10 further issues in estimating Flashcards
1
Q
What should be included in the contractors estimation to their senior management in order for them to convert to a tender bid?
A
1 project description 2 general method statement 3 risks not covered by BoQ 4 unresolved contractual issues 5 financial consequences of the design process 6 assumptions used for direct cost estimates 7 profitability 8 market + industrial conditions 9 direct costs, broken down 10 BoQ with direct costs
2
Q
What must senior management uplift the estimate to account for?
A
1 risk
2 overheads
3 profit
3
Q
example of a project where the design change led to it being massively over budget?
A
Senedd, welsh parliament- arguments between contractor and principle meant construction stop for 2 years, and final project nearly 6 times over budget and over 4 years late