Case Study APC Flashcards

1
Q

Working on adjoining properties did you consider any other factors?

A
  • Party wall, although this was not applicable as there was no works to either unit 6 or 3. The client was also the landlord for these premises.
  • Notice period for the installation of the rear fire escape.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the role of a contract administrator?

A
  • Manage the contractor from a non-influenced stand point, working for the contract alone and taking a non-biased approach.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the role of a Principal Designer?

A
  • To take the lead in planning, managing, monitoring and coordinating health and safety during pre-construction phase. It is a statutory role under the CDM Regulations 2015.
  • Collate pre-construction information, providing information so other roles can work safely.
  • Eliminate foreseeable risk through design.
  • Complete stakeholder communication; both the client and contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Was the project notifiable?

A
  • Yes, as it exceeded both 500 person days on site or 30 days with 20 people or more on site. It was notified through HSE.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How did you make the property more sustainable?

A

I specified both new roof replacement, which has a u-value under 0.16, new windows with a minimum requirement of 1.6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What did you specify for the roof?

A
  • I specified a profiled metal roofing sheet to achieve a 0.16 u-value and 20% roof lights, this element was design specific to the contractor and to achieve a fall safe system with a fall arrest system.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Did you need planning for the new roof?

A
  • The Town and Country Planning Act 1990 stated that the development does not require planning as material change is not occurring to the external envelope, as we are just replacing for a built up insulated profiled metal roof sheet for an improvement.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Did you consult any statutory authorities?

A
  • I consulted with an Approved Inspector throughout, ensuring plan check, visits, and final certification was achieved.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the difference between a Building Control Officer and an Approved Inspector?

A
  • A Building Control Officer works for the Local Authority.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How did you budget the project under £600,000?

A
  • I used BCIS for cost information in relation to the refurbishment of elements, reviewing the Tender Price Indices (TPI) which allows for tender inflation.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How did you write the specification?

A
  • I completed a prescriptive tender specification which included the project preliminaries, work sections and schedules using National Building Specification Uniclass.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Why did you write a prescriptive tender?

A
  • The tender was based on previous units recently refurbished in the local units. Therefore the client wanted to remain in control of the design with visuals, not allowing the contractor to specify there choice as what has worked before has been useful.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

You mentioned you used Contractors Design, how did you consider what would be the Contractors design portion?

A
  • We decided to include the design of the mechanical and electrical portions, as well as a fire alarm L1 system. I proceeded with this as it allowed the contract to be let to the contractor and designs could be developed without further delay. I prescribed the requirement of output of the Lux level to achieve 300 LUX.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How did you select the contractors for tender?

A
  • I used the contractors known from our experience working with them, alongside those that are included on the Canal & River Trust framework.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What tendering procedure did you use?

A
  • A single stage tendering procedure was used instead of either a negotiated contract as the client wanted a competitive price and two stage, as the contractors had previously confirmed insurances and experience to the canal and river trust to be included on their framework.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What pricing document did you produce?

A
  • I completed a schedule of works, accompanied by a drawing which reflected the requirements within the specification.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How did you proceed with the tender process?

A
  • I completed the tender documents, inviting the contractors to tender and ensuring they can complete the desired works with resource for the requested programme. I carried out a tender addendum following issuing for 3 week period. I received the tenders after a tender opening so everything is transparent with the client which recorded programme, time of offer and sum.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What do you check during the tender report?

A
  • Ensuring that no errors, unreasonable qualifications, or conflict of interest with sub-contractors. I ensure that no errors are in the tender, reviewing submitted costs on average to make any of the contractors aware of disparity.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Why did you choose the procurement route?

A
  • The client remained in control of the design and received a lump sum cost from the contractor.
20
Q

Why did you choose the Intermediate Building Contract?

A
  • Involved normal and recognised trades and skills within the industry, complexity was not too confusing.
21
Q

You mentioned Fluctuations, how would you implement this?

A
  • I reviewed the three options in an intermediate contract: contribution, levy and tax (tax increases, NI and other statutory increases), OR Labour and materials (materials increasing from the base date), OR Formula adjustment (hybrid of the above). I would use labour and materials one alone within the contact if proceeded.
  • It would require the involvement of the QS as understanding my competency on the fluctuation provision and reviewing the costs would be out of my remit.
  • I would require a cost from the contractor at the start with the rates they are working too. This is in relation to the roofing element only.
  • I would use the Resource Cost Indices (RCI) to measure the changes within the BCIS.
22
Q

What other ways could you manage with the contractor for cost increases?

A
  • A reimbursable cost may have been used, however the client preferred use of the JCT contract suite rather then using a NEC3 contract, where I understand Option E is available.
23
Q

What is a provisional sum?

A
  • A provisional sum is an allowance of an actual estimate for cost of specific works not able to be defined yet. This may be defined where the contactor includes this inside the prelims, undefined is not.
24
Q

What is the difference between a PS and Prime Cost?

A
  • A PC sum is the client making a provisional sum and asking the contractor to add their overheads and profits.
25
Q

What is asbestos and main ones?

