1
Q
- LOT 203.07 DWS*
- *
What will auto start/stop the DWS Transfer pumps?
A
- Auto Start:*
- *Lead Pump: DWS Header Pressure 97.5 psig**
- *Lag Pump: DWS Header Pressure 93 psig**
- Auto Stop:*
- *Lead Pump: DWS Header Pressure 128 psig**
- *Lag Pump: DWS Header Pressure 125 psig**
- Placing switch in “MAIN” will start pump if DWST Level > 2.75’
- DWST Level > 2.75’ is a pump permissive for ALL pump starts.
- Note:*
- System has 3 transfer pumps*
2
Q
- LOT 203.07 DWS*
- *
What alarms are available in the MCR for the DWS?
A
Pump Trouble on CP009
- Loss of control power
- Thermal overload
3
Q
- LOT 203.07 DWS*
- *
What is the usable capacity of the DWST?
A
961,700 gal
Enough capacity to supply both units for 2 days
4
Q
- LOT 203.07 DWS*
- *
How do we control corrosion in the DWST?
A
Plastite is bonded to metal of the tank
N2 blanket