Performing a Critical Path Analysis Flashcards

1
Q

Elements of Schedule

A

Activity, name, duration, start/finish date, resources, time frame phases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Tools and Techniques of Schedule Development

A
Resource Optimization (leveling, smoothing)
Data Analysis
Schedule Network Analysis
PMIS
Agile Release Planning
Leads/Lags
Schedule Compression
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Resource Optimization

A

adjust resources to optimize
use when resources are overallocated, limited availability
ex: leveling, smoothing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Leveling

A

Resource Optimization technique for scheduling

move resources from non-critical to critical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Smoothing

A

Resource Optimization technique for scheduling
Delaying start of a non-critical activity
Duration of activity doesn’t change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Critical Path

A

minimal total project duration based on critical activities

shortest time in which a project can be completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Critical Chain Method

A

add buffers
feeding buffer- on non-critical
padding buffer- on critical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Forward Pass

A

Method to calculate critical path
early start & early finish
earliest possible date and duration
subtract a day

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Types of Schedule Compression

A

crashing- shortening duration of activities usually by adding resources
fast tracking- performing activities in parallel, may increase risk, only if activities can overlap

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Free Float

A

how long you can delay an activity without delaying the next activity.
No total float means no free float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Total float

A

how long can be delayed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly