AP-17 Flashcards
1
Q
AP-17
What are the different sections to Loss of Charging?
A
A - loss of all charging
B - charging equip malfunction
C - charging leak (at power)
D - charging leak (on RHR)
2
Q
AP-17
When in section A of loss of charging what condtions will have you trip Rx?
are there any “extra” actions that must be taken in these circumstances?
A
Loss of Thermal Barrier cooling to RCP’s and cant be immediatly restored
- trip RCP’s
- isolate seal inj to RCPs (before restart CCP)
- close FCV-357 (CCW return isolation)
During ramp to inject SI pumps, Lpzr cannot be maintained > 17%
- nothing extra
3
Q
AP-17
During a loss of all charging, what is the main success path if a CCP cannot be restored?
A
- Ramp unit
- cool down
- depressurize
- use SI pump to inject and control Lpzr
4
Q
AP-17
When are you directed to AP-1 while progressing through Charging line leak (section B)
A
- Once you isolate letdown and charging and Lpzr is still lowering