Part 43 Contract Modifications Flashcards

1
Q

What is a unilateral modification?

A

Signed just by the CO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is a unilateral modification appropriate?

A

administrative changes, issue change orders, issue other changes authorized by contract clauses other than changes clause.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a bilateral modifications?

A

SIgned by both parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When is a bilateral modification appropriate?

A

Negotiate Equitable adjustments, definitize letter contracts, reflect other agreeements of the parties that change the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Changes clause for fixed price allows what?

A

changes within scope to be done unilaterally.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What happens if CO issues a change order?

A

contractor may request an equitable adjustment to Cost, profit/fee, and delivery schedule, or both.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When is notification of changes clause appropriate?

A

clause used in contract over $1M

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

WHat does the Notification of Changes clause state?

A

KTR must notify CO within a specified number of days if he believes the contract has been changed without direction from the O>

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What must CO do if notified by KTR under Notification of Changes clause?

A

CO must respond within specified number of days with on of the following:
Confirm the change and direct KTR to continue and arrange for funding
Countermand any communication regarded as a change
Deny that change has occurred and direct KTR to continue performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What must a KTR do with requesting an Equitable Adjustment?

A

KTR must provide information supporting REA (Rationale and data)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What happens if the REA is > SAT?

A

KTR must certify the REA is made in good faith, accurate, and complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When is Release of Claims Language required?

A

in all modifications that definitze change orders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What can you change for supplies in the changes clause?

A

Change in drawings, designs, and specs
Change method of shipment/packing
Change palce of delivery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What can you change for services in the changes clause?

A

Change in description of service
Change time of performance
Change place of performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly