9 estimation methods Flashcards
what are the 5 estimation methods?
1 global/ approximate 2 factorial 3 labour-hours 4 unit rate 5 operational
What is the project data required for global method?
1 size
2 location
3 completion date
What is the project data required for factorial method?
1 main items
2 location
3 completion date
What is the project data required for labour-hour method?
1 quantities 2 location 3 key dates 4 simple method statement 5 completion date
What is the project data required for unit-rate method?
1 bill of quantities
2 location
3 completion date
What is the project data required for operational method?
1 material quantities 2 method statements 3 programme 4 key dates 5 completion date
What is the cost data required for global method?
1 overall cost of similar projects
2 inflation indices
3 inflation forecasts
What is the cost data required for factorial method?
1 factorial estimating system
2 quotes for main plant items
3 inflation forecasts
4 ancillary item factors
What is the cost data required for labour-hours method?
1 hourly rates 2 productivity 3 overheads 4 material cost 5 hourly rate forecasts 6 material cost forecasts 7 plant data
What is the cost data required for unit-rate method?
1 historical unit rates for similar work
2 preliminaries
3 inflation indices
4 inflation forecasts
What is the cost data required for operational method?
1 labour rates and productiveness 2 plant cost and productiveness 3 material costs 4 overhead costs 5 material costs forecasts 6 plant capital operating cost forecasts
What are the issues associated with global estimating?
1 may not include all fees ie final account sums, D&E fees, finance costs, land
2 difficult to define capacity and trend may not be linear
3 may not be comparing like with like ie different land conditions, different standards of quality ie motorway to minor road
4 reliability of data source
What are the issues associated with factorial estimating?
1 reliability of the factors - need to be built up by experience
2 changes to the design change the factors
3 reliability of the price of equipment
4 adjustment for inflation needed
What are the issues associated with labour-hours estimating?
1 it assumes that most operations do not vary in their method for different projects
2 allowances are made for materials costs therefore as less applicable for projects where there is a high material element
Where do the unit rates come from?
1 historical rates based on productivity rates for similar projects
2 rates based on data given in price books
3 rates built- up from an analysis of labour, plant and materials for each item and costed at current rates
4 taken from estimators personal manual
What are the issues associated with unit-rates estimating?
1 There are hidden costs such as storage and facilities for workers that are not included
2 It assumes that materials can be unloaded as soon as they arrive, at the place they are needed
3 no account for how many staff members there are to do the task
4 there might be travel time needed during the activity
5 there might be similar materials that slow down the output rate
6 no account for plant idleness
7 assumes resources will always be available
What are the advantages of the operational method?
1 accounts for idle time
2 allows for operations where there is significant uncertainties and risks, as it shows the basic sources of costs and not the cost derived from an output.
3 the programme helps identify sources and risks of delay
4 will eventually accumulate a library of operational data
What influences the accuracy of a cost estimate?
1 The accurancy of the cost model
2 Accuracy of the data fed into it
3 number of items it contains
What are the main disadvantages of the operation model?
1 It does not allow direct entry of overheads
2 it is time consuming
Give an example of when a global estimation would be used?
a new school
Give an example of when a factorial estimation would be used?
a chemical plant
Give an example of when a labour-hours estimation would be used?
electrical installation
Give an example of when a unit-rate estimation would be used?
road
Give an example of when a operational estimation would be used?
pouring concrete