AP-31 (rapid cnmt entry) Flashcards

1
Q

AP-31

Who (in lue of RP managment) is authorized to issue a LHRA key?

VHRA key?

A

SFM or SM

SM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

AP-31

Describe the following using ; plant conditions, rad conditions, location entered, existing survey

Condition A

Condition B

Condition C

A

A - plant & rad condtions stable, entry not in LHRA or VHRA

B - plant & rad condtions stable, entry into LHRA or VHRA, rad condtions well documented

C - plant & rad condtions not stable or unknown

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AP-31

When making a rapid cnmt entry and entry into a LHRA/ VHRA is required, where are you still prohibited to go?

A
  • under Rx Vessel
  • refueling cavity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly