Pre Outage AOP Review (RQ-I-4741) Flashcards

1
Q

The following conditions exist:
RCS temperature is 348ºF and lowering
RCS Pressure 950 psig and lowering
Containment pressure is rising

Which ONE of the following describes the proper procedural implementation based on these conditions?

A) 2-OHP-4022-017-001, Loss of RHR Shutdown Cooling
B) 2-OHP-4023-E-0, Reactor Trip or SI, then go to 1-OHP-4022-002-015, Mode 4 LOCA
C) 2-OHP-4022-002-015, Mode 4 LOCA
D) 2-OHP-4023-E-0, Reactor Trip or Safety Injection, then go to 2-OHP-4023-E-1, Loss of Reactor or Secondary Coolant.

A

C) 2-OHP-4022-002-015, Mode 4 LOCA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly