Chapter Seven | Cost Management Flashcards
What does AC stand for and the interpretation
Actual cost
As of today, what is the actual cost incurred for the work completed?
What does AT stand for and def
Actual time
Actual time used to complete an activity
What does BAC stand for And what is the interpretation?
Budget at completion
How much did we budget for the total project effort?
What does COQ stand for
Cost of quality
What does CPI stand for
Cost performance index
What does CV stand for
Cost variance
What does EAC stand for
Estimate at completion
What does ES stand for and def
Earned schedule
Time allotted to complete an activity
What does ETC stand for, def and formula
Estimate to complete
Represents the funds needed to finish the project based on the current spending efficiency of the project
ETC= EAC - AC
What does EVA stand for and def
Earned value analysis
Compares the performance measurement baseline to the actual schedule and cost performances
A snapshot in time
What does EVM stand for and def
Earned value management
Identifies and monitors key dimensions for each work package, control account, or total project budget BAC
What does IRR stand for
Internal rate of return
What does NPV stand for
Net present value
What does PERT stand for
Program evaluation and review technique
What does PMB stand for
Performance measurement baseline
What does PV stand for and interpretation
Planned value
As of today, but is there estimated value of the work planned, what “should” be done?
What does ROM stand for
Rough order of magnitude
What does SPI stand for
Schedule performance index
What does SV stand for
Schedule variance
What does TCPI stand for and def
To complete performance index
How to finish project on original budget
What does VAC stand for, def and formula
Variance at completion
The difference between the original budget at completion and the estimate at completion
This tells us how much the completed project was over or under budget
VAC= BAC - EAC
What is project cost management?
The process involved in planning estimating budgeting financing funding managing and controlling costs so the project can be completed within the approved budget
Once you pass the project on to where it will live
the impact on the budget of the department you pass this back to Is called what?
Life cycle costing
What needs to be considered and tailoring a project cost plan? 5
Knowledge management
estimating and budgeting
earned value management
use of agile approach
governance
Agile| Detailed estimates are only used for a what?
Short term planning in a just in time style
7.1. Plan cost management
What does this mean and what is the benefit?
The process of defining HOW the project cost will be estimated budget and managed monitored and controlled.
The key benefit is that it provides guidance and direction on how the project costs will be managed throughout the project
This is for the team
7.1. Cost can be either ________ or _________
Variable costs or fixed costs