What are some functions of an ACO?

A

Conducts Pre-award surveys
Establishes indirect rate agreements or recommendations
Reviews KTR financing vouchers
Provides pre-acceptance quality assurance
Performs acceptance when at origin
Monitors government furnished property

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is secondary delegation appropriate?

A

when significant portions of effort are subcontracted and performed at another location. Primary ACO delegates authority over performance at that location to an ACO.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When is retention of ACO funcitions appropriate?

A

For operational contracting and other contracts that are performed on-site
Shall not retain contract administrative functions that are to be performed at the contractor facilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When is Suspension of Work used?

A

for Construction contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does Suspension of Work allow?

A

Allows CO to unilaterally suspend for reasonable period. THe KTR entitled to equitable adjustment if CO action results in additional costs and schedule as appropriate (Cost only…not profit or fee)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When are Stop WOrk Orders appropriate?

A

Supply or sevice Contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does Stop Work Orders allow?

A

Allows CO to unilaterally stop all or any part of work for up to 90 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Can stop work order be extended?

A

Yes, but bilaterally. KTR tentitled to equitable adjustment if CO action results in additional costs and schedule as appropriate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What happens within the 90 days of a Stop Work Oder?

A

Cancel the Stop work order or Terminate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When is Government Delay of Work apporpraite?

A

For supply and Service Contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Government Delay of Work allow?

A

Allows KTR the right to submit an REA in other situations where CO action/inaction causes delay.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What system is used to evaluate contractor performance?

A

Contractor Performance Assessment Reporting System (CPARS) and it’s used to assess KTRs past performance for future acquisitions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When should CPARS be completed?

A

Each year of contract performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When is CPARS required?

A

$5M for systems or Operations
$1M for services
$700K for construction