme or customer organization.
B) They are both the responsibility of the project board, but project assurance may be delegated.
C) They are both independent of the project management team
D)Project assurance and quality assurance are both the responsibility of corporate Programme management or the customer.

A

Project assurance provides assurance to the project stakeholders whereas quality assurance provides assurance to the wider corporate, Programme or customer organization

Quality assurance provides assurance to corporate, Programme management or customer on the projects compliance with relevant corporate Programme management or customer standards and policies. Project assurance provides assurance to the projects stakeholders that he project is being conducted properly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who is responsible for approving any tailoring of work packages?
A) Executive
B) Project Manager
C) Team Manager
D) Project support

A

A) Executive

In the PRINCE2 methodology, the Managing a Stage Boundary process focuses on reviewing the current stage’s performance and preparing for the next stage. One of the key activities in this process is to agree upon tolerances for the stage.

During the Managing a Stage Boundary process, the project manager, along with relevant stakeholders, reviews the completed stage, assesses the project’s current status, and identifies any deviations or potential issues. The project manager then proposes tolerances for the next stage, which define the acceptable limits or boundaries within which the project can operate.

Once the tolerances for the stage are agreed upon in the Managing a Stage Boundary process, they are then approved in the Directing a Project process. The Directing a Project process is responsible for providing overall direction and governance to the project.

In this process, the project board, which is accountable for the project’s success, reviews and approves various management products, including the tolerances proposed for the next stage. The project board ensures that the proposed tolerances align with the project’s objectives, risk appetite, and strategic considerations.

Therefore, option C correctly identifies that agreeing tolerances for the stage is created in the Managing a Stage Boundary process and approved in the Directing a Project process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which process provides accurate progress information to the project manager at an agreed frequency to ensure that expectations are managed?

A) Managing product delivery
B)Initiating a project
C)Controlling a stage
D) Directing a Project

A

A) Managing product delivery

In the PRINCE2 methodology, the Managing a Stage Boundary process focuses on reviewing the current stage’s performance and preparing for the next stage. One of the key activities in this process is to agree upon tolerances for the stage.

During the Managing a Stage Boundary process, the project manager, along with relevant stakeholders, reviews the completed stage, assesses the project’s current status, and identifies any deviations or potential issues. The project manager then proposes tolerances for the next stage, which define the acceptable limits or boundaries within which the project can operate.

Once the tolerances for the stage are agreed upon in the Managing a Stage Boundary process, they are then approved in the Directing a Project process. The Directing a Project process is responsible for providing overall direction and governance to the project.

In this process, the project board, which is accountable for the project’s success, reviews and approves various management products, including the tolerances proposed for the next stage. The project board ensures that the proposed tolerances align with the project’s objectives, risk appetite, and strategic considerations.

Therefore, option C correctly identifies that agreeing tolerances for the stage is created in the Managing a Stage Boundary process and approved in the Directing a Project process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which is the responsibility of project assurance?
A) To ensure an acceptable solution is being developed
B) To prepare a team plan and agree it with the project manager
C) To maintain project files according to document control procedures
D) To approve or reject requests for change within the delegated limits

A

A) To ensure an acceptable solution is being developed In the PRINCE2 methodology, the Managing a Stage Boundary process focuses on reviewing the current stage’s performance and preparing for the next stage. One of the key activities in this process is to agree upon tolerances for the stage.

During the Managing a Stage Boundary process, the project manager, along with relevant stakeholders, reviews the completed stage, assesses the project’s current status, and identifies any deviations or potential issues. The project manager then proposes tolerances for the next stage, which define the acceptable limits or boundaries within which the project can operate.

Once the tolerances for the stage are agreed upon in the Managing a Stage Boundary process, they are then approved in the Directing a Project process. The Directing a Project process is responsible for providing overall direction and governance to the project.

In this process, the project board, which is accountable for the project’s success, reviews and approves various management products, including the tolerances proposed for the next stage. The project board ensures that the proposed tolerances align with the project’s objectives, risk appetite, and strategic considerations.

Therefore, option C correctly identifies that agreeing tolerances for the stage is created in the Managing a Stage Boundary process and approved in the Directing a Project process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What takes place and is performed after the project?

A) The post-project benefits reviews
B)Ownership of the projects products is transferred to the customer
C)An end stage report is prepared for the final stage
D) The project closure notification is reviewed and approved

A

A) The post project benefits reviews are performed

In the PRINCE2 methodology, the Managing a Stage Boundary process focuses on reviewing the current stage’s performance and preparing for the next stage. One of the key activities in this process is to agree upon tolerances for the stage.

During the Managing a Stage Boundary process, the project manager, along with relevant stakeholders, reviews the completed stage, assesses the project’s current status, and identifies any deviations or potential issues. The project manager then proposes tolerances for the next stage, which define the acceptable limits or boundaries within which the project can operate.

