Planning and Managing Project Budget Flashcards

1
Q

Tools and Techniques for Estimating project cost

A
Analogous estimates - look at previous
Bottom-up estimating- determine at lowest level
Parametric Estimating- 
3 Part Estimating- takes risk factors into account
Expert Judgement
Data Analysis
PMIS
Decision Making Techniques
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Bottom Up Estimates

A

determine cost at lowest level and roll up
Use work breakdown structure
materials, labor, and contingency = total for workpackage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost aggregation

A

like bottoms up analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Reserve Analysis

A

Data Analysis for Estimating project cost
contingency reserves
management reserves

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Tools & Techniques for Cost Control

A

Expert Judgement
Data Analysis- Reserve analysis, variance, trend analysis, earned value analysis
To-Complete Performance Index
PMIS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Reserve Analysis

A

Determine if reserves are good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Variance Analysis

A

actual vs planned performance (cost and schedule)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Trend Analysis

A

project performance over time, improving or declining

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Earned Value Analysis

A

scope, cost, schedule

compare actual vs baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

To-Complete Performance Index (TCPI)

A

work left / money left

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cost Variance (CV)

A
PV= planned value- value of work planned for now
EV= earned value
AC= actual cost - total incurred up to date
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To-Complete Performance Index (TCPI)

A

work left / money left
what cost performance needs to be to complete on goal
TCPI >1 performance need to be better than planned to meet goal
if TCPI > CPI need to improve
TCPI= (BAC-EV) / (BAC-AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Estimated at Completion (EAC)

A

forecasting, estimate to complete project based on cost so far

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Cost Performance Index (CPI)

A

CPI > 1 = project earning more than has been spent

CPI = EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Estimated at Completion (EAC)

A

forecasting, estimate to complete project based on cost so far
ID areas with higher cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Bottom Up Estimate at Completion

A

EAC = AC + ETC

most common method to calculate EAC

17
Q

EAC based on Budget VAlue

A

if cost is not going to change

AC + BAC - EV

18
Q

EAC based on CPI

A

if basing on cost so far

BAC / cummulative CPI

19
Q

EAC based on CPI

A

if basing on cost so far

BAC / cumulative CPI

20
Q

EAC based on CPI and SPI

A

EAC = [(BAC-EV) / (CPI x SPI)] + AC

use if timeline is firm

21
Q

Planned Value (PV)

A

authorized budget for work
= BAC x % of time passed
assumes the flow is equal throughout

22
Q

Earned Value (EV)

A

budget for work complete

= BAC x % completed

23
Q

Schedule Variance (SV)

A

difference of actual from plan
SV = EV - PV
positive variance means ahead of schedule

24
Q

Schedule Performance Index (SPI)

A

= EV / PV
SPI > 1 means project is ahead of schedule
SPI of 1.20 = 20% ahead of schedule

25
Q

Cost Variance (CV)

A

CV = EV - AC

positive variance means ahead of schedule

26
Q

Cost Performance Index (CPI)

A

CPI = EV / AC
CPI > 1 means under budget
CPI of 1.07= for every $1 spent, get $1.07 value