Part 15.4 Contract Pricing Flashcards

1
Q

Price Analysis

A

ALWAYS USE; Evaluate the proposed total price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Cost Analysis

A

Shall be used to evaluate cost elements when CCOPD is required and can perform for “other than certified”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Price Analysis Techniques

A

Adequate Price Competition
Comparison to historical prices: prior price must be valid, consider factors (qty, time frame, extent of competition, market conditions, similarity)
Comparison with published prices
Comparison to IGE
Comparison to MR for same or similar items
Parametric Analysis
Analysis of other than cost or pricing data provided by the offeror

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is CCOPD

A

Factual data that a reasonable person would expect to significantly affect the price negotiated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When is CCOPD required

A

Over $2M

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Exceptions to CCOPD

A

Adequate Price Comp, Prices set by law or regulation, commercial item, cost or pricing data is waived

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Examples of CCOPD

A

Materials, Labor, Indirect Labor, G&A, Overhead, and Profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Other Than CCOPD

A

Pricing data, cost data, and judgmental information necessary for the CO to determine the price fair and reasonable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Certificate for CCOPD

A

Certifcate must cite 15.406-2 language exactly; include 2 dates. 1st date - date signed and sent to gov. 2nd date - Date which it was certified current, accurate, and complete (either negotiations completed or agreement of the parties).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Data Sweep

A

between 2 dates to ensure information is current, accurate, and complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Pricing threshold

A

AFLCMC: %25M

AFSC and AFNWC: $10M

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Defective Pricing

A

Contractor did not submit or disclose data that was not current, accurate, or complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Weighted Guidelines ELements

A

Performance Risk, COntract Type Risk, Facilities Capital employed, and cost efficiency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly