The series of phases that a project passes through from its start to its completion is called _________
Project life cycle 1.2.4.1
A collection of logically related project activities that culminate in the completion of one or more deliverables is called ___________________
Project phase 1.2.4.2
A systematic series of activities directed toward causing an end result where one or more inputs will be acted upon to create one or more outputs is called __________
Project management processes 1.2.4.4
An identified area of project management defined by it’s knowledge requirements and described in terms of its component processes, practices, inputs, outputs, tools and technique is called ______________
Project Management Knowledge Area 1.2.4.6
Project Integration - Monitor & Control Project Work - T&T
FMEA - Stands for what…..and 3 analysis
Failure Mode & Effect Analysis
Regression Analysis
Fault Tree Analysis
Grouping Methods
Definition of Transformational Leader
Empowering followers through idealized attitudes and behaviors, inspirational motivation, encouragement for innovation and creativity an individual consideration.
Definition of Transactional Leader
focus on goals, feedback, and accomplishments to determine rewards, management by exception
What are components of the project’s final report?
Summary level description of each phase of the project.
Summary of the validation information for the final project deliverables.
The cost of running a project management office is an example of what type of cost
Indirect.
Not directly traced to specific project.
What is valuable inputs to the Plan Resource Management process.
Lessons learned
Which processes gives the project management team insights into the health of the project
Monitor and Control Project Work
This is the process for collecting, measuring, and disseminating performance information and for assessing measurements and trends to effect process improvements.
If the cost variations observed to date are NOT EXPECTED to continue going forward, we would use what EAC formula?
EAC = AC + BAC – EV
Quality audits are performed during what process?
Manage Quality process.
If you are planning to eliminate the impact of a particular risk, you are using what risk response?
AVOIDANCE
The Define Scope process will result in development of what……..
Project Scope statement
Updates to project documents such as
stakeholder register
requirements documentation and
requirements traceability matrix.