Contract Practice L1 Flashcards
What contracts are you aware of?
- JCT Suite of Contracts
- New Engineering Contract (NEC) use option 4.
- FIDIC Contract
What do you know of NEC Contracts available?
NEC4 provides option clauses which shifts the risk between parties. It has options A-F
A: Lump Sum with activity schedule
B: Lump Sum with Bill of Quantities
C: Target Contract with Activity Schedule
D: Target Contract with Bill of Quantities
E: Cost reimbursable
F: Management Contract
What is Target Cost?
Shares the cost of the project, if over the budget split pain between parties, if under share gain. Cost based on base cost, OH&P, risk allowance.
Allows works to occur quicker and contingency allocation of risk by contractor less.
What warranties have you issued? What is the purpose?
Warranties may be used to provide assurance from one party to another that goods and/or services will meet certain expectations, e.g. fit for purpose, being free from defects, complying with statutory and other regulations and specifications.
What collateral warranties have you issued? What is the purpose?
Collateral warranties create direct contractual relationships between parties that would not otherwise exist.
What Novation’s have you issued? What is the purpose?
A three-way contract which extinguishes a contract and replaces it with another contract in which a third party takes up the rights and obligations which duplicate those of one of the original parties to the agreement.
What is a sub-consultant agreement?
Given the increasing complexity of many construction projects it is becoming more common that a consultant appointed on a project, will in turn themselves appoint consultants to undertake some or all of the work for which they have been engaged.
What are the differences between procurement routes?
Management = employer wants contractor to employ sub contractors
Traditional = Primary bits of work completed by contractor
Design and Build Contract = Design of works completed by Contractor
What is the purpose of having a standard form of contract?
- Avoid disputes
- Industry standard
- Defines fee and payment
- Establishes risk
- Clarity, comfort and protection as used before
- Aligned with current legislation.
What would you do if a contractor went into administration?
- Be informed asap in writing
- Terminate contract between parties.
- Obligations of works and payment suspended.
- Secure site