Asbestos L3 Flashcards

1
Q

What is the 4 stage asbestos procedure?

A

Under Regulation 17 of the CoAR requires cleanliness of the premises.

  • Preliminary check of site & job = establishing scope removed alongside contaminated items.
  • Visual inspection of enclosure/work = check inside enclosure that all surfaces are clean of dust.
  • Air monitoring = Test & analyse for asbestos fibres in the air, brushing areas to disturb dust.
  • Final assessment = checking the enclosure as taken down for materials.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who signs of the asbestos removal?

A

The asbestos specialist following 4-stage removal and providing the certificate of reoccupation complying with section 20 of CoAR.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What asbestos was present on the AIB?

A

Noted chrysolite (white) and amosite (brown) where present.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why do you need a Refurbishment & Demolition Survey?

A

Under Regulation 5 of the CoAR requires the identification of asbestos by the employer before the works start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When working with asbestos, what should be done?

A

Under Regulation 7 of the CoAR requires plan of works to be done prior to commencing work through the RAMS, identifying the control areas of the exposure unit and removing it from site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is asbestos removed from site?

A

Under Regulation 24 of the CoAR requires all items correctly bagged and disposed of with regulated sites and sealed skips. They also use an airlock system and

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who can remove asbestos?

A

A licensed asbestos specialist contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How would you know if works require a licence with asbestos? What form is submitted for each?

A

I would refer to Regulation 2 of the CoAR. This will define if the works are licensable works ASB5 form for 14 days or if notifiable non-licensed works NNLW1 form with no minimum notice period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly