Planning the Project Schedule Flashcards

1
Q

Sections of Schedule Management Plan

A

Model Development
Release and Iteration Lengths
Level of Accuracy for Estimates

May also include
org procedure links
process to maintain schedule model
outline control thresholds for sched variance
reporting format and frequency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Tools and Techniques to Define Project Activities

A

Decomposition- get full breakdown of work packages
Rolling Wave Planning- decompose WBS in stages, start early
Meetings
Expert Judgement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Categories of Activities (size)

A

Sm-Med- WMS is brief, low risk, few unknowns. Likely no need for experts for scheduling
Med-Lg- some dependencies, med risk, some degree of rolling wave, may need experts for scheduling
Large- high complexity, high risk, high unknowns, high dependencies, use rolling wave planning, set milestones, use experts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Activity List

A

list of work by phase
helps track schedule, lets team know what to do
includes activity ID, WBS id, name and description of activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Sequence Activities

A

used for timing
Attribute of Activity List
-predecessor activity (ex: seek approval)
-successor activities (ex: print a document)
-leads- allow to start an activity earlier
- lags- delays, causing waits
- imp____ dates- can’t control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Work Instructions

A
attribute of activity list
-resource requirements
-location
level of effort
-discrete (1 person or team)
-apportioned (can't easily be divided)
-constraints
-assumptions
-misunderstandings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Milestone List

A
lists essential and optional milestones
includes
-ID # for tracking
-what milestone triggers
-when milestone anticipated
-associated activity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule Dependency types

A

Mandatory- inherent, often physical
Discretionary- based on preference
External- between internal and external activities
Internal- between activities, within team’s control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Precedence Diagram Method

A

Id dependencies then put in a schedule

independent activities go under first

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Types of Precedence Dependencies

A

Finish- start: one action must end before next can start
S- S: one must start before next can start
F - F: activity must finish before another can finish
S-F: one activity must start before another can finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule Leads

A

the advance time an activity can be scheduled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Schedule Lags

A

time of delay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Project Schedule Network Diagram

A

critical output of sequencing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Tools and Techniques for Estimating Duration

A
Expert Judgement
Analogous estimating aka top down estimating
Decision Making (ex: fist of five)
Meetings
Data Analysis
Parametric Estimating
3 point estimating
bottom up estimating
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Parametric Estimating for schedule

A

(quantity of work x productivity rate) / resources = duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly