Part 36 Construction Contracting Flashcards

1
Q

What are the two different acquisition approaches for construction?

A

Design-build and Design-bid-build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Design build?

A

One contract for one contractor to design and build to that design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Design-bid-build?

A

2 contracts to two different contractors; one for design and 1 for build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When is past performance evaluations required in construction?

A

at $700K

Any construction contract terminated for default

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of past performance evaluations in construction?

A

Evaluate contractor performance

Used for past performance evaluations in future competitions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When is Differing Site Conditions required?

A

Contracts that exceed SAT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does Differing Site Conditions allow?

A

allows KTR to submit REA under site subsurface or latent conditions different from those specified or site conditions are both unknown and unusual in nature

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When should you use the Site Vist clause?

A

with Differing Site Conditions and Site Investigations and conditions affecting the Work clauses are used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When do you use “USe and Possesion prior to Completion”

A

Required over SAT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What does Use of Possesion Prior to Completion allow?

A

Allows Gov to use a site before the contractor completes work and before the government accepts works. If impacted, the KTR has right to submit REA.