Managing the Project Schedule Flashcards
1
Q
Tools and Techniques of Managing a Project Schedule
A
Data Analysis (EVA) Critical Path Progress PMIS Resource Optimization Leads/Lags Schedule Compression
2
Q
Earned Value Analysis (EVA) for scheduling
A
determine if there is schedule variance
SV = EV - PV
negative SV = activity behind schedule