6 process estimation Flashcards
1
Q
What can an estimate be used for?
A
1 comparing alternative technical solutions
2 identify financial commitment
3 as a basis for tendering
4 to measure performance against
2
Q
What factors affect the estimation process?
A
1 the type of project
2 the organisation doing the estimate
3 the stage of the project
3
Q
Why id the project cost underestimated in the initial stages?
A
1 optimism bias
2 insufficient adjustment - can not see problems in the future
3 over confidence in established probabilities
4
Q
Why does the cost of the project increase over time?
A
progressing through stages in the process - there is more information to make a more accurate estimation