Once the tolerances for the stage are agreed upon in the Managing a Stage Boundary process, they are then approved in the Directing a Project process. The Directing a Project process is responsible for providing overall direction and governance to the project.

In this process, the project board, which is accountable for the project’s success, reviews and approves various management products, including the tolerances proposed for the next stage. The project board ensures that the proposed tolerances align with the project’s objectives, risk appetite, and strategic considerations.

Therefore, option C correctly identifies that agreeing tolerances for the stage is created in the Managing a Stage Boundary process and approved in the Directing a Project process.

17
Q

Which is an objective of initiating a project process?

A) To understand the resources and costs to deliver the projects products
B) To ensure that there is authority to deliver the projects products
C) To do the minimum to decide whether it is worthwhile initiating the project
D) To create the managment products required to control the project

A

A) To understand the resources and costs to deliver the projects products.

In the PRINCE2 methodology, the Managing a Stage Boundary process focuses on reviewing the current stage’s performance and preparing for the next stage. One of the key activities in this process is to agree upon tolerances for the stage.

During the Managing a Stage Boundary process, the project manager, along with relevant stakeholders, reviews the completed stage, assesses the project’s current status, and identifies any deviations or potential issues. The project manager then proposes tolerances for the next stage, which define the acceptable limits or boundaries within which the project can operate.

Once the tolerances for the stage are agreed upon in the Managing a Stage Boundary process, they are then approved in the Directing a Project process. The Directing a Project process is responsible for providing overall direction and governance to the project.

In this process, the project board, which is accountable for the project’s success, reviews and approves various management products, including the tolerances proposed for the next stage. The project board ensures that the proposed tolerances align with the project’s objectives, risk appetite, and strategic considerations.

Therefore, option C correctly identifies that agreeing tolerances for the stage is created in the Managing a Stage Boundary process and approved in the Directing a Project process.

18
Q

when should the project manager and team manger agree the timing of Checkpoint reports?

A) When a work package is being negotiated?
B) At the frequency agreed in the work package
C) On completion of the quality-checking activities for each product.
D) When reviewing how stage is progressing.

A

A) When a work package is being negotiated

Option1 Correct. When a work package is being negotiated is when the project manager and team manager agree the timing of checkpoint reports. Ref 12.2.2.4, 18.4.1

19
Q

Which statement describes the ‘directing a project’ process?

A) It enables the project board to assure that there is continued business justification?
B) It covers the day-to-day activities of the project manager
C) It ensures there are regular progress meetings
D) It begins on completion of the initiating a project process?

A

A) It enables the project board to assure that there is continued business justification.

Option1 Correct. The ‘directing a project’ process provides a mechanism for the project board to achieve such assurance without being overburdened by project activity. Ref 15.3

20
Q

Which is the the purpose of a quality register?

A) To define the customers quality expectations for the project?
B) To define the quality standards to be applied to a project.
C) To identity the level of quality required for each of the projects products.
D) To summarize the planned quality management activities?

A

To summarize the planned quality management activities

21
Q

What is a project benefit
A) A measurable improvement that is perceived as an advantage by one or more stakeholders
B) The reason for the project
C) The result of the change derived from using the projects outputs
D) The project Specialist products

A

A) A measurable improvement that is perceived as an advantage by one or more stakeholders.

22
Q

Which regular report provides the project board with a summary of stages?

A) Checkpoint report
B) Highlight report
C) Lessons learned
D) Product Status account

A

B) Highlight report

23
Q

Which is an objective of the ‘starting up a project’ process?
A) To obtain approval for the project plan from corporate, program management or customer
B) to prepare the project initiation documentation for authorization to initiate the project.
C) To confirm that there are no known restrictions that would prevent the project from being delivered.
D) To ensure that all team managers understand their responsibilities.

A

C. To confirm there are no known restrictions that would prevent the project from being delivered.

24
Q

Which management product should always be updated when a product fails its quality check?

A

Quality register.

25
Q

what is a task of the ‘defining and analyzing products?’\

A

Create the product flow diagram

26
Q

Which is a purpose of a quality management approach?
A) To define the customers quality expectations for the project
B)To define the quality standards to be applied to a project
C) To identify the level of quality required for each of the projects products

A

B) To define the quality standards to be applied to a project

Which is a purpose of the change theme?

27
Q

Which is a minimum requirement for applying the business case them?

A) To document the responsibility for defining the standards for the business case

B)To appoint a senior user from an area of the business impacted by the project

C) To have the benefits management approach approved by the participants of benefits review

D) To delegate the development of the business justification to the project manager

A

A) To document the responsibility defining the standards of the business case

Option1 Correct. It is a minimum requirement that the roles and responsibilities for the business case and benefits management are defined and documented. Therefore this includes responsibility for defining any standards to which the business case needs to be developed. Ref 6.2, tab 6.1