A
  • There are 3 different asbestos: blue (crocidolite (crow-sid-a-light)) 1985 ban, brown (amosite) 1985 ban, white (chrysolite - (chrys-o-tile)) 1999 ban. It is able to be found in flooring, roofing, insulation to 2000.
26
Q

What are the duties and regulations for asbestos requirement?

A
  • Under regulation 4 it requires the person who is either the owner, maintenance responsible person, or repair through lease. Typically this falls to the leaseholder.
  • The duty must be taken responsibility of identifying asbestos, presuming any material may have it, record location and location/condition of the asbestos, assess the risk of exposure, prepare management plan, take necessary action steps, keep reviewing and provide management plan to others.
27
Q

How do you ensure the asbestos has been cleared?

A
  • The asbestos company shall carry out a preliminary check of the site, then visual inspection of the enclosure/work area, then do a air monitoring check to ensure no more dust is present. Removal of the enclosure can then be done and certification provided.
28
Q

What makes asbestos works licensable?

A
  • It is dependent on high risk elements, in this case – it was high risk as insulating board to remove.
29
Q

How do you go about requesting a license for removing the asbestos?

A
  • You apply to the HSE using the ASB5 Form for 14 days before at a minimum.
30
Q

What is a Refurbishment and Demolition Survey?

A
  • The refurbishment and demolition survey is required to any property before works proceed to any building prior to 2000 constructed without a management plan to identify asbestos and comply with regulation 5 of CoAR 2012 regulation to remove ACMs.
31
Q

What other asbestos surveys are you are aware off?

A
  • A management survey is required by the duty holder to manage ACM to ensure nobody is harmed, asbestos remains in good condition and it is not disturbed.
32
Q

How is asbestos removed from site?

A
  • By a notifiable licensed contractor where bagged up correctly, inclusive of all overalls and masks, then held in a lockable skip for removal.
33
Q

What is the HSE?

A
  • They are the national regulator for workplace health and safety. Protect work related deaths, ill health and injury.
34
Q

What is asbestos encapsulation?

A
  • Encapsulation is containing the asbestos behind a protective layer and requires the asbestos to be sound condition. You can encapsulate with rigid boards, paint, spray coatings or cloth wrap.
35
Q

Can you name any other deleterious materials you may come across?

A
  • Woodwool slabs, used as shuttering and may result in reduced fire resistance, reinforcement corrosion, and loss of structural strength,.
  • Brick slips, lack of poor adhesion and the lack of soft joints can cause delamination.
  • Lead – Inhale and ingestion poor. To be picked up in surveys prior in paint and pipework. Lead regulations to be defined.
  • MMMF (Machine Made Mineral Fibres), Where fibres under 3 microns or less.
  • Japanese Knotweed – Use RICS guidance note 2022 to acquire guidance, although aware that a guided management plan is provided to either remove or manage it on and off site in relation to the extent of damage.
36
Q

You mention value engineering, how would you carry out this exercise?

A
  • Identify the product, analyse function of those elements, developing alternative solutions, assess these with costs and performance, choose the likely success.
37
Q

Why was the fire escape route not thought of in first instance?

A
  • Originally the client was wishing to have raised level access to each unit door, now as this wasn’t required, I decided to omit this for flat surface instead.
38
Q

What is value?

A
  • Value can be up to interpretation: efficiency, cost, structural, life expectancy.
39
Q

What did you consider with the other options with regards to defects?

A
  • The concrete could suffer from cracking, spalling, crazing, efflorescence.
  • The asphalt could have cracking, crazing and lifting in areas from tree routes.
40
Q

What is critical path in construction?

A
  • The critical path method of a project scheduling that breaks down activities to calculate the duration required to complete each item, sequential.
41
Q

How did you review the Contractors Design Portion on receiving tenders?

A

The CDP was to have the contractors say they shall comply with the performance of designing a L1 system fire alarm.

42
Q

Why did you choose to use the Contractors Design Portion on the project?

A

This is due to me not being a specialist in fire compliance with the systems to design, so I specified a performance specification of a L1 system, providing Automatic Fire Detection (AFD) to be installed into all areas of a building. The Contractor was then to design compliance with this and provide a design certificate noting compliance. This was further provided to the Approved Inspector who consulted with Local Fire Authority.

43
Q

This project was completed under the previous ethical standards, what were they?

A
  • Integrity
  • High Level of Service
  • Promote trust in the profession
  • Treat others with respect
  • Take responsibility
44
Q

Did you get a guarantee on the roof?

A

Yes, a insurance backed guarantee so even if the contractor went into administration they were protected. Not just a product guarantee.

45
Q

What defects period did you have on the project?

A

12 months, due to the nature of the works with the roof, if cosmetic it would have only been 6 months.

46
Q

Did you have other options to consider with the roof in terms of making it water tight?

A
  • Repairing leaks
  • Replacing roof lights
  • Over clad (economical, less disturbance, quicker BUT not achieve u-value)
  • Full replacement (New roof so guarantee, BUT slower refurbishment and more expensive.)