BOP Electrical Distribution (RQ-C-4763) Flashcards
1
Q
What is the SDG loading sequence
A
EP UV sensed - Wait 150 seconds
MDS Opens
SDGs start
First SDG to speed closes its breaker
Second SDG synchronizes to first
Breaker to EP closes
2
Q
What loads are the alternate offsite power source (EP) rated to carry
A
One train of ESF equipment in one unit
One train of safe shutdown equipment in the other unit
3
Q
What loads are the SDGs rated to carry
A
1 train of RCS inventory control (ESF loads) in a single unit