Contract Practice L1 Flashcards

1
Q

What contracts are you aware of?

A
  • JCT Suite of Contracts
  • New Engineering Contract (NEC) use option 4.
  • FIDIC Contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What do you know of NEC Contracts available?

A

NEC4 provides option clauses which shifts the risk between parties. It has options A-F
A: Lump Sum with activity schedule
B: Lump Sum with Bill of Quantities
C: Target Contract with Activity Schedule
D: Target Contract with Bill of Quantities
E: Cost reimbursable
F: Management Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Target Cost?

A

Shares the cost of the project, if over the budget split pain between parties, if under share gain. Cost based on base cost, OH&P, risk allowance.

Allows works to occur quicker and contingency allocation of risk by contractor less.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What warranties have you issued? What is the purpose?

A

Warranties may be used to provide assurance from one party to another that goods and/or services will meet certain expectations, e.g. fit for purpose, being free from defects, complying with statutory and other regulations and specifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What collateral warranties have you issued? What is the purpose?

A

Collateral warranties create direct contractual relationships between parties that would not otherwise exist.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What Novation’s have you issued? What is the purpose?

A

A three-way contract which extinguishes a contract and replaces it with another contract in which a third party takes up the rights and obligations which duplicate those of one of the original parties to the agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a sub-consultant agreement?

A

Given the increasing complexity of many construction projects it is becoming more common that a consultant appointed on a project, will in turn themselves appoint consultants to undertake some or all of the work for which they have been engaged.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the differences between procurement routes?

A

Management = employer wants contractor to employ sub contractors
Traditional = Primary bits of work completed by contractor
Design and Build Contract = Design of works completed by Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of having a standard form of contract?

A
  • Avoid disputes
  • Industry standard
  • Defines fee and payment
  • Establishes risk
  • Clarity, comfort and protection as used before
  • Aligned with current legislation.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What would you do if a contractor went into administration?

A
  • Be informed asap in writing
  • Terminate contract between parties.
  • Obligations of works and payment suspended.
  • Secure site
How well did you know this?
1
Not at all
2
3
4
5
Perfectly